Chesarone v. Pinewood Builders, Inc.

186 N.E.2d 712, 345 Mass. 236, 1962 Mass. LEXIS 684
CourtMassachusetts Supreme Judicial Court
DecidedDecember 17, 1962
StatusPublished
Cited by26 cases

This text of 186 N.E.2d 712 (Chesarone v. Pinewood Builders, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chesarone v. Pinewood Builders, Inc., 186 N.E.2d 712, 345 Mass. 236, 1962 Mass. LEXIS 684 (Mass. 1962).

Opinion

Spiegel, J.

This is a bill in equity to enjoin the defendants from “discharging and throwing water in an artificial stream on the land” of the plaintiff and for damages. The suit was referred to a master. Bach of the parties filed objections to the master’s report. The court below entered an interlocutory decree in which the exceptions of all the parties were overruled and various motions filed by the “several parties” were denied and recommittal to the master for further findings as follows was ordered:

“1. That further facts be reported after taking additional testimony, if required, for the purpose of applying a correct measure of damages in accordance with the principle of establishing damages suggested in Belkus v. City of Brockton, 282 Mass. 285, more particularly, to report facts which would indicate to the Court whether — if, the injury *238 is reasonably curable by repairs, the reasonable expenses of repairs is less than the diminished market value.

“2. That the master report facts which would indicate to the Court — if the act is continuous, but subject to termination by the later act of the . . . [defendants], the lessened rental value while the injury continued to the date of the bill.”

None of the parties appealed from this decree.

After the master’s report on recommittal each of the parties filed objections to that report which, under Eule 90 of the Superior Court (1954), are treated as exceptions. An interlocutory decree was entered overruling the exceptions of the plaintiff and the defendant Pinewood Builders, Inc., sustaining the exceptions of the town of Framingham, and ordering the master’s report and report on recommittal “confirmed as so modified.” Pinewood Builders, Inc. (hereinafter referred to as Pinewood), appealed from this decree. The court entered a final decree ordering Pinewood to pay to the plaintiff $21,750 plus interest and in “all other respects . . . dismissed” the bill, from which the plaintiff and Pinewood appealed.

A summary of the material facts found by the master follows. In 1931, the plaintiff purchased a parcel of land consisting of about forty-three acres in the towns of Framingham and Sudbury. In 1953, the plaintiff sold a portion of this land to the Lexington Sand & Gravel Co. and as a part of the transaction granted that company an easement for five years to “. . . dump waste water and waste material upon, and . . . erect, maintain, and operate . . . equipment” on a part of the plaintiff’s remaining land. By deeds dated January 10, 1959, and May 15, 1959, the Lexington Sand & Gravel Co. “transferred its title in the land originally belonging to” the plaintiff to the defendant Pinewood. The parcel of land to which the plaintiff retained title comprised approximately fourteen and a half acres. In 1931, all of the land was in a “wild and undeveloped state” and “had a tendency to become damp and wet as a result of the flood of natural water onto it from sur *239 rounding land including land subsequently owned by the” defendant Pinewood. However, about 1932, the plaintiff made certain improvements to the land, chiefly in the form of draining ditches which resulted in drying up the land with the exception of a “wet spot” of about 1,000 square feet. Except for this “wet spot,” the land would remain dry and usable in its natural state if the adjacent land now owned by the defendant Pinewood were left in its “natural undeveloped” state.

In 1959 and 1960, immediately after its purchase of the land from the gravel company, Pinewood embarked upon a project to develop its land, together with some land adjacent thereto, for several hundred housing units “under the name of Woodfield I, II, and III.” Pinewood, with the approval and permission of the planning board of Framing-ham and the permission of the town engineer and members of the engineering department, then graded the land so that it gradually sloped in a descending plane toward the plaintiff’s land. As a part of this authorized plan a surface water drainage system was installed which caused all of the surface water from the area to be collected into the drains and then to be discharged on the land of one Raymond from which it spilled over onto the plaintiff’s land. Upon the complaint of the plaintiff, Pinewood conferred with a representative of Framingham and “it was determined that it would be better for all parties ... to defend one law suit instead of two. ’ ’ As a result thereof a new drain was constructed which discharged the surface water at the boundary of the plaintiff’s land alone, avoiding the Raymond property.

