Chester S. Schreffler v. Birdsboro Corp. v. Bethlehem Steel Corporation

490 F.2d 1148, 1974 U.S. App. LEXIS 10403
CourtCourt of Appeals for the Third Circuit
DecidedJanuary 24, 1974
Docket73-1338
StatusPublished
Cited by36 cases

This text of 490 F.2d 1148 (Chester S. Schreffler v. Birdsboro Corp. v. Bethlehem Steel Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chester S. Schreffler v. Birdsboro Corp. v. Bethlehem Steel Corporation, 490 F.2d 1148, 1974 U.S. App. LEXIS 10403 (3d Cir. 1974).

Opinion

OPINION OF THE COURT

WEIS, Circuit Judge.

We are concerned in this case with the claim of error in the entry of a directed verdict for the defendant in a personal injury suit brought on the theory of defective design of industrial equipment. While the legal principles are not particularly complicated, the highly specialized nature of the machinery and manufacturing operations involved require a somewhat extended discussion of the factual background.

Appellant Chester S. Schreffler, an employee of Bethlehem Steel Corporation, was severely injured at its Steel-ton, Pennsylvania plant when a fellow employee caused a load of hot steel billets to be pushed against Mr. Schreffler, squeezing him against the side of the machine on which he was working. The accident occurred on March 13, 1965 as the appellant was fastening chains around a load of billets resting on a “transfer table” preparatory to having a crane lift them to a nearby railroad car. 1

In the course of his duties as a “cra-dleman,” it was necessary for Schreffler to stand upon the “transfer table” which was located between the “straightener” (a component utilized to straighten some of the rolled steel products manufactured in the mill) and the “shear” (a machine used to cut steel). The steel exiting from the “straightener” would be carried forward by a set of rollers, then moved in a reverse direction by a second set of rollers into the “shear” mechanism.

The “table” consisted generally of rollers in two parallel series separated by a number of parallel steel rails roughly twenty feet long and spaced five feet apart, running perpendicular to the line of direction of the rollers and at the same level above ground. A “rope drag” or “rope transfer,” consisting of multi- *1150 pie depressible dogs pulled by chains, slid the various steel products over the rails from one series of rollers to the other. In addition to its function of facilitating the change of direction of the material being manufactured, the area between the rollers where the rails were located was intended to act as a temporary storage area for material being processed.

When Schreffler stepped onto a wire grating platform located between two of the rails, there were already two stacks of billets lying side-by-side on the surface of the rails. He had put the chain around the first stack of billets and was continuing his work when the accident occurred.

The rope drag operator had started an additional billet over the table from the first set of rollers to add to the second “load” when his attention was distracted by another billet coming out of the straightener. He was concerned about being struck by this billet, forgot that the billet on the table was continuing its progress toward the plaintiff, and consequently did not stop the machine in time.

The table was one of a number of items of mill equipment which had been manufactured by the defendant Birds-boro and installed in 1959 by the third-party defendant, Bethlehem.

Birdsboro, at the request of Bethlehem, had originally .submitted a proposal to manufacture and sell the equipment in 1957, but the plan for a new mill was not carried through to fruition at that time. Bethlehem later revived the project, and with minor variations of the original plans and specifications, Birds-boro furnished the equipment in 1958 and early 1959.

The specifics of the machinery had been agreed upon after consultation between Birdsboro and Bethlehem engineers and to a great extent represented a joint effort of the two companies. It was understood that not all of the existing equipment in the Bethlehem plant was to be replaced, nor was Birdsboro given carte blanche to set up a complete mill. Bethlehem determined what new machinery and equipment it wanted and undertook the work of installation with its own employees. For example, while Bethlehem at one time had thought that it would extend its “cooling bed” and asked for a quotation from Birdsboro, that part of the project was never carried through, and Birdsboro was not asked to manufacture that item.

Although Bethlehem was to install the machinery, the contract did provide that Birdsboro was to have an erector on the scene to furnish technical advice. However, he was given no authority over anyone at Bethlehem. When the work was completed in March of 1959, the Birdsboro representative left the premises.

