Chicago Title Insurance v. Sherred Village Associates

544 F. Supp. 320, 1982 U.S. Dist. LEXIS 12928
CourtDistrict Court, D. Maine
DecidedJune 14, 1982
DocketCiv. 76-56 P
StatusPublished
Cited by3 cases

This text of 544 F. Supp. 320 (Chicago Title Insurance v. Sherred Village Associates) is published on Counsel Stack Legal Research, covering District Court, D. Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chicago Title Insurance v. Sherred Village Associates, 544 F. Supp. 320, 1982 U.S. Dist. LEXIS 12928 (D. Me. 1982).

Opinion

OPINION AND ORDER OF THE COURT

GIGNOUX, Chief Judge.

This action, seeking a declaratory judgment on the respective priorities of a mechanic’s lien and a mortgage assigned to the Department of Housing and Urban Development (HUD), is before the Court for the second time, on a remand from the Supreme Court for reconsideration in light of that Court’s intervening decision in United States v. Kimbell Foods, Inc., 440 U.S. 715, 99 S.Ct. 1448, 59 L.Ed.2d 711 (1979). The Court concludes that state lien priority law is to be adopted as the federal rule of decision, and, accordingly, that the mechanic’s lien is superior to the mortgage in the present case.

I

FACTUAL SETTING

Sherred Corporation, as contractor for Sherred Village Associates (Sherred), the owner and developer of the Sherred Village moderate income housing project in Bath, Maine, entered a contract in 1971 with Hercoform Incorporated pursuant to which Hercoform, as prime subcontractor, agreed to provide and erect prefabricated housing units for the project. In 1972, Sherred obtained mortgage financing for the project from the New England Merchants National Bank, whose loan was insured by HUD under Section 236 of the National Housing Act, 12 U.S.C. § 1715z-l. A regulatory agreement between HUD and the developer was recorded along with the mortgage on the day the latter was executed. Chicago Title Insurance Company insured the developer’s title in the mortgaged property for the benefit of the Bank; among the risks insured against were liens superior to the mortgage.

Following completion of the project in 1973, Hercoform filed in the Sagadahoc County, Maine, Registry of Deeds a mechanic’s lien claim for $440,986.03 in assertedly unpaid bills on the project. On the day the lien was recorded, December 20, 1973, Hercoform also commenced an action in the Sagadahoc County Superior Court to enforce its claim.

When Sherred defaulted on its payments in 1974, the Bank assigned its mortgage to HUD. In the assignment the Bank warranted to HUD that the mortgage would have priority over all mechanics’ and materialmen’s liens recorded after the date on which the mortgage was recorded.

It is undisputed that under Maine law Hercoform’s lien has priority over the mortgage, since Hercoform, with the consent and knowledge of Sherred, performed services as subcontractor before the mortgage was given and timely filed its lien claim and complaint. 10 M.R.S.A. §§ 3251 et seq.; Lyon v. Dunn, 402 A.2d 461, 463 (Me.1979). Prior to any resolution of Hercoform’s state court suit, however, the Bank and Chicago Title brought the present action in this Court under the Declaratory Judgment Act, 28 U.S.C. § 2201, seeking a declaration that the government’s mortgage lien takes priority over Hercoform’s mechanic’s lien. Hercoform and HUD were named as defendants.

Following an evidentiary hearing, this Court ruled on February 16, 1977, that the traditional federal “first in time, first in right” and choateness doctrines applied as the rule for determining lien priority in this case. Accordingly, the Court held that the mortgage assigned to HUD by the Bank *323 was entitled to priority over the mechanic’s lien asserted by Hercoform. After an affirmance by the First Circuit Court of Appeals, 568 F.2d 217 (1st Cir. 1978), the Supreme Court granted certiorari, vacated the judgment, and remanded the case, 441 U.S. 901, 99 S.Ct. 1987, 60 L.Ed.2d 370 (1979), for further consideration in light of United States v. Kimbell Foods, Inc., supra. In an order entered May 22, 1979, the First Circuit remanded the action to this Court. Following a request by HUD, which has joined with plaintiffs Chicago Title and the Bank in asserting the priority of the mortgage over the mechanic’s lien, 1 this Court ordered the record reopened and conducted an evidentiary hearing with respect to the operation of the HUD Section 236 program under which this project was undertaken.

Section 236 of the National Housing Act, 12 U.S.C. § 1715z-1, establishes a program to facilitate the construction of rental housing for lower income families. Under the program, the Secretary of Housing and Urban Development is authorized to insure mortgages and to make interest reduction payments that effectively reduce the rate of interest on the projects to as little as 1%. Not surprisingly, the program is rather complicated and involves a number of participants. 2

Typically, a project originates with an application from a nonprofit or limited distribution sponsor to the appropriate field office of the Federal Housing Administration (FHA) 3 seeking issuance of a site appraisal and market analysis (SAMA) letter. 24 C.F.R. § 236.5. Representatives from the field office visit and appraise the site and assess the marketability of the proposal. If the project appears feasible, the FHA issues a SAMA letter inviting the sponsor to submit an application for a conditional commitment.

At that point, the sponsor must find an FHA-approved lender, 24 C.F.R. §§ 236.1, 221.528, 203.1-203.9, who is willing to initiate the loans needed for construction and permanent financing of the project. The sponsor and lender apply to HUD for a conditional insurance commitment, setting out in the application a broad description of the project, including estimated construction and operating costs; providing detailed estimates of operating expenses and other financial considerations; and identifying other participants, including the contractor and architect, if known. 24 C.F.R. §§ 236.1, 221.509; FHA Form No. 2013. In reviewing the application, the FHA field office examines the experience and previous record of the various named participants to ensure their reliability and ability to complete the project, runs- an initial check on the accuracy of the estimated costs, and carefully considers the feasibility of the particular project.

If the FHA accepts the project, it issues a conditional commitment for insurance, subject to compliance by the sponsor (mortgagor) and lender (mortgagee) with a long list of requirements prior to issuance of a firm commitment and initial closing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
544 F. Supp. 320, 1982 U.S. Dist. LEXIS 12928, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chicago-title-insurance-v-sherred-village-associates-med-1982.