BRIGHTMIRE, Judge.
May an action founded on the breach of a rotary drilling contract be treated by the court instructionally as though it were a common law negligence action? While the parties do not precisely identify this issue as such, we think it is the decisive one, and we answer it in the negative.
Plaintiff, R. W. Chase, appeals from a judgment entered on a jury verdict denying him damages he claimed he sustained as a result of a “blowout” of a well being drilled by defendant, Paul Holt Drilling, Inc., in December 1971 pursuant to a written drilling contract executed November 25, 1971, and instead awarding the drilling company damages on its cross-petition. Appellant assails the judgment on two main grounds: (1) it is not supported by sufficient evidence; (2) it resulted from fundamentally incorrect instructions.
For their drilling agreement the parties used a standard form produced by the American Association of Oilwell Drilling Contractors (August 1964 revision).1 It [219]*219provided for drilling three wells in Noble County, Oklahoma, to a depth of 2,150 feet for $2.30 a foot. Among the equipment the drilling company agreed to furnish was a 10-inch Shaffer Blowout Preventer series 900 single-manual.
Holt Drilling Company commenced drilling the hole the first day of December 1971. By 2:30 in the afternoon of December 2 the hole had reached a depth of about 1,342 feet. Suddenly the derrick man came down the “dead man line” and everybody could be seen running from the rig floor yelling “blowout.”
Plaintiff’s petroleum engineer, who happened to be at the well site when the blowout occurred, said he ran toward the base of the rig, looked at the blowout preventer and as he was about to order it closed he noticed it had no closing mechanism. Some crew member spoke up and said the closing apparatus was at the “bottom of [the] fire crack” and it would take a gin truck to move it. So the engineer ordered all engines shut down and he went into town to get the head of Holt Drilling Company — -Paul Holt. Holt sent a pump truck out which pumped in 25 barrels of 13-pound mud “to no avail, it just blew it right back out.”
Then a Halliburton truck with ,a larger pumping capacity was ordered out. It [220]*220pumped in about 50 barrels of 13-pound mud before the same thing happened — it blew right back up between four drill collars still in the hole.
At this point, with darkness setting in and use of lights hazardous, the driller decided to wait until the following morning and attempt to put the closing mechanism on the blowout preventer.
Plaintiff’s petition was founded on a breach of duty arising from the contract. Specifically the pleading attached a copy of the drilling contract. Making especial reference to paragraphs 10.1 and 10.2 (see footnote 1) plaintiff charged defendant with a “violation of the terms of such agreement . . . [and] as a result of the violation by the Defendant of the terms of the agreement . . . the drilling hole has been lost . . .” at a re-drill cost to plaintiff in the sum of $3,087. Then in the last paragraph plaintiff adds that “as a result of the negligent failure of Defendant to comply with the terms and provisions of the drilling contract . Plaintiff was required to expend . . .” an additional $35,000 in killing the well.
In its answer the drilling company set out a general denial, an admission of making the drilling contract mentioned by plaintiff, but insisted that it performed all of its requirements to the letter. The blowout, defendant alleged, “was due to circumstances beyond his [sic] control” in that “abnormal . . . pressure for such area” was unexpectedly encountered —pressure of such magnitude that “the equipment called for by the drilling contract . . . was unable to stop the flow” of the blowout. And for a final defense defendant asserted the misfortune “was an unavoidable casualty as to him, not brought about by any act of negligence or omission on his part.”
