Judgment rendered August 9, 2023. Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.
No. 55,230-CA
COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA
*****
CHEMICAL INSULATION CO., INC. Plaintiff-Appellant
versus
ARCO BUILDERS, INC. Defendant-Appellee
Appealed from the Fourth Judicial District Court for the Parish of Ouachita, Louisiana Trial Court No. 2022-0866
Honorable Daniel J. Ellender, Judge
DAVID O. MOONEY Counsel for Appellant
DAVENPORT, FILES & KELLY, LLP Counsel for Appellee By: M. Shane Craighead
Before PITMAN, ROBINSON, and MARCOTTE, JJ. MARCOTTE, J.
This appeal arises from the Fourth Judicial District Court, Parish of
Ouachita, the Honorable Daniel J. Ellender presiding. Chemical Insulation
Co., Inc. (“Chemical” or “appellant”) appeals the trial court’s granting of the
peremptory exception of peremption filed by Arco Builders, Inc. (“Arco” or
“appellee”), finding that Chemical’s claim was time-barred under La. R.S.
9:2772, since it was brought after the statute’s five-year peremptive period
for claims arising out of a construction project had run. For the following
reasons, we affirm.
FACTS
The facts are not in dispute. Arco undertook a construction project for
the West Carroll Memorial Hospital in Oak Grove, West Carroll Parish,
Louisiana, in 2013. Arco then subcontracted with Chemical to provide
roofing services on the project. The project was completed on or before
April 30, 2014, and was occupied by the owner in May 2014.
More than seven years later, on March 16, 2022, Chemical filed suit
against Arco seeking to recover amounts it claimed were owed by Arco
pursuant to the contract to provide roofing services on the construction
project. In its petition, Chemical alleged that it fully performed the roofing
services contemplated by the contract but that Arco only paid $69,995.70,
rather than the full amount owed of $77,773. Chemical claimed it was owed
$7,777.30 plus legal interest.
Arco filed its answer on April 20, 2022, denying that it owed any
money to Chemical. Arco asserted that, contemporaneously with the roofing
services contract in West Carroll Parish, Chemical contracted with Arco to
provide roofing services on a nursing home renovation project in Natchitoches, Louisiana. Arco claimed that Chemical performed the work
in an unworkmanlike manner, resulting in significant monetary damages to
Arco, including protracted litigation. Arco further claimed that although the
damages caused by Chemical to Arco remain unsatisfied, Arco applied the
law of compensation to a portion of Chemical’s obligation to Arco by
offsetting amounts held as retainage on the West Carroll Memorial Hospital
project.
In its answer, Arco also affirmatively pled the provisions of La. C.C.
art. 1893, which concerns the extinguishment of an obligation by
compensation, as well as La. R.S. 9:2772, which establishes a peremptive
period for actions arising out of construction projects.
On May 9, 2022, Arco filed its peremptory exception of peremption
and memorandum in support thereof. In its exception, Arco reiterated its
position that it owes Chemical nothing based upon the law of compensation,
but stated that regardless of its defense on the merits, Chemical’s claim is
perempted pursuant to La. R.S. 9:2772, which establishes a five-year
peremptive period for contractual disputes between general contractors and
subcontractors. Arco argued that Chemical’s claims against Arco arising
from the West Carroll Memorial Hospital project were extinguished five
years from when the owner occupied the facility after the project was
completed.
On September 15, 2022, Chemical filed its memorandum in
opposition to Arco’s exception of peremption. In its opposition, Chemical
asserted that its claim is timely because the applicable prescriptive period is
ten years under La. C.C. art. 3457. Chemical claimed that the five-year
peremptive period under La. R.S. 9:2772 does not apply, because that statute 2 only considers actions involving deficiencies in construction, not claims for
an unpaid debt by a general contractor. Chemical further asserted that the
cases cited by Arco in support of its exception are distinguishable in that
they all involve claims against a general contractor arising from construction
defects, which is not the case here.
