Chemical Insulation Co., Inc. v. Arco Builders, Inc.

CourtLouisiana Court of Appeal
DecidedAugust 9, 2023
Docket55,230-CA
StatusPublished

This text of Chemical Insulation Co., Inc. v. Arco Builders, Inc. (Chemical Insulation Co., Inc. v. Arco Builders, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chemical Insulation Co., Inc. v. Arco Builders, Inc., (La. Ct. App. 2023).

Opinion

Judgment rendered August 9, 2023. Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.

No. 55,230-CA

COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA

*****

CHEMICAL INSULATION CO., INC. Plaintiff-Appellant

versus

ARCO BUILDERS, INC. Defendant-Appellee

Appealed from the Fourth Judicial District Court for the Parish of Ouachita, Louisiana Trial Court No. 2022-0866

Honorable Daniel J. Ellender, Judge

DAVID O. MOONEY Counsel for Appellant

DAVENPORT, FILES & KELLY, LLP Counsel for Appellee By: M. Shane Craighead

Before PITMAN, ROBINSON, and MARCOTTE, JJ. MARCOTTE, J.

This appeal arises from the Fourth Judicial District Court, Parish of

Ouachita, the Honorable Daniel J. Ellender presiding. Chemical Insulation

Co., Inc. (“Chemical” or “appellant”) appeals the trial court’s granting of the

peremptory exception of peremption filed by Arco Builders, Inc. (“Arco” or

“appellee”), finding that Chemical’s claim was time-barred under La. R.S.

9:2772, since it was brought after the statute’s five-year peremptive period

for claims arising out of a construction project had run. For the following

reasons, we affirm.

FACTS

The facts are not in dispute. Arco undertook a construction project for

the West Carroll Memorial Hospital in Oak Grove, West Carroll Parish,

Louisiana, in 2013. Arco then subcontracted with Chemical to provide

roofing services on the project. The project was completed on or before

April 30, 2014, and was occupied by the owner in May 2014.

More than seven years later, on March 16, 2022, Chemical filed suit

against Arco seeking to recover amounts it claimed were owed by Arco

pursuant to the contract to provide roofing services on the construction

project. In its petition, Chemical alleged that it fully performed the roofing

services contemplated by the contract but that Arco only paid $69,995.70,

rather than the full amount owed of $77,773. Chemical claimed it was owed

$7,777.30 plus legal interest.

Arco filed its answer on April 20, 2022, denying that it owed any

money to Chemical. Arco asserted that, contemporaneously with the roofing

services contract in West Carroll Parish, Chemical contracted with Arco to

provide roofing services on a nursing home renovation project in Natchitoches, Louisiana. Arco claimed that Chemical performed the work

in an unworkmanlike manner, resulting in significant monetary damages to

Arco, including protracted litigation. Arco further claimed that although the

damages caused by Chemical to Arco remain unsatisfied, Arco applied the

law of compensation to a portion of Chemical’s obligation to Arco by

offsetting amounts held as retainage on the West Carroll Memorial Hospital

project.

In its answer, Arco also affirmatively pled the provisions of La. C.C.

art. 1893, which concerns the extinguishment of an obligation by

compensation, as well as La. R.S. 9:2772, which establishes a peremptive

period for actions arising out of construction projects.

On May 9, 2022, Arco filed its peremptory exception of peremption

and memorandum in support thereof. In its exception, Arco reiterated its

position that it owes Chemical nothing based upon the law of compensation,

but stated that regardless of its defense on the merits, Chemical’s claim is

perempted pursuant to La. R.S. 9:2772, which establishes a five-year

peremptive period for contractual disputes between general contractors and

subcontractors. Arco argued that Chemical’s claims against Arco arising

from the West Carroll Memorial Hospital project were extinguished five

years from when the owner occupied the facility after the project was

completed.

On September 15, 2022, Chemical filed its memorandum in

opposition to Arco’s exception of peremption. In its opposition, Chemical

asserted that its claim is timely because the applicable prescriptive period is

ten years under La. C.C. art. 3457. Chemical claimed that the five-year

peremptive period under La. R.S. 9:2772 does not apply, because that statute 2 only considers actions involving deficiencies in construction, not claims for

an unpaid debt by a general contractor. Chemical further asserted that the

cases cited by Arco in support of its exception are distinguishable in that

they all involve claims against a general contractor arising from construction

defects, which is not the case here.

On September 19, 2022, Arco filed its reply memorandum in support

of its peremptory exception. Arco asserted that just because La. C.C. art.

3457 contains a broad prescriptive period of ten years for contractual

obligations does not mean that the court should not apply the specific

peremptive period of five years to claims arising from the construction of

immovables. Regarding Chemical’s attempt to distinguish the cited cases,

Arco pointed out that in each case, the provisions of La. R.S. 9:2772 were

applied to claims between general contractors and subcontractors arising

from those parties’ contracts relating to the construction of immovable

property.

On September 23, 2023, the trial court held a hearing on Arco’s

peremptory exception and ruled in favor of Arco. In its oral ruling, the trial

court held that Chemical’s claim was perempted by La. R.S. 9:2772 because

subsection (B)(3) of the statute extends to “every demand” whether brought

by the owner or “any other person.” Chemical now appeals.

DISCUSSION

Chemical’s sole assignment of error is that the trial court erred in

granting Arco’s exception of peremption. Chemical argues that the trial

court erred because La. R.S. 9:2772 does not apply to a contractual claim for

payment brought against a general by a subcontractor completely unrelated

3 to any deficiencies in construction. Appellant’s argument focuses on the

reason given by the legislature for the creation of the statute in 1964:

To amend Title 9 of the Louisiana Revised Statutes of 1950 by adding a new section to be designated as Section 2772, limiting the time within which actions may be brought for deficiencies in design, planning, inspection, supervision or construction of improvements to immovable property or for property damage, personal injury or wrongful death arising from any such deficiency.”

Chemical claims that because the reason given for creating the

statute mentions workmanship deficiencies, the statute is only meant

to cover actions arising from such deficiencies.

Chemical also argues that the title of the statute, “peremptive period

for actions involving deficiencies in surveying, design, supervision, or

construction of immovables and improvements thereon,” means that it only

applies to claims arising from deficiencies in the areas covered by the

statute. Chemical’s argument is essentially that since its claim is strictly one

for services rendered on a construction project, it is not subject to the five-

year peremptive period of La. R.S. 9:2772, which only extends to claims

involving workmanship deficiencies. Appellant asks this court to reverse

the trial court’s judgment and remand the matter for further proceedings.

Appellee’s argument focuses on the plain language of La. R.S.

9:2772, which specifically states that it applies to contractual claims and any

claims “otherwise arising out of” a construction project of an immovable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bunge Corp. v. Gatx Corp.
557 So. 2d 1376 (Supreme Court of Louisiana, 1990)
Rando v. Anco Insulations Inc.
16 So. 3d 1065 (Supreme Court of Louisiana, 2009)
ACADEMY PAfRK IMP. ASS'N v. City of New Orleans
469 So. 2d 2 (Louisiana Court of Appeal, 1985)
Thrasher Construction, Inc. v. Gibbs Residential, L.L.C.
197 So. 3d 283 (Louisiana Court of Appeal, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Chemical Insulation Co., Inc. v. Arco Builders, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/chemical-insulation-co-inc-v-arco-builders-inc-lactapp-2023.