Then defendant filed a “cross-petition” setting up a rather unusual allegational theory upon which to base a recovery against plaintiff for damages the drilling company says it suffered. First defendant acknowledged validity of the drilling contract and that the “blow-out preventer was entirely inoperative . . . [but] it should have been known to ... [plaintiff when he agreed to a 10-inch 900 single-manual] that if abnormal pressure was encountered . . . [such] blow-out preventer would be inoperative” under the circumstances. Moreover, defendant continued, plaintiff “should have known” about the existence of the abnormal subsurface pressure, and therefore if someone’s fault occasioned the blowout, it was plaintiff’s “lack of precautions . in the requirements of equipment as well as in the weight of mud” in predictable anticipation of the abnormal pressure condition. Further, alleged defendant, while it was faultless, plaintiff was not and “as a result of the neglect [unspecified] of [plaintiff] and the violation of the contract . . . this Cross-Petitioner has suffered damages in the amount of $12,802.50 . . . [for] labor and materials . . . . ”
A substantial amount of evidence was adduced in an effort by both parties to support only ex contractu theories following which the court gave a series of stock negligence instructions replete with such dandies as: “The mere proof of an accident or injury carries with it no presumption of negligence or contributory negligence, but the burden of proof rests upon the party alleging negligence . . .” etc., etc.
The instructions continued with a definition of “proximate cause” as used in connection with “any act of negligence.” And then came this one:
“You are instructed that an unavoidable accident is a casualty which occurs without negligence of either party, and when all means which common prudence suggests have been used to prevent it. Neither party to an unavoidable accident is liable to the other for damages sustained, and the mere proof of that injury resulting therefrom raises no presumption of negligence.
[221]*221“You are instructed that if you find by a preponderance of the evidence that the accident in this case was an unavoidable accident, then your verdict must be for the defendant.”
Following this came an instruction defining common law “ordinary care” and “negligence.”
Later on another instruction was given (No. 12) which told the jury it “should find for the plaintiff” if it found “defendant did not perform it’s [sic] part of the contract to drill said Well in a good and workmanlike manner with due diligence . and use the reasonable or ordinary care required to prevent damage or injury to the Well, and was negligent in performing said contract and through no fault of the plaintiff . . . damages [were] occasioned ... as submitted to you by the evidence of the plaintiff.
“On the other hand, if you do not so find and the damages sustained were caused by the plaintiff through his failure to perform his part of the contract and use the care required, you should find for the defendant.
“You are further instructed that if you find neither party failed to perform his part of the contract to drill the Well . and is not guilty of negligence in causing the damages . . . and [the] same was the result of an unavoidable casualty, you should . . . allow neither party to recover against the other.
Free access — add to your briefcase to read the full text and ask questions with AI
BRIGHTMIRE, Judge.
May an action founded on the breach of a rotary drilling contract be treated by the court instructionally as though it were a common law negligence action? While the parties do not precisely identify this issue as such, we think it is the decisive one, and we answer it in the negative.
Plaintiff, R. W. Chase, appeals from a judgment entered on a jury verdict denying him damages he claimed he sustained as a result of a “blowout” of a well being drilled by defendant, Paul Holt Drilling, Inc., in December 1971 pursuant to a written drilling contract executed November 25, 1971, and instead awarding the drilling company damages on its cross-petition. Appellant assails the judgment on two main grounds: (1) it is not supported by sufficient evidence; (2) it resulted from fundamentally incorrect instructions.
For their drilling agreement the parties used a standard form produced by the American Association of Oilwell Drilling Contractors (August 1964 revision).1 It [219]*219provided for drilling three wells in Noble County, Oklahoma, to a depth of 2,150 feet for $2.30 a foot. Among the equipment the drilling company agreed to furnish was a 10-inch Shaffer Blowout Preventer series 900 single-manual.
Holt Drilling Company commenced drilling the hole the first day of December 1971. By 2:30 in the afternoon of December 2 the hole had reached a depth of about 1,342 feet. Suddenly the derrick man came down the “dead man line” and everybody could be seen running from the rig floor yelling “blowout.”
Plaintiff’s petroleum engineer, who happened to be at the well site when the blowout occurred, said he ran toward the base of the rig, looked at the blowout preventer and as he was about to order it closed he noticed it had no closing mechanism. Some crew member spoke up and said the closing apparatus was at the “bottom of [the] fire crack” and it would take a gin truck to move it. So the engineer ordered all engines shut down and he went into town to get the head of Holt Drilling Company — -Paul Holt. Holt sent a pump truck out which pumped in 25 barrels of 13-pound mud “to no avail, it just blew it right back out.”