On September 19, 2022, Arco filed its reply memorandum in support
of its peremptory exception. Arco asserted that just because La. C.C. art.
3457 contains a broad prescriptive period of ten years for contractual
obligations does not mean that the court should not apply the specific
peremptive period of five years to claims arising from the construction of
immovables. Regarding Chemical’s attempt to distinguish the cited cases,
Arco pointed out that in each case, the provisions of La. R.S. 9:2772 were
applied to claims between general contractors and subcontractors arising
from those parties’ contracts relating to the construction of immovable
property.
On September 23, 2023, the trial court held a hearing on Arco’s
peremptory exception and ruled in favor of Arco. In its oral ruling, the trial
court held that Chemical’s claim was perempted by La. R.S. 9:2772 because
subsection (B)(3) of the statute extends to “every demand” whether brought
by the owner or “any other person.” Chemical now appeals.
DISCUSSION
Chemical’s sole assignment of error is that the trial court erred in
granting Arco’s exception of peremption. Chemical argues that the trial
court erred because La. R.S. 9:2772 does not apply to a contractual claim for
payment brought against a general by a subcontractor completely unrelated
3 to any deficiencies in construction. Appellant’s argument focuses on the
reason given by the legislature for the creation of the statute in 1964:
To amend Title 9 of the Louisiana Revised Statutes of 1950 by adding a new section to be designated as Section 2772, limiting the time within which actions may be brought for deficiencies in design, planning, inspection, supervision or construction of improvements to immovable property or for property damage, personal injury or wrongful death arising from any such deficiency.”
Chemical claims that because the reason given for creating the
statute mentions workmanship deficiencies, the statute is only meant
to cover actions arising from such deficiencies.
Chemical also argues that the title of the statute, “peremptive period
for actions involving deficiencies in surveying, design, supervision, or
construction of immovables and improvements thereon,” means that it only
applies to claims arising from deficiencies in the areas covered by the
statute. Chemical’s argument is essentially that since its claim is strictly one
for services rendered on a construction project, it is not subject to the five-
year peremptive period of La. R.S. 9:2772, which only extends to claims
involving workmanship deficiencies. Appellant asks this court to reverse
the trial court’s judgment and remand the matter for further proceedings.
Appellee’s argument focuses on the plain language of La. R.S.
9:2772, which specifically states that it applies to contractual claims and any
claims “otherwise arising out of” a construction project of an immovable.
Free access — add to your briefcase to read the full text and ask questions with AI
Judgment rendered August 9, 2023. Application for rehearing may be filed within the delay allowed by Art. 2166, La. C.C.P.
No. 55,230-CA
COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA
*****
CHEMICAL INSULATION CO., INC. Plaintiff-Appellant
versus
ARCO BUILDERS, INC. Defendant-Appellee
Appealed from the Fourth Judicial District Court for the Parish of Ouachita, Louisiana Trial Court No. 2022-0866
Honorable Daniel J. Ellender, Judge
DAVID O. MOONEY Counsel for Appellant
DAVENPORT, FILES & KELLY, LLP Counsel for Appellee By: M. Shane Craighead
Before PITMAN, ROBINSON, and MARCOTTE, JJ. MARCOTTE, J.
This appeal arises from the Fourth Judicial District Court, Parish of
Ouachita, the Honorable Daniel J. Ellender presiding. Chemical Insulation
Co., Inc. (“Chemical” or “appellant”) appeals the trial court’s granting of the
peremptory exception of peremption filed by Arco Builders, Inc. (“Arco” or
“appellee”), finding that Chemical’s claim was time-barred under La. R.S.
9:2772, since it was brought after the statute’s five-year peremptive period
for claims arising out of a construction project had run. For the following
reasons, we affirm.
FACTS
The facts are not in dispute. Arco undertook a construction project for
the West Carroll Memorial Hospital in Oak Grove, West Carroll Parish,
Louisiana, in 2013. Arco then subcontracted with Chemical to provide
roofing services on the project. The project was completed on or before
April 30, 2014, and was occupied by the owner in May 2014.
