Chicago Ambulatory Surgery Associates, LLC v. Restore Construction, Inc.

2021 IL App (1st) 201157-U
CourtAppellate Court of Illinois
DecidedSeptember 14, 2021
Docket1-20-1157
StatusUnpublished

This text of 2021 IL App (1st) 201157-U (Chicago Ambulatory Surgery Associates, LLC v. Restore Construction, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chicago Ambulatory Surgery Associates, LLC v. Restore Construction, Inc., 2021 IL App (1st) 201157-U (Ill. Ct. App. 2021).

Opinion

2021 IL App (1st) 201157-U

SECOND DIVISION September 14, 2021

No. 1-20-1157

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).

IN THE APPELLATE COURT OF ILLINOIS FIRST JUDICIAL DISTRICT

CHICAGO AMBULATORY SURGERY ) Appeal from the Circuit Court of ASSOCIATES, INC., CHICAGO PAIN AND ) Cook County. ORTHOPEDIC INSTITUTE, LLC, ) ACCREDITED AMBULATORY CARE, LLC, ) RAPID REHAB OF ILLINOIS, LTD., FOOT ) AND ANKLE TREATMENT CENTER OF ) CHICAGO, LLC, IMH MEDICAL BILLING ) SERVICES, INC., and BREACHED, LLC, ) ) Plaintiffs, ) ) v. ) ) RESTORE CONSTRUCTION, INC., PATRICK ) No. 16 L 7611 L. SANTORO SR., and MICHAEL P. SANTORO, ) ) Defendants. ) _________________________________________ ) ) RESTORE CONSTRUCTION, INC., ) ) Third-Party Plaintiff-Appellant, ) ) v. ) ) (Super T Plumbing and General Contracting, Inc., ) George Tompoe, Gary L. Matthews, GMP ) Honorable Daniel J. Kubasiak, Development, LLC, Steven Searles, ) Judge Presiding. 1-20-1157

Third-Party Defendants.) ) ) ONYX ARCHITECTURAL SERVICES, INC, ) ) Third-Party Defendant-Appellee. )

JUSTICE HOWSE delivered the judgment of the court. Justices McBride and Burke concurred in the judgment.

ORDER

¶1 Held: The circuit court did not err when it entered summary judgment in favor of a third-party defendant in a contribution action. The record demonstrates that the third-party defendant, an architectural firm, did not have a duty to inspect the plumbing installation that is the basis of the third-party plaintiff’s contribution claim. ¶2 Third-Party Plaintiff Restore Construction, Inc. retained third-party defendant Onyx

Architectural Services, Inc. to provide architectural services for a construction project in

Chicago. During construction, the plumbing contractors deviated from the plans. After the

project was completed, the improper plumbing work caused water and sewage to flood the

building on dozens of occasions.

¶3 The building owners sued Restore Construction, and Restore Construction filed a third-

party complaint against Onyx Architectural, among other parties. Restore Construction alleges

that Onyx Architectural is liable for failing to inspect the plumbing work and ensure that the

plumbing work was done properly and done in accordance with the architectural plans. The trial

court found that Onyx Architectural did not have the legal duties that underlie Restore

Construction’s contribution claim. We affirm.

¶4 BACKGROUND

¶5 The plaintiffs in the first-party action in this case hired defendant Restore Construction,

Inc. to build out medical office space at 1212 N. LaSalle Street in Chicago. In turn, Restore

2 1-20-1157

Construction retained the services of several contractors to perform the varying tasks associated

with the construction project.

¶6 After construction was completed, flooding events began to occur at the property. The

plaintiffs allege that, on no less than 61 occasions, sudden floods caused water and sewage to

back up into the building and begin overflowing into various rooms. The plaintiffs allege that the

water and sewage sometimes accumulated to as much as six inches deep. Water damage

occurred throughout the building and the property damage and the improper plumbing work had

to be fixed at significant cost to plaintiffs. Plaintiffs also allege that they lost significant business

revenue by having to cancel surgeries that they were scheduled to perform. The flooding was

primarily the result of the plumbers tying into the wrong line, meaning that the plumbers

deviated from the plans and improperly connected the sanitary sewer line to the storm water

piping.

