Chesapeake & O. Ry. Co. v. Gorman

188 S.W.2d 316, 300 Ky. 230, 1945 Ky. LEXIS 517
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedJune 8, 1945
StatusPublished
Cited by2 cases

This text of 188 S.W.2d 316 (Chesapeake & O. Ry. Co. v. Gorman) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chesapeake & O. Ry. Co. v. Gorman, 188 S.W.2d 316, 300 Ky. 230, 1945 Ky. LEXIS 517 (Ky. 1945).

Opinion

Opinion op the Court by

Judge Thomas

Reversing.

The appellees, and defendants below, Charles E. Gorman and Arthur Gorman, á partnership doing business under the name of Gorman Construction Company, were constructing a section of a state highway in Floyd County, Kentucky, in 1938, under a contract they had entered into with the State Highway Commission.

An essential material in the performance of their contract was crushed rock, which was transported from a quarry located within this Commonwealth to a nearby station called Eastern on appellant’s railroad traversing Floyd county. There was a depot at that place and a sidetrack, but no agent was maintained there, and it apparently had become abandoned as a station. The sidetrack of appellant at Eastern was one-half mile from the highway the appellees were constructing, and about *231 midway that distance was a stream, apparently immediately between two hills called “Little Beaver Creek.” There was an old unballasted county road running from the station to the highway under construction which, of course, crossed Little Beaver Creek over which there was no bridge, but only a ford as a crossing. There was also a constructed footbridge considerably higher than the banks of the creek. In order to repair that half-mile of the old county road so as to enable appellees to truck the stone from the station and carry it to and spread it upon the highway they were constructing, they repaired that stretch of road, which partly consisted in laying four feet tiling in the bed of the creek in the old ford and surfacing the tiling with concrete to the height of what was supposed to be the usual and ■ ordinary water carried by the creek.

In June, July and August of 1938 there were unusual rains in the vicinity and the territory drained by the creek, which overflowed the bridge that defendants had constructed across it for the purpose stated, and which prevented the use of trucks between the highway and the station where the cars containing the stone were spotted on the sidetrack. Appellees had therefore obtained the permission of appellant to excavate a space under the sidetrack — which was built on a dump — into which the crushed stone might be emptied from the hopper cars containing it into a conveyor placed in the opening under the track and carried it to, and deposited it in trucks, after which it was carried over the road referred to to the place of deposit on the highway which was the only one traversing that space over which vehicles might pass.

The parties were operating at all times involved in this litigation under a schedule of tariff rates (including demurrage) which appellant had previously filed with both the Federal Interstate Commerce Commission, and the Eailroad Commission of Kentucky. Liability charges, as well as free time within which the consignee (defendants here) was given to unload the freight, were stipulated in the schedule filed with the Kentucky Eailroad Commission, and also provisions for extending the period of free time under certain conditions, among which was “because of high water or snow drifts it is impossible during the prescribed free time to get to the *232 cars for loading or unloading.” (Our emphasis.) But even under that provision the free time was only extended as therein set out. Such provisions are contained in Paragraph 1 of Section A of Rule 8 in the filed schedule. Paragraph 4 of the same Rule (No. 8) says:

“When because of floods, earthquakes, hurricanes or tornadoes, and conditions in the devastated area resulting therefrom, it is impossible for a consignor or consignee to get to or to load or unload, a car, the detention directly chargeable thereto will be eliminated in computing demurrage. ’ ’

Rule 9 of the schedule prescribes that a carrier and the consignee, or consignor (as the case may be), may enter into what is called an “Average Agreement” which is explained to be that the one liable for demurrage may obtain a credit for unconsumed free time in unloading freight from cars in which it was transported and which might be credited on excess time in unloading other cars. Section E of the same Rule prescribes: “A party who enters into this Average Agreement shall not * * * be entitled to cancellation or refund of demurrage charges under Section A, Paragraph 1 of Rule 8 * * * except when bunching has been caused by floods, earthquakes, hurricanes or tornadoes and conditions in the devastated area resulting therefrom, strikes of carrier’s employees etc.” It is therefore seen from the quoted excerpt from Section E of Rule 9 under the Average Agreement which the parties had entered into that Paragraph 1 of Section A of Rule 8 becomes eliminated as an excuse for not paying demurrage in failing to load or unload freight within the prescribed free time. However, no part of Section E of Rule 9 eliminates the nonliability for demur-rage of the consignee when the delay over and above his free time for unloading the freight was caused by the conditions set forth in Paragraph 4 of Section A of Rule 8, inserted above.

By the delay of appellees in unloading the cars they incurred liability under the schedule herein to the defendants for demurrage to the amount of $367.40 in the month of June of the year referred to, and the amount of $1,895.30 during the month of July of the same year; but the amount chargeable during the month of August was admitted by appellees and is not involved in the case.

*233 Appellant sued appellees in the Fleming circuit court to recover the alleged demurrage due for the months of June and July. Appellees’ answer denied liability for any of the amount sought to be recovered, upon the ground that inserted Paragraph 4 of Section A of Rule 8 supra relieved them of such liability. The facts, substantially as above stated, were agreed to in the filed stipulation which was signed by the parties. The cause was then submitted to the court without the intervention of a jury, and it dismissed appellant’s petition, evidently upon the sole ground that the facts as hereinbefore outlined brought the case within Paragraph 4 of Section A of Rule 8 supra. Appellant’s motion for a new trial was overruled from which it prosecutes this appeal.

It will be observed that by Paragraph 4 of Section A of Rule 8 of the filed schedule a consignor or consignee is relieved of liability for demurrage because of floods, earthquakes, hurricanes or tornadoes, only when such phenomena renders the devastated area “impossible for a consignor or consignee to get to or to load or unload a car.” (Our emphasis.) It does not say that exemption from the payment of demurrage will be allowed to any one guilty of the delay when the conditions enumerated were such as to disable the one liable to transport the freight from the terminal of the shipment to the place where it was to be employed by the consignee with either a truck or other vehicle, since the paragraph prescribed for nonliability for the causes therein outlined only when it is impossible for him to get to or to load or unload the freight from the car by any means adaptable to the particular freight which, as is shown in this case, is stone that could not be injured or damaged by unloading it from the car onto the ground and later carting it away when conditions permitting that to be done are restored.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riddle v. City of Providence
781 S.W.2d 41 (Court of Appeals of Kentucky, 1989)
Missouri Pacific Railroad Company v. Terrell
410 S.W.2d 356 (Missouri Court of Appeals, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
188 S.W.2d 316, 300 Ky. 230, 1945 Ky. LEXIS 517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chesapeake-o-ry-co-v-gorman-kyctapphigh-1945.