Cherco, Inc. v. Town Square Mall Associates, Inc.

246 A.D.2d 850, 668 N.Y.S.2d 404, 1998 N.Y. App. Div. LEXIS 516

This text of 246 A.D.2d 850 (Cherco, Inc. v. Town Square Mall Associates, Inc.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cherco, Inc. v. Town Square Mall Associates, Inc., 246 A.D.2d 850, 668 N.Y.S.2d 404, 1998 N.Y. App. Div. LEXIS 516 (N.Y. Ct. App. 1998).

Opinion

Peters, J.

Appeal from an order of the Supreme Court (Rose, J.), entered December 10, 1996 in Broome County, which granted defendants’ motion for summary judgment dismissing the complaint.

This action alleges nonpayment in connection with plaintiffs work on defendants’ project known as Town Square Mall in the Town of Vestal, Broome County. It remains undisputed that there were at least two contracts between these parties, one for $235,000 and the second for $225,000. Plaintiff contends that defendants asked it to perform work outside of the scope of such contracts in return for additional compensation and that these oral change orders amounted to $1,476,325 due plaintiff, with only $983,551 paid. Upon defendants’ refusal to pay the outstanding balance, plaintiff commenced this action alleging breach of contract, quantum meruit, implied contract and fraud.

Defendants moved for dismissal alleging the existence of both releases in connection with these two contracts and a third contract with its attendant release. Although plaintiff acknowledged the release of the first two contracts, it denied signing both the third contract and its release, maintaining that there existed an oral contract between the parties.

In its January 1994 order, Supreme Court found that the releases extinguished any claims against defendants alleging, breach of contract, implied contract or quantum meruit which arose from the first two contracts. With respect to the third contract, whether oral or written, it found a question of fact to be raised as to its very existence, let alone release, and the amount of recovery, if any, still due plaintiff. With the fraud claims dismissed in their entirety, defendants thereafter pursued discovery solely in connection with the amount alleged to be outstanding pursuant to the third contract.

Defendants commenced with a request for the discovery of relevant documents. After receiving “a carton filled with documents” which were “incapable of interpretation”, it deposed plaintiffs president on three separate occasions. According to defendants, such depositions yielded little information. After serving interrogatories seeking specific information pertaining [851]*851only to the damages claimed, plaintiffs perfunctory response triggered a motion to compel. On August 16, 1996, Supreme Court ordered plaintiff to serve, within 30 days of the date of that decision, verified responses to the interrogatories posed. It specified that such responses should “clearly state all amounts claimed as damages on plaintiffs remaining cause of action for services and equipment unrelated to the first two contracts * * * how each amount was calculated, and, at a minimum, the detailed information concerning those services and equipment which was requested by defendants”. Recognizing the overproduction of documents submitted by plaintiff, the court specifically ordered that the “responses shall not require defendants to perform any arithmetical computation in order to ascertain the requested information”.

Upon reviewing plaintiffs new responses, defendants again claimed them to be inadequate. After further communication and extensions of time, defendants moved to dismiss the final claim remaining from the January 1994 order. Counsel for plaintiff explained that he had a vigorous work schedule which precluded him from having the ability to meticulously detail the information requested and that plaintiff had already produced those documents from which the information could be culled. Further explaining that it was required to provide a monumental amount of information in “an unreasonably short period of time” since the entire billing method “on this contract agreement” was orally changed in mid-June to a “costs plus” basis, plaintiff represented that it would be “prepared to produce invoices” which would demonstrate such change by the time of trial. Notwithstanding its inclusion of a revised computation of employee, equipment and subcontractor costs, Supreme Court, by order entered December 10, 1996, granted defendants’ motion for summary judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burke v. Crosson
647 N.E.2d 736 (New York Court of Appeals, 1995)
Clark-Fitzpatrick, Inc. v. Long Island Rail Road
516 N.E.2d 190 (New York Court of Appeals, 1987)
Panetta v. Tonetti
182 A.D.2d 977 (Appellate Division of the Supreme Court of New York, 1992)
De Thomasis v. Riccardi
194 A.D.2d 849 (Appellate Division of the Supreme Court of New York, 1993)
Rivera v. Our Lady of Knox Roman Catholic Church
197 A.D.2d 764 (Appellate Division of the Supreme Court of New York, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
246 A.D.2d 850, 668 N.Y.S.2d 404, 1998 N.Y. App. Div. LEXIS 516, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cherco-inc-v-town-square-mall-associates-inc-nyappdiv-1998.