More than seven years later, on March 16, 2022, Chemical filed suit
against Arco seeking to recover amounts it claimed were owed by Arco
pursuant to the contract to provide roofing services on the construction
project. In its petition, Chemical alleged that it fully performed the roofing
services contemplated by the contract but that Arco only paid $69,995.70,
rather than the full amount owed of $77,773. Chemical claimed it was owed
$7,777.30 plus legal interest.
Arco filed its answer on April 20, 2022, denying that it owed any
money to Chemical. Arco asserted that, contemporaneously with the roofing
services contract in West Carroll Parish, Chemical contracted with Arco to
provide roofing services on a nursing home renovation project in Natchitoches, Louisiana. Arco claimed that Chemical performed the work
in an unworkmanlike manner, resulting in significant monetary damages to
Arco, including protracted litigation. Arco further claimed that although the
damages caused by Chemical to Arco remain unsatisfied, Arco applied the
law of compensation to a portion of Chemical’s obligation to Arco by
offsetting amounts held as retainage on the West Carroll Memorial Hospital
project.
In its answer, Arco also affirmatively pled the provisions of La. C.C.
art. 1893, which concerns the extinguishment of an obligation by
compensation, as well as La. R.S. 9:2772, which establishes a peremptive
period for actions arising out of construction projects.
On May 9, 2022, Arco filed its peremptory exception of peremption
and memorandum in support thereof. In its exception, Arco reiterated its
position that it owes Chemical nothing based upon the law of compensation,
but stated that regardless of its defense on the merits, Chemical’s claim is
perempted pursuant to La. R.S. 9:2772, which establishes a five-year
peremptive period for contractual disputes between general contractors and
subcontractors. Arco argued that Chemical’s claims against Arco arising
from the West Carroll Memorial Hospital project were extinguished five
years from when the owner occupied the facility after the project was
completed.
On September 15, 2022, Chemical filed its memorandum in
opposition to Arco’s exception of peremption. In its opposition, Chemical
asserted that its claim is timely because the applicable prescriptive period is
ten years under La. C.C. art. 3457. Chemical claimed that the five-year
peremptive period under La. R.S. 9:2772 does not apply, because that statute 2 only considers actions involving deficiencies in construction, not claims for
an unpaid debt by a general contractor. Chemical further asserted that the
cases cited by Arco in support of its exception are distinguishable in that
they all involve claims against a general contractor arising from construction
defects, which is not the case here.
On September 19, 2022, Arco filed its reply memorandum in support
of its peremptory exception. Arco asserted that just because La. C.C. art.
3457 contains a broad prescriptive period of ten years for contractual
obligations does not mean that the court should not apply the specific
peremptive period of five years to claims arising from the construction of
immovables. Regarding Chemical’s attempt to distinguish the cited cases,
Arco pointed out that in each case, the provisions of La. R.S. 9:2772 were
applied to claims between general contractors and subcontractors arising
from those parties’ contracts relating to the construction of immovable
property.
On September 23, 2023, the trial court held a hearing on Arco’s
peremptory exception and ruled in favor of Arco. In its oral ruling, the trial
court held that Chemical’s claim was perempted by La. R.S. 9:2772 because
subsection (B)(3) of the statute extends to “every demand” whether brought
by the owner or “any other person.” Chemical now appeals.
DISCUSSION
Chemical’s sole assignment of error is that the trial court erred in
granting Arco’s exception of peremption. Chemical argues that the trial
court erred because La. R.S. 9:2772 does not apply to a contractual claim for
payment brought against a general by a subcontractor completely unrelated
3 to any deficiencies in construction. Appellant’s argument focuses on the
reason given by the legislature for the creation of the statute in 1964:
To amend Title 9 of the Louisiana Revised Statutes of 1950 by adding a new section to be designated as Section 2772, limiting the time within which actions may be brought for deficiencies in design, planning, inspection, supervision or construction of improvements to immovable property or for property damage, personal injury or wrongful death arising from any such deficiency.”