Then a Halliburton truck with ,a larger pumping capacity was ordered out. It [220]*220pumped in about 50 barrels of 13-pound mud before the same thing happened — it blew right back up between four drill collars still in the hole.
At this point, with darkness setting in and use of lights hazardous, the driller decided to wait until the following morning and attempt to put the closing mechanism on the blowout preventer.
Plaintiff’s petition was founded on a breach of duty arising from the contract. Specifically the pleading attached a copy of the drilling contract. Making especial reference to paragraphs 10.1 and 10.2 (see footnote 1) plaintiff charged defendant with a “violation of the terms of such agreement . . . [and] as a result of the violation by the Defendant of the terms of the agreement . . . the drilling hole has been lost . . .” at a re-drill cost to plaintiff in the sum of $3,087. Then in the last paragraph plaintiff adds that “as a result of the negligent failure of Defendant to comply with the terms and provisions of the drilling contract . Plaintiff was required to expend . . .” an additional $35,000 in killing the well.
In its answer the drilling company set out a general denial, an admission of making the drilling contract mentioned by plaintiff, but insisted that it performed all of its requirements to the letter. The blowout, defendant alleged, “was due to circumstances beyond his [sic] control” in that “abnormal . . . pressure for such area” was unexpectedly encountered —pressure of such magnitude that “the equipment called for by the drilling contract . . . was unable to stop the flow” of the blowout. And for a final defense defendant asserted the misfortune “was an unavoidable casualty as to him, not brought about by any act of negligence or omission on his part.”
Then defendant filed a “cross-petition” setting up a rather unusual allegational theory upon which to base a recovery against plaintiff for damages the drilling company says it suffered. First defendant acknowledged validity of the drilling contract and that the “blow-out preventer was entirely inoperative . . . [but] it should have been known to ... [plaintiff when he agreed to a 10-inch 900 single-manual] that if abnormal pressure was encountered . . . [such] blow-out preventer would be inoperative” under the circumstances. Moreover, defendant continued, plaintiff “should have known” about the existence of the abnormal subsurface pressure, and therefore if someone’s fault occasioned the blowout, it was plaintiff’s “lack of precautions . in the requirements of equipment as well as in the weight of mud” in predictable anticipation of the abnormal pressure condition. Further, alleged defendant, while it was faultless, plaintiff was not and “as a result of the neglect [unspecified] of [plaintiff] and the violation of the contract . . . this Cross-Petitioner has suffered damages in the amount of $12,802.50 . . . [for] labor and materials . . . . ”
A substantial amount of evidence was adduced in an effort by both parties to support only ex contractu theories following which the court gave a series of stock negligence instructions replete with such dandies as: “The mere proof of an accident or injury carries with it no presumption of negligence or contributory negligence, but the burden of proof rests upon the party alleging negligence . . .” etc., etc.
The instructions continued with a definition of “proximate cause” as used in connection with “any act of negligence.” And then came this one:
“You are instructed that an unavoidable accident is a casualty which occurs without negligence of either party, and when all means which common prudence suggests have been used to prevent it. Neither party to an unavoidable accident is liable to the other for damages sustained, and the mere proof of that injury resulting therefrom raises no presumption of negligence.
[221]*221“You are instructed that if you find by a preponderance of the evidence that the accident in this case was an unavoidable accident, then your verdict must be for the defendant.”
Following this came an instruction defining common law “ordinary care” and “negligence.”
Later on another instruction was given (No. 12) which told the jury it “should find for the plaintiff” if it found “defendant did not perform it’s [sic] part of the contract to drill said Well in a good and workmanlike manner with due diligence . and use the reasonable or ordinary care required to prevent damage or injury to the Well, and was negligent in performing said contract and through no fault of the plaintiff . . . damages [were] occasioned ... as submitted to you by the evidence of the plaintiff.
