Chill v. Kadean Construction Co.

716 S.W.2d 860, 1986 Mo. App. LEXIS 4656
CourtMissouri Court of Appeals
DecidedSeptember 9, 1986
DocketNo. 51085
StatusPublished
Cited by2 cases

This text of 716 S.W.2d 860 (Chill v. Kadean Construction Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chill v. Kadean Construction Co., 716 S.W.2d 860, 1986 Mo. App. LEXIS 4656 (Mo. Ct. App. 1986).

Opinion

CRIST, Judge.

Defendant-builder appeals from $1,000 judgment awarded at trial de novo in circuit court. Action, originally brought in small claims court, was for damages from alleged negligent construction of concrete patio at plaintiffs’ home. Plaintiffs-homeowners obtained judgment in small claims court and again at trial de novo. We affirm.

In its first point relied on, builder alleges error in the procedures employed at the trial de novo: failure to follow the rules of evidence, admission of hearsay declarations, and denial of a request for findings of fact and conclusions of law. As authority for this point, builder cites Section 512.310, RSMo (1978); and State ex rel. Dover v. Lewis, 666 S.W.2d 35 (Mo.App.1984). These authorities do support builder in that “[t]he trial de novo shall be governed by the practice in trials before circuit judges,” Section 512.310, RSMo (1978); however, builder has failed to preserve the point for review. Builder does not, in the point relied on or the corresponding argument section, indicate the specific actions or rulings it is seeking review of and wherein and why they are erroneous. The less than one page “argument” refers neither to the facts nor the record on appeal; rather it is a short discussion of the requirement for circuit court procedures at a trial de novo. Likewise, builder does not discuss the issue of a court’s refusal to make findings of fact and conclusions of law after a general request for such. Thus, we find nothing in builder’s first point to review. Rule 84.04(d); Thummel v. King, 570 S.W.2d 679 (Mo. banc 1978).

Builder’s second point relied on deals with unsworn testimony given by plaintiffs. Homeowners appeared pro se and the judge conducted a direct examination of them. Builder’s attorney did not object to the testimony until cross-examination. The circuit court admitted its error [861]*861and had homeowners sworn as to both the testimony already given and the testimony to be given. Builder did not object to the oath or to the continuation of the proceedings. While an oath administered in the middle of testimony is not ideal, this oath sufficiently placed homeowners under the pains and penalties of perjury and insured the truthfulness of their testimony. Section 492.060, RSMo (1978); and State v. McClain, 541 S.W.2d 351, 356 [12] (Mo.App.1976).

Judgment affirmed.

DOWD, P.J., and REINHARD, J., concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bolin v. Hanton
924 S.W.2d 15 (Missouri Court of Appeals, 1996)
McCutcheon v. Cape Mobile Home Mart, Inc.
796 S.W.2d 901 (Missouri Court of Appeals, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
716 S.W.2d 860, 1986 Mo. App. LEXIS 4656, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chill-v-kadean-construction-co-moctapp-1986.