Chemical Insulation Co., Inc. v. Arco Builders, Inc.
Opinion
Judgment rendered August 9, 2023.
Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.
No. 55,230-CA
COURT OF APPEAL
SECOND CIRCUIT
STATE OF LOUISIANA
*****
CHEMICAL INSULATION CO., INC. Plaintiff-Appellant versus
ARCO BUILDERS, INC. Defendant-Appellee
*****
Appealed from the
Fourth Judicial District Court for the Parish of Ouachita, Louisiana Trial Court No. 2022-0866
Honorable Daniel J. Ellender, Judge
*****
DAVID O. MOONEY Counsel for Appellant
DAVENPORT, FILES & KELLY, LLP Counsel for Appellee By: M. Shane Craighead
*****
Before PITMAN, ROBINSON, and MARCOTTE, JJ.
MARCOTTE, J.
This appeal arises from the Fourth Judicial District Court, Parish of Ouachita, the Honorable Daniel J. Ellender presiding. Chemical Insulation Co., Inc. (“Chemical” or “appellant”) appeals the trial court’s granting of the peremptory exception of peremption filed by Arco Builders, Inc. (“Arco” or “appellee”), finding that Chemical’s claim was time-barred under La. R.S. 9:2772, since it was brought after the statute’s five-year peremptive period for claims arising out of a construction project had run. For the following reasons, we affirm.
FACTS
The facts are not in dispute. Arco undertook a construction project for the West Carroll Memorial Hospital in Oak Grove, West Carroll Parish, Louisiana, in 2013. Arco then subcontracted with Chemical to provide roofing services on the project. The project was completed on or before April 30, 2014, and was occupied by the owner in May 2014.
More than seven years later, on March 16, 2022, Chemical filed suit against Arco seeking to recover amounts it claimed were owed by Arco pursuant to the contract to provide roofing services on the construction project. In its petition, Chemical alleged that it fully performed the roofing services contemplated by the contract but that Arco only paid $69,995.70, rather than the full amount owed of $77,773. Chemical claimed it was owed $7,777.30 plus legal interest.
Arco filed its answer on April 20, 2022, denying that it owed any money to Chemical. Arco asserted that, contemporaneously with the roofing services contract in West Carroll Parish, Chemical contracted with Arco to provide roofing services on a nursing home renovation project in
Natchitoches, Louisiana. Arco claimed that Chemical performed the work in an unworkmanlike manner, resulting in significant monetary damages to Arco, including protracted litigation. Arco further claimed that although the damages caused by Chemical to Arco remain unsatisfied, Arco applied the law of compensation to a portion of Chemical’s obligation to Arco by offsetting amounts held as retainage on the West Carroll Memorial Hospital project.
In its answer, Arco also affirmatively pled the provisions of La. C.C.
art. 1893, which concerns the extinguishment of an obligation by compensation, as well as La. R.S. 9:2772, which establishes a peremptive period for actions arising out of construction projects.
On May 9, 2022, Arco filed its peremptory exception of peremption and memorandum in support thereof. In its exception, Arco reiterated its position that it owes Chemical nothing based upon the law of compensation, but stated that regardless of its defense on the merits, Chemical’s claim is perempted pursuant to La. R.S. 9:2772, which establishes a five-year peremptive period for contractual disputes between general contractors and subcontractors. Arco argued that Chemical’s claims against Arco arising from the West Carroll Memorial Hospital project were extinguished five years from when the owner occupied the facility after the project was completed.
On September 15, 2022, Chemical filed its memorandum in opposition to Arco’s exception of peremption. In its opposition, Chemical asserted that its claim is timely because the applicable prescriptive period is ten years under La. C.C. art. 3457. Chemical claimed that the five-year peremptive period under La. R.S. 9:2772 does not apply, because that statute
only considers actions involving deficiencies in construction, not claims for an unpaid debt by a general contractor. Chemical further asserted that the cases cited by Arco in support of its exception are distinguishable in that they all involve claims against a general contractor arising from construction defects, which is not the case here.
On September 19, 2022, Arco filed its reply memorandum in support of its peremptory exception. Arco asserted that just because La. C.C. art. 3457 contains a broad prescriptive period of ten years for contractual obligations does not mean that the court should not apply the specific peremptive period of five years to claims arising from the construction of immovables. Regarding Chemical’s attempt to distinguish the cited cases, Arco pointed out that in each case, the provisions of La. R.S. 9:2772 were applied to claims between general contractors and subcontractors arising from those parties’ contracts relating to the construction of immovable property.
On September 23, 2023, the trial court held a hearing on Arco’s peremptory exception and ruled in favor of Arco. In its oral ruling, the trial court held that Chemical’s claim was perempted by La. R.S. 9:2772 because subsection (B)(3) of the statute extends to “every demand” whether brought by the owner or “any other person.” Chemical now appeals.
DISCUSSION
Chemical’s sole assignment of error is that the trial court erred in granting Arco’s exception of peremption. Chemical argues that the trial court erred because La. R.S. 9:2772 does not apply to a contractual claim for payment brought against a general by a subcontractor completely unrelated
to any deficiencies in construction. Appellant’s argument focuses on the reason given by the legislature for the creation of the statute in 1964:
To amend Title 9 of the Louisiana Revised Statutes of 1950 by adding a new section to be designated as Section 2772, limiting the time within which actions may be brought for deficiencies in design, planning, inspection, supervision or construction of improvements to immovable property or for property damage, personal injury or wrongful death arising from any such deficiency.”
Chemical claims that because the reason given for creating the statute mentions workmanship deficiencies, the statute is only meant to cover actions arising from such deficiencies.
Chemical also argues that the title of the statute, “peremptive period for actions involving deficiencies in surveying, design, supervision, or construction of immovables and improvements thereon,” means that it only applies to claims arising from deficiencies in the areas covered by the statute. Chemical’s argument is essentially that since its claim is strictly one for services rendered on a construction project, it is not subject to the five- year peremptive period of La. R.S. 9:2772, which only extends to claims involving workmanship deficiencies. Appellant asks this court to reverse the trial court’s judgment and remand the matter for further proceedings.
Appellee’s argument focuses on the plain language of La. R.S.
9:2772, which specifically states that it applies to contractual claims and any claims “otherwise arising out of” a construction project of an immovable. Appellee also argues that subsection (B)(3) of the statute clarifies that except as otherwise provided within the statute, the “peremptive period shall extend to every demand, whether brought by direct action or for contribution or indemnity or by third-party practice, and whether brought by the owner or by any other person.”
Free access — add to your briefcase to read the full text and ask questions with AI
Chemical Insulation Co., Inc. v. Arco Builders, Inc. (Chemical Insulation Co., Inc. v. Arco Builders, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.