¶7 Plaintiffs filed this case against Restore Construction and its principals for the damages

resulting from the allegedly improper construction. After being sued, Restore Construction filed

a third-party action against the contractors it hired to perform certain work. Relevant here is

Restore Construction’s third-party claim against Onyx Architectural Services. Restore

Construction retained Onyx Architectural to provide architectural services for the project,

including the preparation of architectural plans and specifications for the project. The

relationship between Restore Construction and Onyx Architectural is governed by a contract.

¶8 The contract between Restore Construction and Onyx Architectural provides that Onyx

Architectural would provide its services during five stages of construction: (1) the schematic

design phase; (2) the design development phase; (3) the construction document phase; (4) the

bidding phase; and (5) the construction observation phase. Most relevant here is the

3 1-20-1157

“construction observation phase.” Restore Construction contends that Onyx Architectural is

liable in contribution because it failed to make reasonable inspections of the plumbing services,

failed to ensure that the proper piping connections existed, and generally failed to properly

perform architectural services relating to the piping connections. Restore Construction maintains

that Onyx Architectural had a duty during the construction observation phase of the project to

ensure that the construction taking place at the site complied with the architectural drawings it

prepared. Onyx Architectural moved for summary judgment arguing that it had no duty to

perform the services that Restore Construction alleges it was negligent in performing.

¶9 The contract between Restore Construction and Onyx Architectural stipulates that Onyx

was required to make a minimum of one site visit per week throughout the construction schedule.

Onyx was further required under the contract to attend weekly meetings to discuss project

progress and adherence to the drawings and the construction schedule. Although the contract

between Restore Construction and Onyx Architectural does not mention any obligation to

“inspect,” Restore Construction maintains that Onyx had a duty to inspect and ensure compliance

with its drawings.

¶ 10 Pointing to the deposition testimony of Stephen Searles, the project manager Restore

Construction hired for the project, Restore Construction contends that the parties understood that

Onyx would inspect all work, or that Onyx would at least observe the work and ensure it

complied with the architectural drawings. Searles testified that, typically, architects inspect all

work. Searles further testified that architects look to see if the work is complete, but that

architects depend on the city inspectors, such as the plumbing inspector, to perform the deep

dives on particular building disciplines.

4 1-20-1157

¶ 11 In contrast to the deposition testimony that Restore Construction relies upon, Onyx

Architectural points to portions of Searles’s deposition in which he testified that he did not hire

Onyx Architectural to inspect the work, including the plumbing work. He testified that all the

services Onyx was required to perform were memorialized in the contract. The contract did not

give Onyx Architectural the authority to define the means and methods of the work.

¶ 12 In the first party action, the plaintiffs did not allege that Onyx Architectural was negligent

in any way. The plaintiffs did not allege that there was any negligence or anything improper

about the plans drawn up by Onyx Architectural. Instead, the plaintiffs allege that Restore

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kahn v. First Nat. Bank of Chicago
576 N.E.2d 321 (Appellate Court of Illinois, 1991)
Unterschuetz v. City of Chicago
803 N.E.2d 988 (Appellate Court of Illinois, 2004)
Marshall v. City of Centralia
570 N.E.2d 315 (Illinois Supreme Court, 1991)
McGovern v. Standish
341 N.E.2d 739 (Appellate Court of Illinois, 1975)
Block v. LOHAN ASSOCIATES, INC.
645 N.E.2d 207 (Appellate Court of Illinois, 1993)
Ferentchak v. Village of Frankfort
475 N.E.2d 822 (Illinois Supreme Court, 1985)
Zubi v. Acceptance Indemnity Insurance
751 N.E.2d 69 (Appellate Court of Illinois, 2001)
George W. Kennedy Construction Co. v. City of Chicago
491 N.E.2d 1160 (Illinois Supreme Court, 1986)
Thompson v. Gordon
948 N.E.2d 39 (Illinois Supreme Court, 2011)
Illinois Tool Works Inc. v. Travelers Casualty and Surety Company
2015 IL App (1st) 132350 (Appellate Court of Illinois, 2015)
Fox v. Seiden
2016 IL App (1st) 141984 (Appellate Court of Illinois, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2021 IL App (1st) 201157-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chicago-ambulatory-surgery-associates-llc-v-restore-construction-inc-illappct-2021.