“On the other hand, if you do not so find and the damages sustained were caused by the plaintiff through his failure to perform his part of the contract and use the care required, you should find for the defendant.
“You are further instructed that if you find neither party failed to perform his part of the contract to drill the Well . and is not guilty of negligence in causing the damages . . . and [the] same was the result of an unavoidable casualty, you should . . . allow neither party to recover against the other.
“If, however, you find the Well blew out from an abnormal pressure, as defined in these instructions,2 which made the drilling abnormally difficult or hazardous without the negligence of either party and said abnormal pressure was the proximate cause of the losses . . . then your verdict ihould be for the defendant on his cross-petition against the plaintiff.” (emphasis ¿urs)
i Finally came Instruction No. 14, advising the jury that if their verdict was for plaintiff on his petition “then it must necessarily be against the defendant upon the tross-Petition”; and by the same token if it found for defendant on its cross-petition it had to find for defendant on plaintiff’s petition. „
From the foregoing it becomes obvious ihat confusion overtook the case when an ¿ttempt was made to amalgamate two dis-Iinct legal theories of recovery — contract nd tort — without discriminating regard for the pleadings or the evidence. This resulted in a hodgepodge of illegalities which imdoubtedly were as incomprehensible to the jury as they are to us.
In an effort to untangle the instructional lines it is first necessary to analyze the pleadings to see just exactly what issues they raise.
I [2] As we mentioned earlier plaintiff’s petition speaks only to a failure of defendant to perform its contractual obligations. Pt does not contain any allegation relating to the breach of a common law duty by defendant. Reference in the last paragraph to a “negligent failure of Defendant to tomply with the terms and provisions of the drilling contract” cannot be construed, fes defendant suggests, as an attempt to plead the tort of common law negligence. In the context used the word “negligent” is teally a superfluous adjective describing the reason for defendant’s alleged failure to fulfill its contractual obligations. We kay superfluous because if indeed defend-fent breached the contract, it is immaterial Whether it did so negligently or otherwise.3
[222]*222In joining issues defendant answered with a general denial; an affirmation that it “complied strictly with the contract”; a statement that the blowout was “due to circumstances beyond [its] control,” namely, an unforeseen subterranean pressure abnormal for the area requiring use of equipment not called for in the contract to control it; and that the blowout “was an unavoidable casualty . . . not brought about by any act of negligence” on its part.
At this point it can be seen the pleadings raise these contractual issues: Did loss of the well result from a breach of paragraphs 10.1 and 10.2 of the drilling contract? If so, was it excused by the “abnormal pressure” provisions of paragraph 13.2? Defendant’s denial of negligence and assertion of “unavoidable casualty” not being connected to the contract amounted to no more than inoperative surplusage.
We turn now to the cross-petition defendant filed. It begins by affirming the drilling contract and though not well worded we infer defendant tried to allege in substance that the well was lost because (1) the blowout preventer specified by the contract was inadequate to stop the blowout, (2) the specification deficiency “should have been known to” plaintiff because he “should have made inquiries” about whether “any abnormal pressure might be encountered,” and (3) such “lack of precautions” by plaintiff resulted in the inadequate contractual equipment specification “as well as in the weight of mud” and a consequent failure to save the well. Because of this “neglect of [plaintiff] and the violation of the contract,” defendant has sustained $12,802.50 damage “as additional costs, labor and material expended” (additional to what or for what is left to the reader’s imagination).
To this cross-petition plaintiff filed a general denial and a demurrer.
Now what issues did these pleadings raise? Being as generous as we can with the import of defendant’s cross-petition we see but one possible theory for recovery pleaded in it, namely, that defendant executed an improvident contract because of the precontractual negligence of plaintiff in failing to procure and provide it with sufficient geological information about the area thereby causing it damage in the sum of $12,802.50 for labor and materials expended in its fruitless effort to conquer the blowout. This might be called “negligence in the inducement” of the contract. True defendant refers conclusionarily to plaintiff’s “neglect . . . and the violation of the contract” but if facts are pleaded describing a breach of the agreement on the part of plaintiff we simply cannot find them.
