Chester Upland School District v. Edward J. Meloney, Inc.

901 A.2d 1055, 2006 Pa. Super. 141, 2006 Pa. Super. LEXIS 1471
CourtSuperior Court of Pennsylvania
DecidedJune 15, 2006
StatusPublished
Cited by4 cases

This text of 901 A.2d 1055 (Chester Upland School District v. Edward J. Meloney, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chester Upland School District v. Edward J. Meloney, Inc., 901 A.2d 1055, 2006 Pa. Super. 141, 2006 Pa. Super. LEXIS 1471 (Pa. Ct. App. 2006).

Opinion

OPINION BY BENDER, J.:

¶ 1 Gillan & Hartmann, Inc. (Architect) appeals from the order denying its motion for summary judgment and granting Edward J. Meloney, Inc.’s (Contractor) cross-motion for summary judgment on Architect’s claim for indemnification for costs and attorney’s fees incurred in defending itself in a lawsuit against it and Contractor brought by the Chester Upland School District (School District). For the following reasons, we affirm.

¶ 2 The facts of this case are as follows. The School District contracted with various parties, among them Contractor and Architect, for the purchase and installation of a new chiller and cooling tower for the HVAC system at the Chester High School. There are numerous documents that constitute the agreement between the various parties; however, for purposes of our decision here we are concerned with the following: (1) the Contract between Contractor and School District (Reproduced Record (R.) at 28a); (2) the Specifications drafted by Architect and incorporated into the Contract (Brief for Appellee Contractor, Appendix A); (3) the General Conditions drafted by Architect and made applicable pursuant to the Specifications (R. at 125a); (4) the Supplementary General Conditions drafted by Architect and made applicable pursuant to the Specifications (R. at 156a); and (5) the Special Conditions drafted by Architect and made part of the “Contract Documents” pursuant to the Supplementary General Conditions (R. at 174a). 1

¶ 3 Pursuant to the Specifications, Contractor was to use an absorption chiller that met Architect’s specific requirements, which included, inter alia, certain capacities, electrical requirements, the type of generator and condenser, and the type of refrigerant to be used. Specifications, ¶¶ 2.2-2.7. The Specifications listed only one available manufacturer (McQuay, Snyder General (McQuay)) from whom Contractor could purchase an absorption chiller meeting the very detailed requirements, and Contractor chose to use the absorption chiller manufactured by McQuay. Specifications, ¶ 2.1. 2

¶ 4 Sometime in January or February of 1997, the installation of the McQuay chiller was completed. In April of 1997, the parties attempted to start the chiller, but for several reasons, the attempt failed. As of April of 1998, the chiller still did not function properly, and in June of 1998, Con *1058 tractor, McQuay and Tri-State HVAC Equipment (Tri-State) attempted to fix the chiller by cutting the top off in order to re-align trays that were allegedly improperly installed by McQuay. However, the alterations were to no avail, and the chiller continued to malfunction.

¶ 5 In September of 2000, School District declared Contractor in default on the Contract, and the instant action ensued on May 18, 2001. On September 10, 2001, School District filed the Complaint containing nine counts. Pertinent to the instant appeal are counts eight and nine against Architect for breach of contract and negligence, respectively. (R. at 19a-21a.) Architect then filed a cross-claim against Contractor for indemnification. The case proceeded to a bench trial before the Honorable James F. Proud, however; during the trial, the parties settled the action and all that remained was Architect’s claim for indemnification against Contractor. 3 Ultimately, the court granted Contractor’s cross-motion for summary judgment, and Architect then filed this appeal raising the following two questions for our review:

A. Whether a party to be indemnified pursuant to a contractual provision providing indemnification against suits and claims must pay a claim for damages before obtaining the right to indemnification.
B. Whether a party to be indemnified pursuant to a contractual provision providing indemnification against suits and claims is entitled to recover its legal fees and expenses and its legal fees and its expenses paid by its insurer, together with internal costs of defense.

Brief for Appellant at 4.

¶ 6 In an appeal arising from a trial court’s ruling upon motions for summary judgment, our scope and standard of review are well settled.

We view the record in the light most favorable to the non-moving party, and all doubts as to the existence of a genuine issue of material fact must be resolved against the moving party. Only where there is no genuine issue as to any material fact and it is clear that the moving party is entitled to a judgment as a matter of law will summary judgment be entered. Our scope of review of a trial court’s order granting or denying summary judgment is plenary, and our standard of review is clear: the trial court’s order will be reversed only where it is established that the court committed an error of law or abused its discretion.

Atlantic States Ins. Co. v. Northeast Networking Systems. Inc., 893 A.2d 741, 745 (Pa.Super.2006) (citations omitted).

¶ 7 The central issue in this appeal is whether Architect has a right of indemnification against Contractor for costs and attorney’s fees incurred by Architect in defending itself against claims for its own negligence and breach of contract in the underlying action brought by the School District. In the subsequent analysis we identify various indemnification clauses contained in the Contract, the General Conditions, the Supplementary General Conditions, and the Special Conditions. *1059 Some of these clauses conflict with one another, and for the reasons that follow, we conclude that the indemnification clause relied upon by Architect does not apply. Our discussion necessarily departs from addressing the questions presented by Architect, as its arguments are founded upon the presumption that a particular indemnification clause applies. Nonetheless, our analysis, which concludes that the applicable indemnification clause bars Architect’s claims, is dispositive of the issues presented by Architect in this appeal.

¶ 8 “The fundamental rule in interpreting the meaning of a contract is to ascertain and give effect to the intent of the contracting parties.” Murphy v. Duquesne Univ. of the Holy Ghost, 565 Pa. 571, 777 A.2d 418, 429 (2001). “Indemnity agreements are to be narrowly interpreted in light of the parties’ intentions as evidenced by the entire contract.” Consolidated Rail Corp. v. Delaware River Port Autk, 880 A.2d 628, 632 (Pa.Super.2005). “In interpreting the scope of an indemnification clause, the court must consider the four corners of the document and its surrounding circumstances.” Widmer Engineering, Inc. v. Dufalla, 837 A.2d 459, 472 (Pa.Super.2003) (citations and quotation marks omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michael, G. v. Stock, J.
162 A.3d 465 (Superior Court of Pennsylvania, 2017)
Burlington Coat Factory v. Grace Construction
Superior Court of Pennsylvania, 2015

Cite This Page — Counsel Stack

Bluebook (online)
901 A.2d 1055, 2006 Pa. Super. 141, 2006 Pa. Super. LEXIS 1471, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chester-upland-school-district-v-edward-j-meloney-inc-pasuperct-2006.