Chicago Rivet & Machine Co. v. Capital City Lumber & Planing Mill

145 P.2d 171, 158 Kan. 5, 1944 Kan. LEXIS 58
CourtSupreme Court of Kansas
DecidedJanuary 22, 1944
DocketNo. 35,913
StatusPublished
Cited by1 cases

This text of 145 P.2d 171 (Chicago Rivet & Machine Co. v. Capital City Lumber & Planing Mill) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chicago Rivet & Machine Co. v. Capital City Lumber & Planing Mill, 145 P.2d 171, 158 Kan. 5, 1944 Kan. LEXIS 58 (kan 1944).

Opinion

The opinion of the court was delivered by

Smith, J.:

This is an action to recover money. Judgment was for the defendant on a cross petition. The plaintiff appeals.

The plaintiff is in the business of making rivets in Chicago. It alleged that between certain dates in 1941 it furnished merchandise to the defendant and that there was still owing it the sum of $615.87. Judgment was prayed for this amount.

The defendant operates a planing mill in Topeka. It alleged by way of cross petition that it had a contract with the government to build certain field desks in accordance with specifications, which [6]*6specified the size and quantity of rivets needed; that it furnished the plaintiff with a copy of these plans; that it was required to complete the making of the desks within a certain time, all of which was known by the plaintiff. The answer .further alleged that the plaintiff agreed to make prompt delivery of all the rivets needed by defendant for the work; that plaintiff, pursuant to the oral .contract, sent tó defendant certain machines for use in fastening the rivets which were the wrong size and kind, and that the plaintiff sent rivets of the wrong size and shape so defendant was required to expend $320 in making these rivets so they could be used; that plaintiff also agreed to take certain rivets back and defendant paid freight charges in the sum of $14 and that on account of the failure of plaintiff to furnish these rivets promptly the defendant expended $16.48 in telephone calls and telegrams and that defendant returned to plaintiff rivets amounting to $90.44. The answer further alleged that the failure of the plaintiff to furnish a proper machine and the rivets as provided in the oral contract caused the defendant delay in the delivery of the desks and to be penalized by the government at the rate of $60 per day or a total of $1,020, and on account of this failure in its efforts to complete the contract on time defendant was compelled to pay overtime to its workmen in the amount of $480. Judgment was prayed by the defendant for $1,940.92.

In response to a motion by the plaintiff the court ordered the defendant to make its answer and cross petition more definite and certain, and the defendant did so by stating the names of the individuals with whom the oral agreement pleaded in its answer and cross petition was made, and that the plaintiff agreed to make delivery of the machine and rivets in not more than thirty days after the date of the oral agreement.

The reply was a general denial and an allegation that the rivets and the machines had been delivered promptly.

The case was submitted to the trial court without a jury. The court found in effect that sometime prior to December 5, 1940, the defendant bid for the construction of 1,020 field desks, Type III, and 2,000 of another type known as Type II; that the Type III desks were to be made of 5-ply wood and Type II of 3-ply wood; that about December 5, 1940, a representative of the defendant called on the plaintiff in Chicago with blue prints and specifications for these desks; that the representatives of the defendant told plaintiff that it was not versed in the use of rivets, whereupon plaintiff [7]*7assured defendant that it knew the riveting business and could take care of defendant’s needs and wants with respect to rivets and riveting machines, and the defendant could rest assured that if it got the government contract its riveting machine needs would be taken care of promptly and properly; that the defendant did get the contract and thereafter on December 11, 1940, it wired plaintiff that it had received the contract and requested shipment of about 20 per cent of the rivets and the machines at once, and on December 14, 1940, the plaintiff submitted to the defendant a list of the rivets required for both types of desks; that plaintiff knew that this was a rush job; that after the contract with the government was entered into the defendant started the construction of the desks and the plaintiff entered upon the business of furnishing it with the necessary rivets and machines. The court further found that the defendant had some difficulty in getting the plaintiff to furnish the rivets necessary to construct samples of the two types to be submitted to the government for inspection, but finally they were furnished and it developed that one of the machines furnished to set the rivets did not perform the work for which it was intended and that some of the split rivets furnished for the large desks were not suitable because by reason of their manner of construction the points spread out and did not properly clinch; that the desks were subject to government'inspection and the inspector refused to accept those constructed with these rivets and the defendant notified the plaintiff of this condition about the 28th of February, 1941; that in order that certain unsuitable rivets might be used the defendant reground some of them at an additional cost of $320; that plaintiff was informed that some of the rivets were unsuitable and sent its personal representative to defendant’s place of business sometime between February 28 and March 2; that on March 6, 1941, the plaintiff admitted that the 12/16 rivets and 13/16 rivets originally planned for the large desk were not of correct design, whereupon the plaintiff redesigned the rivets and sent the defendant a supply about March 14, 1941; that the redesigned rivets proving satisfactory were shipped to defendant, the last on April 3, 1941. The court further found that on January 18 the plaintiff shipped a riveting machine; that machine proved unsatisfactory and plaintiff sent its representative to make alterations on the machine; that these were completed and the machines ready for use on January-27, 1941; that under the terms of the government contracts 320 large desks were to be delivered on [8]*8February 9,1941, and 700 additional large desks on March 11, 1941; that 500 small desks were to be delivered February 9, 1941, and 1,500 on March 11, 1941; that defendant failed to make delivery of the desks within the time specified, and penalties were imposed against the defendant in the amount of $4,174.48; that no desks were delivered to the government under these contracts prior to March 26, 1941, and this was fifteen days subsequent to the time when penalties attached; that a wood production company had brought an action in the Shawnee district court against the defendant in this case for the price of ply-wood furnished the defendant for these desks in the amount of $5,075.80; that this defendant had ' claimed in a cross petition in that action that it had been damaged by failure of the wood company to furnish materials; that this action was settled by the planing mill company paying the wood company $2,500. The court further found that the defendant had paid a $14 freight bill in returning some rivets; that it returned two shipments of rivets that were sent in the amount of $54.85 and spent-$16.48 in telephone calls; that of all the delay chargeable to defendant by the government seventeen days was occasioned by the failure • of the plaintiff to furnish rivets of the proper size and shape for use upon these field desks and the failure of the plaintiff to furnish a machine suitable to such rivets and that the average penalty per day was $56, or a total of $952.- The court further found to the effect that it was impossible to tell from the evidence how much overtime had been paid by defendant and refused to allow anything to the defendant for that claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Billups v. American Surety Co.
251 P.2d 237 (Supreme Court of Kansas, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
145 P.2d 171, 158 Kan. 5, 1944 Kan. LEXIS 58, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chicago-rivet-machine-co-v-capital-city-lumber-planing-mill-kan-1944.