Chem Construction Corp. v. Board of Education

105 Misc. 2d 980, 430 N.Y.S.2d 771, 1980 N.Y. Misc. LEXIS 2606
CourtNew York Supreme Court
DecidedMarch 27, 1980
StatusPublished
Cited by1 cases

This text of 105 Misc. 2d 980 (Chem Construction Corp. v. Board of Education) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chem Construction Corp. v. Board of Education, 105 Misc. 2d 980, 430 N.Y.S.2d 771, 1980 N.Y. Misc. LEXIS 2606 (N.Y. Super. Ct. 1980).

Opinion

[983]*983OPINION OF THE COURT

Aaron D. Bernstein, J.

This is an action for damages arising out of a construction contract entered into by the parties in March, 1973. Plaintiff, alleging three causes of action, seeks recovery for (1) the contract balance due; (2) additional work done under change Orders Nos. G13 and G14; and (3) extra work done under protest. The defendant, board of education, now moves to amend its answer to assert a defense based upon plaintiff’s failure to comply with the notice of claim requirements of section 3813 of the Education Law, and for summary judgment dismissing plaintiff’s second and third causes of action on the ground that said notice of claim was not timely served pursuant to section 3813.

Leave to amend the pleadings “shall be freely given” absent prejudice or surprise (CPLR 3025, subd [b] ; Fahey v County of Ontario, 44 NY2d 934, 935), neither of which has been demonstrated here. Accordingly, defendant’s motion to amend its answer to include a defense pursuant to the notice of claim requirements of section 3813 is granted. Said amended answer shall be served within 15 days following the date of this decision.

The merits of this new defense shall hereafter be considered in conjunction with the second branch of defendant’s motion for summary judgment which is based on said defense.

A condition precedent to the commencement of an action against the board of education is compliance with subdivision 1 of section 3813 of the Education Law which requires the presentment to it of a “written verified claim * * * within three months after the accrual of such claim” (Matter of Board of Educ. [Heckler Elec. Co.], 7 NY2d 476, 482; Anderson Constr. Co. v Board of Educ., 229 NYS2d 337, 339). It being undisputed that plaintiff served an otherwise proper notice of claim upon the board of education on December 22, 1976, the only issue facing this court is whether the notice was timely served within the requisite three-month period after the claim had accrued.

Our appellate courts unanimously agree that a claim accrues under section 3813 when the damages are ascer[984]*984tamable (see, e.g., Board of Educ. [Wager Constr. Corp.], 37 NY2d 283, 290; Shalman v Board of Educ., 31 AD2d 338, 341; McKay Constr. Corp. v Board of Educ., 33 AD2d 862, 864; Wm. J. Schmitt, Inc. v Penfield Cent. School Dist., 54 AD2d 1100, 1101). Unfortunately, however, none of these decisions offer any helpful or meaningful guidelines as to when damages become ascertainable. Instead, they simply leapfrog from a statement of the principle to a conclusion as to when this occurred within the facts of the particular case (see, e.g., Board of Educ. [Wager Constr. Corp.], supra, pp 290-291; Central School Dist. No. 3, Towns of Romulus, Varick & Fayette v Kosoff & Sons, 53 AD2d 1058, 1059). The concept is further muddled by the additional proposition set forth in some of these opinions that the time when damages are ascertainable is not to be confused with the time when a cause of action accrues (Board of Educ. [Wager Constr. Corp.], supra, p 291; Central School Dist. No. 3, Towns of Romulus, Varick & Fayette v Kosoff & Sons, supra, p 1059). Again, however, the courts fail to tell us how and why these time frames are to be distinguished, particularly in light of the wording of section 3813 (see infra). This lack of any clear analysis has, in this court’s opinion, placed a great burden on the litigants in deciding when they must serve their notices of claim (as the instant case graphically illustrates) and upon the courts in making the same determination vis-a-vis motions such as this.

Within the factual context of this case, this court will therefore attempt to formulate some guiding principles applicable to the accrual of construction contract claims under section 3813 in accordance with the purposes of this notice of claim statute. Section 3813 itself begins by stating that “No action or special proceeding * * * shall be prosecuted or maintained”, thus indicating that a notice of claim is to be principally used in connection with a potential lawsuit. Consistent therewith, it has been stated that “Section 3813 is clearly intended to afford a school district the opportunity to investigate the claims of all kinds to obtain evidence promptly while it is still readily available, and to adjust or make payment before litigation is commenced” (Matter of Board of Educ. [Great Neck Teachers Assn.], 69 Misc 2d 1061, 1067, affd 40 AD2d 950; Board of Educ. [985]*985[Wager Constr. Corp.], 37 NY2d 283, 289, supra; Board of Educ. v Southern, 97 Misc 2d 631, 633).

Considered in light of these purposes, a notice of claim should not be required unless and until there is some basis or reason for the claimant to believe that there is a dispute with his claim and that an action may be necessary to recover thereon (cf. Mars Assoc. v Board of Educ., 96 Misc 2d 393, 395). “Prior to that time it could not be known whether he would in fact sustain any substantial damages” (Scherman v Board of Educ., 44 AD2d 831, 832, affd 37 NY2d 839, 840-841). This necessarily leads to the conclusion that it is only at such time as the claimant is advised by the board of education, either in writing or by the board’s actions, that his claim or request for payment thereof may not be honored or, in fact, will be rejected, that the three-month period within which he must serve a notice of claim should accrue (cf. Anderson Constr. Co. v Board of Educ., 229 NYS2d 337, 339, supra). It is at that critical time that the claim should be regarded as having ripened into one for ascertainable damages, provided, of course, that the amount of damages are then known. If, at that time the extent of damages has not yet been determined, then we must await the completion of the work in question to determine when the damages become ascertainable and so fix the date for the accrual of the claim. (McKay Constr. Co. v Board of Educ., 33 AD2d 862, 864, supra; Wm. J. Schmitt, Inc. v Penfield Cent. School Dist., 54 AD2d 1100, 1101, supra; see, also, Carthage Cent. School Dist. No. 1 v Reddick & Sons of Gouverneur, 67 AD2d 808.) On the other hand, the completion of work which is not yet in dispute should not alone be decisive, but must await a subsequent rejection or disavowal before the accrual period begins. Otherwise, every request for payment or change order, or extra work performed by a contractor would require the claimant or contractor to serve a separate notice of claim simultaneously therewith or upon the completion of the specific work in question without regard to whether the item is in dispute or not, a result which would seemingly not be intended by section 3813 (see Carthage Cent. School Dist. No. 1 v Reddick & Sons of Gouverneur, supra, p 808). Finally, the principles enunciated herein may be varied by [986]*986the parties by express provision in their underlying agreement.

In applying the foregoing analysis to the instant matter, the court notes at the outset that while the board has raised in their answer a provision in their contract with plaintiff which provides for a statement of claim, its applicability herein has not been demonstrated on this motion. A recitation of the pertinent uncontroverted facts and the respective positions of the parties is therefore in order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pope v. Hempstead Union Free School District Board of Education
194 A.D.2d 654 (Appellate Division of the Supreme Court of New York, 1993)