Having identified the issue raised in defendant’s cross-petition the next question is whether it is a justiciable one — that is does it involve the breach of a duty which the law recognizes as being owed by plaintiff to defendant?
We are not aware of any law that imposed upon plaintiff — under the circumstances of this case — a duty to obtain and provide information to defendant regarding the geology and subsurface pressure potentials of the well site in question. If no duty was owed then none there was to breach. And if no duty was breached then negligence there could not be as a matter of law.
But assuming such a duty did exist, the theory was given no attention whatsoever at trial and, as a matter of fact, the driller’s proof actually disproved it by establishing its defense that the blowout resulted from an abnormal pressure the existence of which there was no way the owner or anyone else could have foreseen.4
Further destruction of the cross-petition theory was wrought by an acknowledge[223]*223ment of the drilling company president that he furnished the contract form, filled it in, and that the specification of the single-manual blowout preventer was his idea. It was admitted that the owner did not sign or even see the completed contract until the afternoon of the blowout.
The conclusion is then that the drilling company did not plead nor prove a recoverable claim against plaintiff based on tort. If the countersuit stated a cause of action it had to rest on contract — specifically paragraph 13.2 as it relates to the subject of abnormal pressures.
Consequently, since neither the pleadings nor the evidence formed the basis for finding either party guilty of common law negligence, it follows that instructions on the subject should not have been given.
Furthermore since the common law defense of unavoidable accident was not a permissible defense to a breach of contract action no instruction at all on the subject should have been given — much less the one that was.
We think these many errors could have been avoided if the trial judge had followed the supreme court’s long-standing requirement5 of analyzing both the pleadings and the evidence with a view toward identifying the submissible issues involved instead of reading the pleadings and telling the jury that they bespoke “the issues thus joined.”
The trial judge did give one instruction (No. 12) relating to the contractual issues in the case,6 though, even in it he tosses in negligence and, in effect, contributory negligence by specifying that before plaintiff can recover he must be free from fault and “use the care required.” A further reference to the negligence of both parties follows along with another pronouncement regarding “unavoidable casualty” which not only contradicts an earlier one on the subject but, apparently oblivious to the contractual issues involved, incredibly tells the jury if they find the parties’ damages result from an unavoidable casualty, they “should . . . allow neither party to recover against the other.” This might conceivably cancel out everything else and be overlooked except that there follows one more paragraph directing the jury to find for defendant on its cross-claim if they find “abnormal pressure” was the cause of the loss — a phenomenon which ironically under the evidence was “unavoidable.”
We hold Instruction No. 12 was grossly in error in requiring plaintiff to prove both a breach of contract and common law negligence on the part of defendant, as well as freedom from contributory negligence before he could recover. We fur[224]*224ther hold the charge is ambiguous, misleading, unclear and slanted in favor of defendant. Even the last paragraph (together with the damage instruction) leaves the impression that finding an “abnormal pressure” entitles defendant to all “the losses complained of,” whereas paragraph 13.2 says, for instance, that “Owner shall assume risk of loss of or damage to the hole and to Contactor’s equipment in the hole .” and after 24 hours contractor shall operate on a “day work rate” basis.
Finally the record which is certified as complete contains neither a verdict, a judgment, nor any other thing indicating that plaintiff’s lawsuit has been adjudicated. The one verdict on file inferentially relates only to the cross-petition because it says simply: “We . . . find for the Defendant and against the Plaintiff and fix the amount of Defendant’s recovery at $13,152.99.”7 The Journal Entry of Judgment8 adjudicates the cross-action but not the primary one. The effect of this is that dismissing the jury without requiring a verdict deciding the issues raised by plaintiff resulted in a mistrial.
Since plaintiff’s action is still pending without any final determination and since the judgment entered below for defendant was based on a verdict resulting from fundamentally erroneous instructions, it is reversed and the cause remanded for a new trial.
NEPTUNE, P. J., and BACON, J., concur.