Chicago Fire Brick Co. v. General Roofing Manufacturing Co.

133 Ill. App. 269, 1907 Ill. App. LEXIS 257
CourtAppellate Court of Illinois
DecidedMarch 15, 1907
StatusPublished
Cited by1 cases

This text of 133 Ill. App. 269 (Chicago Fire Brick Co. v. General Roofing Manufacturing Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chicago Fire Brick Co. v. General Roofing Manufacturing Co., 133 Ill. App. 269, 1907 Ill. App. LEXIS 257 (Ill. Ct. App. 1907).

Opinion

Mr. Justice Myers

delivered the opinion of the court.

Appellant filed a bill in the City Court of East St. Louis to establish and enforce a lien for building tile and other material sold and delivered to appellee and by it used in the construction of a building on the premises described in the bill. The complainant alleged that on or about December 2, 1904, the defendant entered into a contract with complainant, whereby complainant agreed to furnish the material of. the kind and at prices specified in the bill, for which the defendant agreed to pay. It is further represented that pursuant of said contract and upon orders made from time ¡to time by the defendant, complainant shipped and delivered material amounting in all to the sum of $1,227 and that the payments made by the defendant aggregated $520, leaving balance due complainant the sum of $707. The defendant answering admits the making of a contract with complainant which is evidenced by a writing set ont in the answer as follows:

“East St. Louis, Ill., Dec. 2, 1904.
Chicago Eire Brick Co.,
Chicago, Ill.

Dear Sirs: Confirming verbal arrangement with your Mr. Spencer, we hereby place our order for your heavy Hollow Building Blocks 8x8x16 glazed weighing about 36 lb. each at price 8^ each f. o. b. East St. Louis. We will use sufficient number of these to erect a building according to the plans shown Mr. Spencer, and according to our estimate approximately about 12,000 blocks. Our order will also include about 2,300 partition blocks 12x12x6 at price of 5%^ per block f. o. b. E. St. Louis. It is understood that you will furnish the requisite number of corner blocks and fractional size blocks to complete our building in a good and proper manner, according to plans shown Mr. Spencer. The price on the fractional and corner blocks to be on basis of above prices, that is, a half block will cost half above price and a quarter block one-quarter price, etc.

“It is further understood that you will furnish a reputable contractor, who will be a strictly responsible mason, to lay these tiles in the building, he to furnish all material necessary, except the tile, to complete the job and all necessary labor, which shall be union or of such nature that it will not cause any conflict here with the local union on the rest of the work. Such labor and materials to be furnished at his expense and all the work to be done by him in accordance with the instructions to masons on page 17 of your circular left with us by Mr. Spencer and in "a good and workmanlike manner, we to pay him 3%^ each for laying all full size tiles above ordered, the fractional blocks being charged for on the basis of 8x8x16, that is, the half block will cost only half as much for laying as a full block and a quarter block as much, etc. You guarantee the wall to stand fire and weather, at least as well as a brick wall of equal thickness and the wall will stand intact for at least five years. He to do this work promptly upon notification by us that the material is here, and finish the work as quickly as the weather will permit. We agree to furnish one round-trip ticket for his transportation here and back to Chicago. Terms one-half cash for all the material as soon as it is on the ground and the balance on completion of the work by your contractor as above specified. Very truly yours,

General Roofing Mfg. Co.,
DiC. G. M. B. (Per Geo. M. Brown, President.)

“P. S. We reserve the right to cancel this order not later than next Tuesday in case we find that we are unable to get a satisfactory carpenter contractor to do the balance of the work in a satisfactory way and are compelled to let the work to a general contractor who objects to using your goods in the work at a satisfactory price. It is understood that as soon as we notify you that everything is all right you will make immediate shipment of at least half the goods.

G. M. B.
Geo. M. Brown.
Accepted. Chicago Fire Brick Co. B. T. Spencer.”

Defendant claims that under the terms of the contract complainant was to furnish a contractor - to construct the walls of the proposed building with the tile furnished and to • see that the work was properly done, and claims in recoupment of damages, $60 paid for pointing walls, $250 paid in making the building weather-proof, and $51 for delay in furnishing a man to do the work as required by the contract. A general replication was filed and the cause heard by the court which rendered a decree finding that there was due the complainant, after deducting payments made, for building blocks furnished, the sum of $490.75, at the time of filing the bill. And as against this sum the court allowed to the defendant, in recoupment or set-off, items claimed, aggregating $418, leaving as balance due the complainant the sum of $72.73, and decreed that complainant was entitled to a lien upon the premises for the sum of $72.73 with interest at 5 per cent from June 25,1906, and costs of suit, including $25 for complainant’s solicitor’s fees. Complainant appealed to this court, assigning a number of errors, the one chiefly relied upon being that the court erred in decreeing that the defendant was entitled to recoup $418, or any sum, from the amount due the complainant. Whether or not the decree should be reversed depends upon the contract between the parties. If the trial court was right in its construction and finding as to the contract, the decree should be affirmed, for upon an examination of the evidence we think the conclusions reached as to the facts and the allowance made the appellee in recoupment, were justified by the evidence, and we find no prejudicial error in the court’s rulings upon the admission and exclusion of evidence. Appellant contends that the letter or order of December 2, 1904, set out in the answer, does not ip itself constitute a contract, and standing alone may not be considered as the agreement between the parties. We cannot agree with appellant in this contention. The instrument, order or letter, whichever it may be termed, clearly amounts to a proposition based upon verbal negotiations between the duly authorized representatives of the two companies, appellant and appellee. The proposition and acceptance are in writing duly signed, in duplicate, each party retaining a copy. ISTothing further was needed to complete a contract mutually binding upon the parties and sufficiently clear and definite to warrant the construction claiméd by appellee and given to it by the court respecting the obligation of appellant “to furnish a reputable contractor, who shall be a strictly responsible mason, to lay these tile in the building, he to furnish all material necessary, except the tile, to complete the job and all necessary labor, * "* * such labor and materials to be furnished at his expense and all the work to be done by him in accordance to instructions to masons on page 17 of your (appellant’s) circular left with us by Mr. Spencer and in good workmanlike manner, we to pay him 3%$ each for laying full sized tile above ordered,” etc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Devine v. Notter
2008 WI App 87 (Court of Appeals of Wisconsin, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
133 Ill. App. 269, 1907 Ill. App. LEXIS 257, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chicago-fire-brick-co-v-general-roofing-manufacturing-co-illappct-1907.