Chicago Bridge & Iron Co. v. Olson

83 N.W. 461, 80 Minn. 533, 1900 Minn. LEXIS 557
CourtSupreme Court of Minnesota
DecidedJuly 24, 1900
DocketNos. 12,083—(228)
StatusPublished
Cited by1 cases

This text of 83 N.W. 461 (Chicago Bridge & Iron Co. v. Olson) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chicago Bridge & Iron Co. v. Olson, 83 N.W. 461, 80 Minn. 533, 1900 Minn. LEXIS 557 (Mich. 1900).

Opinion

LEWIS, J.

Defendants and the city of Le Sueur, on April 4,1896, entered into a contract in writing, whereby defendants agreed to furnish all of the material and perform all the labor for the construction of a waterworks system and an electric light plant according to certain specifications then on file in the office of the city clerk. Under the head of “Time of Completion” are found the following provisions:

“The entire work shall be fully completed on or before the 15th day of August, 1896. If, however, the work is let in separate contracts, each part shall be completed in the time mentioned under its proper heading. * * * For any delay in the full completion of the entire work on or before the 15th day of August, 1896, or for any portion of the work when let in separate contract, not including the entire work, beyond the time specified for the completion pf such portion, the council shall have the right to deduct from tibie final estimate, as liquidated damages, the sum of ten dollars per day for the entire period of such delay.”

The specifications provided for a standpipe for the waterworks, [535]*535and the terms and conditions in reference to it are set out under the heading “Standpipe,” and the time for completion of the same was fixed on or before August 15, 1896, but there was no reference to forfeiture for delay in that connection. Defendants relet the building of the standpipe to plaintiff, according to the following proposition and acceptance:

“St. Paul, Minn., April 10th, 1896.
O. H. Olson & Co.,
Stillwater, Minn.
Gentlemen: We hereby propose to furnish all material and labor necessary to build and erect that portion of your contract at Le Sueur, Minn., under the head of ‘standpipe/ for the sum of three thousand and ninety-fire dollars ($3,095). All work to be done to the entire satisfaction of the city council and engineer in charge as limited by plans on file, and we to assume all responsibility of doing this work to their entire satisfaction, and to hare the same complete on or before the time for completion of same specified in your contract with the city of Le Sueur, Minn.
Tours respectfully,
Chicago Bridge & Iron Co.
S. H. Hedges, Agt.
This contract must be countersigned by Horace E. Horton to be binding on the Chicago Bridge & Iron Co.
Approved by Horace E. Horton, Pt.
Accepted this--day of April, 1896.
O. H. Olson & Co.”

Neither of the plants were completed on August 15, 1896, but on August 22 the electric light plant was turned over to the city, and the city from that time used the plant, although no formal acceptance was made other than the resolution hereinafter stated. Plaintiff completed the standpipe on September 28, and on October 2, 1896, the city council held a meeting, at which the engineer for the city made a report that the light and water plant furnished by defendants was completed, with the following exceptions: That the street lights were one hundred ten volt instead of two hundred twenty, that the portable volt meter had not been furnished, and that the standpipe should be made tighter; whereupon the city council passed the following resolution:

“Resolved, that with the following exceptions the standpipe waterworks, and electric light plant, boiler, pump, and all matters [536]*536included in the contract of O. H. Olson & Co., be accepted, the exceptions being as follows: $480 shall be, and hereby is, declared forfeited under the terms of the contract and retained for the delay of forty-eight days since the 15th day of August, 1896. The standpipe is declared defective for leakage, a portable volt meter contracted to be furnished is not furnished, and the street lights are one hundred ten volts, and not two hundred twenty volts, as required. * *”

The resolution further provided that $175 be retained until such matters be completed.

This action was brought by plaintiff to recover from defendants the sum of $607.13, alleged to be still due for constructing the standpipe. The complaint refers to the contract between the city and defendants, sets up plaintiff’s agreement with defendants, and alleges that the contract was complied with, and the standpipe completed and accepted by the city, no special mention being made of the time of completion. Defendants, in answer, plead a counterclaim for damages based on the failure of plaintiff to complete its contract within the time agreed, and that the city had deducted $480 on account of such delay. The reply denied that defendants were damaged by reason of the delay in completing the standpipe, and alleges that the delay in completing the entire plant was caused by defendants themselves. At the close of the evidence plaintiff moved the court to direct a verdict for the plaintiff upon the ground that defendants had failed to show any damages by reason of the failure to complete the standpipe in time. The motion was granted, and the jury directed to return a verdict for plaintiff for $592.65, with interest. Afterwards, upon-a motion by defendants, the court granted a new trial, and plaintiff appeals.

1. Was the plaintiff at the close of the trial entitled to judgment for the amount of the verdict, unless defendants succeeded in proving their counterclaim or some part thereof?

This proposition is denied by respondents upon the following ground: That the complaint referred to the contract of defendants with the city as the basis of the agreement between plaintiff and defendants, and therefore it appeared from- the complaint that plain-' tiff contracted with defendants with knowledge of, and in contemplation of, the forfeiture clause; that the reply was a departure; [537]*537that plaintiff could not be heard to show under the pleadings that defendants caused the delay, and therefore defendants were entitled to judgment. The complaint does not in any sense admit that plaintiff was the cause of the delay. The mere fact that it refers to the original contract is no such admission, and, on the contrary, the allegation in the complaint is specific that the contract with defendants was performed, and the standpipe accepted. The reply was defensive to the new matter in the answer, and the burden was not in the first instance on the plaintiff to show that it was not responsible for the delay. That issue was tendered by the defendants, denied by the plaintiff, and the burden of proving the issue remained with the defendants.

2. Was there any evidence reasonably tending to show that defendants were damaged on account of the failure of plaintiff to complete the standpipe within the stipulated time?

In the first place, we must determine what the agreement was on that subject. In the absence of any other evidence, we are restricted to the instruments in writing already referred to, and from them alone must discover what was contemplated by the parties in reference to the forfeiture clause. The specifications attached to the original contract between defendants and the city treated the subject “standpipe” under one head, and required that it be completed on or before August 15, 1896.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wallis v. Inhabitants of Wenham
90 N.E. 396 (Massachusetts Supreme Judicial Court, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
83 N.W. 461, 80 Minn. 533, 1900 Minn. LEXIS 557, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chicago-bridge-iron-co-v-olson-minn-1900.