Evans, J.

This was an action against a carrier to recover damages for the breach of an oral agreement to furnish cars. In his petition the plaintiff alleged that he was a grower of peaches, and on July 1, 1901, before the peach season opened, he saw the general manager of the defendant, who told him that the defendant could handle his fruit, and that cars would be placed for him at [128]*128a designated station in twenty-four hours after they were ordered through the defendant’s local agent. At various times between July 15 and August 15, 1904, the plaintiff, after ordering cars, carried to the shipping point 7,802 crates of peaches to be loaded twenty-four hours after the cars were ordered. The cars were not placed within twentj'-four hours after they were ordered, but were placed from twelve to twenty-four hours after they were due. The peaches thus brought to the point of loading remained without refrigeration until the cars were delivered, and deteriorated in value between the time the cars were due and the time they arrived $5,019.67. The jury returned a verdict for the plaintiff for $1,-989.54, which the court refused to set aside on motion for a new trial. Exception is taken to the overruling of the defendant’s demurrer, and to the refusal of the court to grant a new trial.

1. It is urged by the demurrer that the contract as alleged is too vague and uncertain to be the basis of a cause of action. The proposition seems to be thoroughly established that an oral agreement by a duly authorized agent of a carrier to furnish ears to a shipper constitutes a contract which is valid and binding on both parties. San Antonio etc. R. Co. v. Timon, 45 Tex. Civ. App. 47 (99 S. W. 418). The allegation of the petition is that the general manager of the defendant made a certain agreement. The contract of a corporation made by its general manager is binding on the corporation. Raleigh &c. R. Co. v. Pullman Co., 122 Ga. 700 (50 S. E. 1008). So the person alleged to have made the contract was clothed with ample authority to bind the defendant. His proposal to the plaintiff was that the railroad company would ship his fruit in cars which would be placed at a certain station in twenty-four hours after they were ordered through the defendant’s local agent. The petition sets forth in detail the various dates, and the number of cars on such dates, the plaintiff ordered through the local agent to be placed at this station, and that the railroad company furnished the cars in response to such orders, but twelve to twenty-four hours late in each instance, and actually transported the plaintiff’s peaches. The proposal was to furnish cars after specified notice; the plaintiff gave the notice, and the cars were furnished, but not within the specified time. The contract was definite, certain, and binding as to the cars actually ordered. McCaw Mfg. Co. v. Felder, 115 Ga. 408 (41 S. [129]*129E. 664); Toledo &c. R. Co. v. Roberts, 71 Ill. 640; A. & W. P. R. Co. v. Camp, 130 Ga. 1 (60 S. E. 177, 15 L. R. A. (N. S.) 594).

2. Another ground of demurrer complains that the petition improperly joined causes of action ex contractu and ex delicto. The action is based upon defendant’s alleged breach of a contract to furnish ears. After setting out the contract before alluded to, the petition contains these words: “Belying upon this contract and assurance, petitioner made no other arrangement for the transportation of his fruit.” Later on in the petition allusion was again made to the contract alleged to have been entered into with the general manager of defendant company, and it was alleged that the terms of this contract “was a reasonable regulation both towards petitioner and defendant, and was the one theretofore commonly of force at said station.” The 7th and 8th paragraphs of the petition were as follows: “Petitioner alleges that it was wrongful in defendant not to supply cars as it had agreed to do, in not having and furnishing sufficient cars to handle petitioner’s crop, in not providing storage facilities to protect petitioner from loss by reason of defendant’s failure to furnish cars. By reason of the foregoing facts, petitioner has been injured and damaged by defendant in the sum of $8,500.” We have reproduced such of the allegations of the petition as the demurrant relies upon as confounding actions of tort and contract. Beference to the contract as being a reasonable regulation is not inconsistent with the contention that the plaintiff’s injury was consequent upon a breach of the contract. So much of paragraph seven as refers to the failure to have and furnish cars, when construed with the other allegations of the petition, indicates that the defendant’s liability from this cause arose from its failure to furnish cars according to contract.

Another element of damages claimed in the petition was $91 extra expense which the plaintiff incurred in transferring and loading the peaches by reason of the defendant’s failure to furnish cars as agreed; and so much of paragraph seven .as refers to the failure of defendant to provide storage facilities to protect the shipments from loss evidently had reference to this item of damages claimed to have resulted from a breach of the contract. Besides, even if these allusions were inappropriate or irrelevant, they should have been pointed out by special demurrer. So many of the spe[130]*130eial demurrers as were meritorious were met by appropriate amendments.

3. The obligation of a carrier to furnish cars to a patron may arise either from the duty imposed by the law, or from a special contract between the carrier and the patron. When the obligation is imposed by the law, a reasonable excuse for failure to perform it is allowable; but where the obligation springs from the contract, the carrier will be held liable in all cases where the circumstances are not such as to relieve from the performance of contracts generally. Mauldin v. Seaboard &c. R. Co., 73 S. C. 9 (52 S. E. 677); Toledo &c. R. Co. v. Roberts, 71 Ill. 540. The plaintiff’s cause of action was not for a breach of duty imposed by law; and therefore the various assignments of error on the admission and rejection of evidence, and on the charge of the court, wherein it is contended that the ruling complained of eliminated a defense solely applicable to the duty imposed by law, are not meritorious.

4. The plaintiff contends that if the cars had been placed according to the contract, his peaches, which were of a fancy grade and in good condition, and which had been placed at the station of the carrier’s line of road appointed to receive them, could and would have been immediately loaded by him in refrigerator-cars, and would not have been exposed to the more rapid process of decay resulting from the delay in tendering the car, if the defendant had complied with its contractual obligation. If damages are to be awarded to the plaintiff, they are ,to compensate him for the deterioration in the condition of the peaches, caused by the defendant’s delay in furnishing cars according to contract. If his peaches deteriorated in value because of the delay in furnishing cars, then the carrier is responsible for the damages proximately resulting from such delay. The point is raised that the court adopted an erroneous standard of estimating the damages by allowing proof of the market value of the peaches at Menlo, the station appointed by the carrier to receive them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Powell v. Jerome
36 S.E.2d 371 (Court of Appeals of Georgia, 1945)
Central of Georgia Railway Co. v. Greene & Co.
154 S.E. 809 (Court of Appeals of Georgia, 1930)
Strock v. So. Ry. &8212 Carolina Division
140 S.E. 470 (Supreme Court of South Carolina, 1927)
Davis v. Cornwell
264 U.S. 560 (Supreme Court, 1924)
Hancock v. Miller
111 S.E. 80 (Court of Appeals of Georgia, 1922)
Thompson v. Atlantic Coast Line Railroad
106 S.E. 322 (Court of Appeals of Georgia, 1921)
Levy v. Nevada-California-Oregon Ry.
169 P. 898 (Oregon Supreme Court, 1916)
Georgia Northern Railway Co. v. Snellgrove
85 S.E. 790 (Court of Appeals of Georgia, 1915)
Oregon R. & Navigation Co. v. Dumas
181 F. 781 (Ninth Circuit, 1910)
Southern Railway Co. v. Moore
67 S.E. 85 (Supreme Court of Georgia, 1910)
Georgia Coast & Piedmont Railroad v. Durrence & Sands
65 S.E. 583 (Court of Appeals of Georgia, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
65 S.E. 285, 133 Ga. 127, 1909 Ga. LEXIS 166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chattanooga-southern-railroad-v-thompson-ga-1909.