The installation of the transfer table, which measured 90 feet by 30 feet and had a gross weight of approximately 500,000 pounds, was a substantial undertaking and required the excavation of a foundation so that the table could be properly positioned. As originally designed, the spaces between the rails of the transfer table were left open, thus leaving a gap between the rails through which objects could fall to the floor several feet below. However, at the time of installation, Bethlehem placed solid steel plates between four of the sets of the rails, at a depth of 16 to 18 inches below their top surfaces.

The record does not disclose what use of these solid steel plates was contemplated at the time of their installation, but it is known that during the period between the time production of billets began in December, 1960 and the accident in 1965, the solid steel plates were utilized as walk-ways or platforms by the “cradlemen” who worked on the transfer table to unload billets.

The testimony was somewhat imprecise, but it seems that about a year or two after installation of the table, Bethlehem placed sheets of open steel grating in three or four of the remaining open spaces between the rails in a position similar to that of the solid steel plates. *1151 This was done in order to prevent falling accidents by the cradlemen working on the table. No evidence indicates any knowledge on the part of Birdsboro that this additional modification had been performed.

The machinery which Birdsboro had furnished is part of a “merchant mill” which produces such specialty steel items as rails, cutting edges, tractor shoes, guard rails, curb facing, and other products in addition to “billets” and “rounds” (rounded equivalents of billets).

Before the renovation, the mill had produced billets which were about 2 inches by 2 inches in cross section. But it was not until December of 1960, about a year and a half after delivery of the Birdsboro equipment, that Bethlehem began to manufacture billets using the new machinery.

Though it was not necessary for billets to be put through the “straightener,” the practice was to adjust this device in such a fashion that the billets could pass through it, a procedure called “dummying.” After being taken from the rollers by the rope drag, the billets were lifted to a railroad car by a crane hooking onto the chains fastened around the loads by the cradlemen.

Although there were billet discharge points at prior locations in the line of production, 2 they had not been utilized because experience had shown that the billets did not cool sufficiently in the old cooling beds. The new equipment, being more efficient, produced more billets in any given period of time than the old mill.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fisher v. Walsh Parts & Service Co., Inc.
277 F. Supp. 2d 496 (E.D. Pennsylvania, 2003)
Sisco v. Broce Manufacturing, Inc.
1 F. App'x 420 (Sixth Circuit, 2001)
Davis v. Berwind Corp.
640 A.2d 1289 (Superior Court of Pennsylvania, 1994)
First National Bank v. Sedgwick James of Minnesota, Inc.
792 F. Supp. 409 (W.D. Pennsylvania, 1992)
Olson v. U.S. Industries, Inc.
649 F. Supp. 1511 (D. Kansas, 1986)
Van Buskirk v. Carey Canadian Mines, Ltd.
760 F.2d 481 (Third Circuit, 1985)
Anderson Banks v. Iron Hustler Corp.
475 A.2d 1243 (Court of Special Appeals of Maryland, 1984)
Kuhnke v. Textron, Inc.
684 P.2d 159 (Court of Appeals of Arizona, 1984)
Neal v. Carey Canadian Mines, Ltd.
548 F. Supp. 357 (E.D. Pennsylvania, 1982)
Cropper v. Rego Distribution Center, Inc.
542 F. Supp. 1142 (D. Delaware, 1982)
Wright v. Federal MacH. Co., Inc.
535 F. Supp. 645 (E.D. Pennsylvania, 1982)
Hollinger v. Wagner Mining Equipment Co.
505 F. Supp. 894 (E.D. Pennsylvania, 1981)
Orion Ins. Co., Ltd. v. United Technologies Corp.
502 F. Supp. 173 (E.D. Pennsylvania, 1980)
Meuller v. Jeffrey Manufacturing Co.
494 F. Supp. 275 (E.D. Pennsylvania, 1980)
Abdul-Warith v. Arthur G. McKee and Co.
488 F. Supp. 306 (E.D. Pennsylvania, 1980)
David v. Broadway Maintenance Corp.
451 F. Supp. 877 (E.D. Pennsylvania, 1978)
Mattocks v. Daylin, Inc.
78 F.R.D. 663 (W.D. Pennsylvania, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
490 F.2d 1148, 1974 U.S. App. LEXIS 10403, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chester-s-schreffler-v-birdsboro-corp-v-bethlehem-steel-corporation-ca3-1974.