Chattanooga Car & Foundry Co. v. Lefebvre

37 So. 38, 113 La. 487, 1904 La. LEXIS 666
CourtSupreme Court of Louisiana
DecidedFebruary 29, 1904
DocketNo. 14,677
StatusPublished
Cited by9 cases

This text of 37 So. 38 (Chattanooga Car & Foundry Co. v. Lefebvre) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chattanooga Car & Foundry Co. v. Lefebvre, 37 So. 38, 113 La. 487, 1904 La. LEXIS 666 (La. 1904).

Opinions

Statement of the Case.

MONROE, J.

This is an action brought by-Henry Clay Evans, doing business under the name of the Chattanooga Car & Foundry Company, for a balance alleged to be due for certain cane cars furnished to Victor M. Lefebvre under the following contract, to wit:

“Chattanooga, Tenn., July 6th, 1901.
“Mr. V. M. Lefebvre, Plaquemine, La.
“Dear Sir. We hereby agree to furnish you-30, double track, skeleton, cane cars, as per the attached specifications, at $145, each, delivered at Australia Plantation. We agree to furnish a man to superintend the putting up of the cars after they are received at the plantation. Terms, $1000, cash, on the arrival of the cars; balance due, by note payable Dec. 15th,. [489]*489•with, interest at 6% from date of shipment. Cars to he shipped as early as possible in September. Very truly yours.
“[Signed] Chattanooga Car Co.
“Accepted. [Signed] V. M. Lefebvre.”

Plaintiff alleges that the cars were manufactured and delivered agreeably to this contract; that defendant has paid $613.63 on account of the price; and that there is due a balance of $3,736.37, for which he prays judgment, with recognition of the vendor’s lien on the cars.

Defendant denies the allegations of the petition, save as specially admitted. He admits the execution of the contract sued on, which, he alleges, was negotiated with Louis Kaufman, plaintiff’s agent in New Orleans. He further alleges that Kaufman was aware that the cars contracted .for were to be used in transporting from the fields to the factory the cane crop for the year 1901 on defendant’s plantation; that he was notified that defendant wished to begin grinding not later than October 10th, and that it was of the essence of the contract that the cars should be shipped as early as possible in September; that, relying on the discharge by plaintiff of his obligation in the premises, defendant constructed at his factory a railroad switch yard and carrier feeder, so as to provide for the delivery of cane in cars, instead of carts, as theretofore; that he made repeated demands upon plaintiff, through his said agent, during the month of September, 1901, to make delivery of said cars according to contract, but that said agent finally admitted that it would be impossible for him to do so, and that the cars were not shipped during the month of September, but at a later date; that, even after their shipment, by reason of the negligence of the plaintiff, they were not seasonably delivered, and, when delivered, were defective, and had to be made good at an expense of $100; and, that plaintiff failed seasonably to furnish a man to put them up. Defendant further alleges that by reason of the failure of the plaintiff to comply with his contract in the particulars mentioned he was unable to begin grinding until October 29th, and then only with an inadequate equipment; that he notified plaintiff, through his agent, that, although he would he compelled to use the cars as furnished, he would hold him responsible for the loss resulting from the delay in their delivery; that, despite his best efforts, 10,000 tons of cane remained unground on December 14, 1901, when a freeze occurred, which destroyed 5,000 tons, and reduced the yield of the balance by more than one-half; that said cane was worth $4 per ton; and that the loss amounts to $30,100, the whole of which is attributable to plaintiff’s breach of his contract; and he prays for judgment in reconvention for that amount.

There was a verdict and judgment for plaintiff on the main demand as prayed, and for defendant on the reconventional demand in the sum of $21,000, and plaintiff has appealed.