Chemical claims that because the reason given for creating the
statute mentions workmanship deficiencies, the statute is only meant
to cover actions arising from such deficiencies.
Chemical also argues that the title of the statute, “peremptive period
for actions involving deficiencies in surveying, design, supervision, or
construction of immovables and improvements thereon,” means that it only
applies to claims arising from deficiencies in the areas covered by the
statute. Chemical’s argument is essentially that since its claim is strictly one
for services rendered on a construction project, it is not subject to the five-
year peremptive period of La. R.S. 9:2772, which only extends to claims
involving workmanship deficiencies. Appellant asks this court to reverse
the trial court’s judgment and remand the matter for further proceedings.
Appellee’s argument focuses on the plain language of La. R.S.
9:2772, which specifically states that it applies to contractual claims and any
claims “otherwise arising out of” a construction project of an immovable.
Appellee also argues that subsection (B)(3) of the statute clarifies that except
as otherwise provided within the statute, the “peremptive period shall extend
to every demand, whether brought by direct action or for contribution or
indemnity or by third-party practice, and whether brought by the owner or
by any other person.” 4 Arco argues that Chemical’s claim about the meaning of the statute’s
title is unfounded, since La. R.S. 1:13 specifically provides that “headings to
sections, source notes, and cross references are given for purposes of
convenient reference and do not constitute part of the law.” Arco’s
argument is essentially that the language of the statute is clear that actions
arising from the construction of immovables are perempted upon the passage
of five years after occupation of the improvement by the owner, and it is
undisputed that Chemical filed its claim beyond the five-year period.
Appellee requests this court to affirm the trial court’s ruling sustaining its
peremptory exception of peremption.
Peremption is a period of time fixed by law for the existence of a
right. La. C.C. art. 3458. The function of the peremptory exception is to
have the plaintiff’s action declared legally nonexistent, or barred by effect of
law, and hence this exception tends to dismiss or defeat the action. La.
C.C.P. art. 923. Peremption may not be renounced, interrupted, or
suspended. La. C.C. art. 3461.
When the peremptive period has run, the cause of action itself is
extinguished unless timely exercised. Rando v. Anco Insulations Inc., 08-
1163 (La. 5/22/09), 16 So. 3d 1065. The rules governing the burden of
proof as to prescription apply to peremption. Mgmt. Grp. Four, L.L.C. v. L
B Elec., L.L.C., 54,550 (La. App. 2 Cir. 6/29/22), 342 So. 3d 1123, writ
denied, 22-01160 (La. 11/1/22), 349 So. 3d 6. If prescription is evident on
the face of the pleadings, the burden shifts to the plaintiff to show the action
has not prescribed. Id.
A judgment granting a peremptory exception of peremption is
generally reviewed de novo, because the exception raises a legal question 5 and involves the interpretation of a statute. Thrasher Const. v. Gibbs
Residential, L.L.C., 15-0607, p. 6 (La. App. 4 Cir. 6/29/16), 197 So.3d 283.
Arco asserts that Chemical’s claim is perempted pursuant to La. R.S.
9:2772, which provides, in pertinent part:
A. Except as otherwise provided in this Subsection, no action, whether ex conctractu, ex delicto, or otherwise, including but not limited to an action for failure to warn, to recover on a contract, or to recover damages or otherwise arising out of an agreement of planning, construction, design or building immovable . . . property shall be brought against any person performing or furnishing . . . the design, planning, supervision, inspection or observation of construction or the construction of immovables . . . … (1)(b) . . . more than five years after the improvement has been thus occupied by the owner. … (B)(3) Except as otherwise provided in Subsection A of this Section, this peremptive period shall extend to every demand, whether brought by direct action or for contribution or indemnity or by third-party practice, and whether brought by the owner or by any other person.