There never was any natural watercourse “existent” from Pinewood’s land running over the plaintiff’s land. Pinewood’s construction “created a substantial additional burden” on the plaintiff’s land making the plaintiff’s drainage system inadequate to drain off the water and this resulted in water backing up and flooding the plaintiff’s land. Pinewood’s actions were “intentional,” “deliberate,” and “tortious.” It “knew the full effect and result of its con *240 struction and location of the exit point of the drainage system. of surface water” from Woodfield I, II, and III. Part of the surface water emptying onto the plaintiff’s land through Pinewood’s system came from land belonging to Framingham and this water “can be adequately diverted from the present system to another system in such fashion that” the plaintiff’s land “will he free of any future flow from . . . Framingham’s land.” A deed from Pinewood to one of the lot owners, typical of the hundreds granted, revealed that Pinewood retained ownership of the streets and drains in the development. The cost of correcting the condition by a proper drain under the plaintiff’s land was determined to he $28,130.60.

In his supplemental report the master found that twelve and a half acres of the plaintiff’s land were either flooded or affected by the flooding, and the value of that land to be $21,750, which figure was adopted by the court in its final decree.

1. The plaintiff contends that he is entitled to injunctive relief against both defendants and not merely damages from Pinewood. Subject to the possibility of certain additional findings of fact to which we shall refer later in this opinion we hold that injunctive relief should he decreed against Pinewood. Without the pretext of an easement or other legal right, Pinewood has artificially collected, channeled, and discharged its surface waters onto the plaintiff’s land. Such action constitutes a continuing trespass. Manning v. Woodlawn Cemetery Corp. 245 Mass. 250, 251. Fortier v. H. P. Hood & Sons, Inc. 307 Mass. 292, 296. Miller v. Darby, 336 Mass. 243, 246. An intentional and continuing trespass to real estate may he enjoined. Ottavia v. Savarese, 338 Mass. 330, 336. Damages are usually inadequate because the plaintiff is not to be compelled to part with his property for a sum of money. “The principal reason for this is that which lies at the foundation of the jurisdiction for decreeing specific performance of contracts for the sale of real estate. A particular piece of real estate cannot he replaced by any sum of money, however large, *241

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Field v. Hughes-Birch (In re Hughes-Birch)
499 B.R. 134 (D. Massachusetts, 2013)
Bennett v. Amadio
900 F. Supp. 2d 95 (D. Massachusetts, 2012)
Fease v. Vendenakker
29 Mass. L. Rptr. 567 (Massachusetts Superior Court, 2012)
Dilbert v. Hanover Insurance
825 N.E.2d 1071 (Massachusetts Appeals Court, 2005)
Providence & Worcester Railroad v. Rivard
19 Mass. L. Rptr. 81 (Massachusetts Superior Court, 2005)
Russo v. Gulla
15 Mass. L. Rptr. 49 (Massachusetts Superior Court, 2002)
Fortier v. Town of Essex
752 N.E.2d 818 (Massachusetts Appeals Court, 2001)
Guaranty-First Trust Co. v. Textron, Inc.
622 N.E.2d 597 (Massachusetts Supreme Judicial Court, 1993)
Attorney General v. Dime Savings Bank of New York, FSB
596 N.E.2d 1013 (Massachusetts Supreme Judicial Court, 1992)
Schleissner v. Town of Provincetown
538 N.E.2d 995 (Massachusetts Appeals Court, 1989)
Salim Aoude v. Mobil Oil Corporation
862 F.2d 890 (First Circuit, 1988)
Lane v. Commonwealth
517 N.E.2d 1281 (Massachusetts Supreme Judicial Court, 1988)
Kelley v. Tsiroyannis
3 Mass. Supp. 36 (Massachusetts Superior Court, 1981)
Franchi v. Boulger
425 N.E.2d 372 (Massachusetts Appeals Court, 1981)
Neponset Reservoir Corp. v. Bashaw
391 N.E.2d 911 (Massachusetts Appeals Court, 1979)
Tucker v. Badoian
384 N.E.2d 1195 (Massachusetts Supreme Judicial Court, 1978)
Kattor v. Sabatini
351 N.E.2d 553 (Massachusetts Appeals Court, 1976)
Hamilton v. Planning Board
345 N.E.2d 906 (Massachusetts Appeals Court, 1976)
Howe v. DiPIERRO MANUFACTURING CO. INC.
294 N.E.2d 495 (Massachusetts Appeals Court, 1973)
Department of Public Health v. Cumberland Cattle Co.
282 N.E.2d 895 (Massachusetts Supreme Judicial Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
186 N.E.2d 712, 345 Mass. 236, 1962 Mass. LEXIS 684, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chesarone-v-pinewood-builders-inc-mass-1962.