The evidence shows that 23 of the cars called for by the contract were shipped from Chattanooga October 11th; that they reached Australia plantation part of them on the 17th, and the rest on the 22d; that the plaintiff began grinding on the 29th of that month, and that he thereafter operated his mill to its full capacity, Sundays excepted, until December 13th, when he stopped on account of a hard freeze, and, resuming about the 21st, continued to grind, profitably, for three or four days, and thereafter, unprofitably, until January 4, 1902, when the mill was shut down. The seven remaining cars were shipped at a later date, and reached the plantation about November 10th, but it does not appear that the plaintiff would have ground any more cane if they had been included in the first shipment, nor does it appear that the delay which ensued between the first shipment, on October 11th and the starting of the mill on October 29th was attributable to the fault of the plaintiff, part [491]*491of that delay having been necessary for the transportation and putting together of the cars, and part of it having been unnecessarily occasioned by the failure of the steamboat St. John to take to the plantation, from New Orleans, at one time, the entire shipment received by it, at one time, from the railroad company by which it had been brought from Chattanooga. Assuming that the same delay would have occurred if the plaintiff had shipped the cars on the last day of September, the defendant would have begun grinding on October 19th, and accepting December 24th as the last day on which he was able to grind profitably, he would have had 67 days, less nine Sundays and less 7 days during which he was unable to grind on account of the frozen condition of the cane, or 51 working days, within which to take off his crop. Beginning, as he did, on October 29th, and ending on December 24th, he had 57 days, less 7 Sundays and 7 days of frozen cane, or 43 working days, within which to take off his crop.

The defendant asserts that he had 650 acres of cane for the mill, and, whilst the evidence upon the subject is rather estimative than positive, that number may be accepted as correct, after deducting 58% acres, the cane upon which belonged to his tenants.

The tonnage per acre is left somewhat more at large. At one time the defendant, referring to the entire 650 acres, says: “I suppose the average tonnage, from what I had weighed, was about 25 or 26 tons to the acre.” At another time he testifies that he had from 125 to 150 acres of “spring plant,” which was bad, and did not average more than 15 or 20 tons to the acre; from 215 to 225 acres of “fall plant,” which averaged from 25 to 30 tons to the acre; and about 300 acres of “stubble,” which averaged from 30 to 35 tons to the acre. And from this his counsel present the following figures as the basis of their argument, to wit;

125 acres, spring plant, averaging 17% tons 2,187 tons
225 “ fall " “ 27% “ 6,187 “
300 “ first years stubble averaging 32% tons .............................. 9,760 “
640 acres yielding total crop of............18,124 tons

According to these figures, the entire crop averaged something over 27% tons to the acre, whereas the plaintiff himself had “supposed, from what he had weighed,” that it averaged 25 or 26 tons to the acre; and, whilst the other witnesses sworn on his behalf were not, as a rule, interrogated about the “spring” and “fall” plant, they were interrogated concerning the stubble, and none of them testify to a higher estimative average than 30 tons per acre. Our conclusion, then, on this point, is that the figures should be stated as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Howard L. Makofsky, Jr. v. Raymond C. Cunningham, II
576 F.2d 1223 (Fifth Circuit, 1978)
Jones v. Whittington
171 So. 2d 764 (Louisiana Court of Appeal, 1965)
Bancroft v. Indemnity Insurance Co. of North America
203 F. Supp. 49 (W.D. Louisiana, 1962)
Williams Lumber Co. v. Stewart Gast Bro.
21 So. 2d 773 (Louisiana Court of Appeal, 1945)
Cerami v. Daigle
6 La. App. 556 (Louisiana Court of Appeal, 1927)
Riccobono v. Kearney
7 La. App. 738 (Louisiana Court of Appeal, 1927)
Alonzo v. Westfeldt Bros.
111 So. 675 (Supreme Court of Louisiana, 1927)
Stamm-Scheele Mfg. Co. v. Young
104 So. 377 (Supreme Court of Louisiana, 1925)
Fort Dearborn Coal Co. v. Newaygo Portland Cement Co.
202 N.W. 977 (Michigan Supreme Court, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
37 So. 38, 113 La. 487, 1904 La. LEXIS 666, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chattanooga-car-foundry-co-v-lefebvre-la-1904.