Cherco Properties, Inc. v. Law, Snakard & Gambill, P.C.

985 S.W.2d 262, 1999 Tex. App. LEXIS 563, 1999 WL 35350
CourtCourt of Appeals of Texas
DecidedJanuary 28, 1999
Docket2-97-131-CV
StatusPublished
Cited by68 cases

This text of 985 S.W.2d 262 (Cherco Properties, Inc. v. Law, Snakard & Gambill, P.C.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cherco Properties, Inc. v. Law, Snakard & Gambill, P.C., 985 S.W.2d 262, 1999 Tex. App. LEXIS 563, 1999 WL 35350 (Tex. Ct. App. 1999).

Opinion

*264 OPINION

SAM J. DAY, Justice.

This appeal results from a judgment rendered in accordance -with the terms of a written settlement agreement between the parties to this suit, Appellant CherCo Properties, Inc. (CherCo), and Appellees Law, Snakard & Gambill, P.C., (Law) and Calhoun & Stacy f/k/a Calhoun, Gump, Spillman & Stacy, P.C. (Calhoun). Because the trial court did not err in rendering judgment on the parties’ settlement agreement and in granting summary judgment in favor of Ap-pellees, we affirm.

I. BACKGROUND

CherCo sued Appellees for legal malpractice for their work on a lawsuit involving several oil and gas wells in Cherokee County, Texas. On December 12, 1995, before the malpractice trial began, the parties announced to the trial court and in front of the jury that they had reached a settlement. That same day, the settlement was reduced to writing and signed by each party. The parties’ written agreement, which was handwritten by CherCo’s attorney, read in its entirety as follows:

Parties:
a) Calhoun & Stacey, P.C.
b) Law Snakard & Gambill, P.C.
c) CherCo Properties, Inc., & Ayers related companies
Consideration:
a) Calhoun & Stacey, P.C. pays CherCo $15,000.00
b) Law Snakard & Gambill pays CherCo $30,000.00 & returns CherCo’s $ sanctions check of $5,560.00
e) All parties bear their own costs and attys fees
d) All parties execute mutual releases including a release of Ralph Ayers & related companies as to any and all claims
e)All parties agree to indemnify one another for any claims that could have been brought by through or under them

The agreement was dated December 12,1995 and signed by representatives of CherCo and Appellees. Law returned the $5,560 sanctions check to CherCo that same day. 1

On March 8, 1996, Law drafted a formal settlement document incorporating the terms of the agreement and sent it to CherCo for approval. CherCo, however, did not approve, and a flurry of correspondence ensued regarding additional terms the parties wanted to include in the final document. In May 1996, CherCo threatened to file a motion to enforce the agreement. Instead of following through on its threat, CherCo waited until September 13, 1996 and filed a motion to set the matter for trial on the jury docket, contending that the settlement had failed and it had withdrawn its consent to the agreement. CherCo also asserted that the written settlement agreement was unenforceable because it did not include a time for performance.

A week later, Law filed the parties’ handwritten settlement agreement with the trial court. On November 8, Law sent another draft of the final agreement to CherCo and tendered payment of $30,000. Several days later, CherCo returned the check and notified Law that the formal agreement was still unacceptable and it was proceeding to have the matter reset for trial.

On December 18, 1996, Law filed a counterclaim alleging that CherCo had breached the written settlement agreement and asking the trial court to specifically enforce the agreement. On December 19, 1996 — more than one year after the parties signed the settlement agreement — Law filed a motion to enforce the agreement or alternatively, a motion for summary judgment. Attached to the motion was the parties’ handwritten agreement and evidence that CherCo had accepted the sanctions check returned by Law on December 12, 1995, and that Law had tendered a check for $30,000 to CherCo in November 1996 that CherCo refused to accept.

*265 After a hearing, the trial court found that no genuine issue of material fact existed and granted Law’s motion to enforce. The trial court rendered judgment in accordance with the terms of the parties’ December 12th agreement and assessed attorney’s fees, future attorney’s fees, costs, and pre-judgment interest against CherCo.

II. THE SETTLEMENT AGREEMENT

In its first four points, CherCo contends that the parties’ settlement agreement was unenforceable under Texas law and raises the following issues:

(1) What was the effect of CherCo withdrawing its consent to the parties’ agreement?
(2) Did the omission of a time for performance render the agreement unenforceable (in other words, was time of performance a material term)?
(3) Was the trial court precluded from implying a reasonable time for performance?
(4) Under the circumstances of this case, was Law’s performance within a reasonable time as a matter of law?

A. Rule 11

Under Rule 11 of the Texas Rules of Civil Procedure, no agreement between the attorneys or parties to a suit is enforceable unless it is in writing, signed, and filed with the papers as part of the record, or unless it is made in open court and entered of record. See TexJR. Civ. P. 11. A settlement agreement must comply with Rule 11 to be enforceable. See Padilla v. LaFrance, 907 S.W.2d 454, 460 (Tex.1995). To satisfy the “in writing” provision of Rule 11, the same contract principles apply that are used to determine when a “writing” satisfies the statute of frauds. See id. Thus, a Rule 11 settlement agreement is not enforceable unless it is complete within itself as to every material detail and contains all the essential elements of the agreement so the contract can be ascertained from the writing, without resort to oral testimony. See id.

B. Applicable Case Law

Padilla is dispositive in this case. In Padilla, the parties had exchanged a series of letters regarding terms of a settlement while a lawsuit was pending against Enrique Padilla. See id. at 455. Padilla contended that the letters represented a written settlement between the parties and asked the trial court to enforce the agreement. See id. at 457. The plaintiffs contended that there was no written agreement between the parties. Furthermore, plaintiffs argued, even if there had been an agreement, it could not be enforced because (1) they had withdrawn their consent before judgment had been rendered on the agreement, and (2) Padilla had failed to file the letters until after plaintiffs had withdrawn their consent. See id.

The Texas Supreme Court held that Rule 11 does not require a writing to be filed in the trial court before the other party withdraws its consent. Rather, the purpose of the filing requirement is satisfied “so long as the agreement is filed before it is sought to be enforced.” Id. at 461.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Armando Velardez v. Carlos E. Parra Jr.
Court of Appeals of Texas, 2022
Young v. Ershick
E.D. Texas, 2022
MKM Engineers, Inc. v. Guzder
476 S.W.3d 770 (Court of Appeals of Texas, 2015)
William Scott v. Brad Livingston
628 F. App'x 900 (Fifth Circuit, 2015)
Julie Johnson v. Bank of America, N.A.
Court of Appeals of Texas, 2014
DaimlerChrysler Motors Co., LLC v. Manuel
362 S.W.3d 160 (Court of Appeals of Texas, 2012)
Cunningham v. Zurich American Insurance Co.
352 S.W.3d 519 (Court of Appeals of Texas, 2011)
Allegiance Hillview, L.P. v. Range Texas Production, LLC
347 S.W.3d 855 (Court of Appeals of Texas, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
985 S.W.2d 262, 1999 Tex. App. LEXIS 563, 1999 WL 35350, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cherco-properties-inc-v-law-snakard-gambill-pc-texapp-1999.