Chemical claims that this statute does not apply to a contractual
claim for payment brought against a general contractor by a subcontractor
that is unrelated to any deficiencies on the project. The plain language of the
statute indicates otherwise. La. R.S. 9:2772 specifically states that it applies
to contractual claims (“ex contractu”). Furthermore, included within the
statute’s ambit are claims “including but not limited to any action . . . to
recover on a contract.” Thus, not only does it specifically include
contractual claims, but its applicability further reaches to any claims
“otherwise arising out of” a construction project of an immovable.
Moreover, section (B)(3) of the statute provides that the five-year
peremptive period extends to “every demand . . . whether brought by the
owner or by any other person.”
6 Legislation is the solemn expression of legislative will. La. C.C. art.
2. When a law is clear and unambiguous and its application does not lead to
absurd consequences, the law shall be applied as written and no further
interpretation may be made in search of the intent of the legislature. La.
C.C. art. 9.
Here, it is undisputed that Chemical filed its claim more than five
years from when the owner occupied the improvement. We must apply the
law as written. Thus, according to the clear and unambiguous language of
La. R.S. 9:2772, Chemical’s claim is perempted.
We are unpersuaded by Chemical’s assertion that La. R.S. 9:2772
does not apply because there is no claim of any deficiency. Chemical invites
the court to seize upon the inclusion of the word “deficiencies” in the
heading of La. R.S. 9:2772, but the reality is that the word “deficiencies” is
not a limitation contained within the clear language of the statute.
Moreover, “headings to sections, source notes, and cross references are
given for purposes of convenient reference and do not constitute part of the
law.” La. R.S. 1:13. In other words, the inclusion of the word
“deficiencies” in the title of La. R.S. 9:2772 is not a source of law.
We are similarly unpersuaded by the cases relied upon by Chemical in
support of its argument. Chemical cited Bungee Corp. v. GATX Corp., 557
So. 2d 1376 (La. 1990), for the proposition that La. R.S. 9:2772 only applies
to cases of deficiencies in construction projects. However, Bungee, supra,
actually stands for the proposition that “failure to warn” claims were not
included within the ambit of the statute as it read at that time. The
legislature responded by amending the statute to specifically include an
7 “action for failure to warn.” La. R.S. 9:2772(A). See also La. R.S.
9:2772(B)(2).
Chemical also cited Academy Park Improvement Ass’n v. City of New
Orleans, 469 So. 2d 2 (La. App. 4 Cir. 1985), writ denied sub nom. Academy
Park Improvement Ass’n v. City of New Orleans, 475 So. 2d 361 (La. 1985),
and State v. Henderson, 22-0405, (La. App. 1 Cir. 12/15/22), __ So. 3d __,
2022 WL 17688337, both of which are inapposite. Academy Park
Improvement Ass’n v. City of New Orleans involved a claim which alleged
fraud against an improvement association, and La. R.S. 9:2772 expressly
excepts allegations of fraud from its application. State v. Henderson, supra,
involved a claim against a homeowner to recover funds which had been paid
to her via a grant to rebuild her home, and the applicability of La. R.S.
9:2772 was not at issue.
The gravamen of Chemical’s argument is that because the heading of
La. R.S. 9:2772 includes the word “deficiencies,” the otherwise clear
language of the statute itself should be ignored and its application be limited
to construction deficiencies. The heading, however, does not constitute part
of the statute.
The language of the statute is clear: actions arising from the
construction of immovables are perempted upon the passage of five years
after occupation of the improvement by the owner. The facts of this case are
likewise clear: Chemical filed its claim more than five years after the owner
occupied the West Carroll Memorial Hospital project. Therefore, the trial
court did not err in sustaining Arco’s peremptory exception of peremption
and Chemical’s sole assignment of error is without merit.
8 CONCLUSION
For the foregoing reasons, we affirm the judgment of the trial court in
favor of Arco Builders, Inc., and against Chemical Insulation, Inc., granting
Arco’s peremptory exception of peremption. All costs of this appeal are
assessed to appellant.
AFFIRMED.