Chase v. Paul Holt Drilling, Inc.

1975 OK CIV APP 9, 538 P.2d 217
CourtCourt of Civil Appeals of Oklahoma
DecidedFebruary 19, 1975
DocketNo. 46698
StatusPublished
Cited by3 cases

This text of 1975 OK CIV APP 9 (Chase v. Paul Holt Drilling, Inc.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chase v. Paul Holt Drilling, Inc., 1975 OK CIV APP 9, 538 P.2d 217 (Okla. Ct. App. 1975).

Opinion

BRIGHTMIRE, Judge.

May an action founded on the breach of a rotary drilling contract be treated by the court instructionally as though it were a common law negligence action? While the parties do not precisely identify this issue as such, we think it is the decisive one, and we answer it in the negative.

Plaintiff, R. W. Chase, appeals from a judgment entered on a jury verdict denying him damages he claimed he sustained as a result of a “blowout” of a well being drilled by defendant, Paul Holt Drilling, Inc., in December 1971 pursuant to a written drilling contract executed November 25, 1971, and instead awarding the drilling company damages on its cross-petition. Appellant assails the judgment on two main grounds: (1) it is not supported by sufficient evidence; (2) it resulted from fundamentally incorrect instructions.

For their drilling agreement the parties used a standard form produced by the American Association of Oilwell Drilling Contractors (August 1964 revision).1 It [219]*219provided for drilling three wells in Noble County, Oklahoma, to a depth of 2,150 feet for $2.30 a foot. Among the equipment the drilling company agreed to furnish was a 10-inch Shaffer Blowout Preventer series 900 single-manual.

Holt Drilling Company commenced drilling the hole the first day of December 1971. By 2:30 in the afternoon of December 2 the hole had reached a depth of about 1,342 feet. Suddenly the derrick man came down the “dead man line” and everybody could be seen running from the rig floor yelling “blowout.”

Plaintiff’s petroleum engineer, who happened to be at the well site when the blowout occurred, said he ran toward the base of the rig, looked at the blowout preventer and as he was about to order it closed he noticed it had no closing mechanism. Some crew member spoke up and said the closing apparatus was at the “bottom of [the] fire crack” and it would take a gin truck to move it. So the engineer ordered all engines shut down and he went into town to get the head of Holt Drilling Company — -Paul Holt. Holt sent a pump truck out which pumped in 25 barrels of 13-pound mud “to no avail, it just blew it right back out.”

Then a Halliburton truck with ,a larger pumping capacity was ordered out. It [220]*220pumped in about 50 barrels of 13-pound mud before the same thing happened — it blew right back up between four drill collars still in the hole.

At this point, with darkness setting in and use of lights hazardous, the driller decided to wait until the following morning and attempt to put the closing mechanism on the blowout preventer.

Plaintiff’s petition was founded on a breach of duty arising from the contract. Specifically the pleading attached a copy of the drilling contract. Making especial reference to paragraphs 10.1 and 10.2 (see footnote 1) plaintiff charged defendant with a “violation of the terms of such agreement . . . [and] as a result of the violation by the Defendant of the terms of the agreement . . . the drilling hole has been lost . . .” at a re-drill cost to plaintiff in the sum of $3,087. Then in the last paragraph plaintiff adds that “as a result of the negligent failure of Defendant to comply with the terms and provisions of the drilling contract . Plaintiff was required to expend . . .” an additional $35,000 in killing the well.

In its answer the drilling company set out a general denial, an admission of making the drilling contract mentioned by plaintiff, but insisted that it performed all of its requirements to the letter. The blowout, defendant alleged, “was due to circumstances beyond his [sic] control” in that “abnormal . . . pressure for such area” was unexpectedly encountered —pressure of such magnitude that “the equipment called for by the drilling contract . . . was unable to stop the flow” of the blowout. And for a final defense defendant asserted the misfortune “was an unavoidable casualty as to him, not brought about by any act of negligence or omission on his part.”

Then defendant filed a “cross-petition” setting up a rather unusual allegational theory upon which to base a recovery against plaintiff for damages the drilling company says it suffered. First defendant acknowledged validity of the drilling contract and that the “blow-out preventer was entirely inoperative . . . [but] it should have been known to ... [plaintiff when he agreed to a 10-inch 900 single-manual] that if abnormal pressure was encountered . . . [such] blow-out preventer would be inoperative” under the circumstances. Moreover, defendant continued, plaintiff “should have known” about the existence of the abnormal subsurface pressure, and therefore if someone’s fault occasioned the blowout, it was plaintiff’s “lack of precautions . in the requirements of equipment as well as in the weight of mud” in predictable anticipation of the abnormal pressure condition. Further, alleged defendant, while it was faultless, plaintiff was not and “as a result of the neglect [unspecified] of [plaintiff] and the violation of the contract . . . this Cross-Petitioner has suffered damages in the amount of $12,802.50 . . . [for] labor and materials . . . . ”

A substantial amount of evidence was adduced in an effort by both parties to support only ex contractu theories following which the court gave a series of stock negligence instructions replete with such dandies as: “The mere proof of an accident or injury carries with it no presumption of negligence or contributory negligence, but the burden of proof rests upon the party alleging negligence . . .” etc., etc.

The instructions continued with a definition of “proximate cause” as used in connection with “any act of negligence.” And then came this one:

“You are instructed that an unavoidable accident is a casualty which occurs without negligence of either party, and when all means which common prudence suggests have been used to prevent it. Neither party to an unavoidable accident is liable to the other for damages sustained, and the mere proof of that injury resulting therefrom raises no presumption of negligence.
[221]*221“You are instructed that if you find by a preponderance of the evidence that the accident in this case was an unavoidable accident, then your verdict must be for the defendant.”

Following this came an instruction defining common law “ordinary care” and “negligence.”

Later on another instruction was given (No. 12) which told the jury it “should find for the plaintiff” if it found “defendant did not perform it’s [sic] part of the contract to drill said Well in a good and workmanlike manner with due diligence . and use the reasonable or ordinary care required to prevent damage or injury to the Well, and was negligent in performing said contract and through no fault of the plaintiff . . . damages [were] occasioned ... as submitted to you by the evidence of the plaintiff.

“On the other hand, if you do not so find and the damages sustained were caused by the plaintiff through his failure to perform his part of the contract and use the care required, you should find for the defendant.

“You are further instructed that if you find neither party failed to perform his part of the contract to drill the Well . and is not guilty of negligence in causing the damages . . . and [the] same was the result of an unavoidable casualty, you should . . . allow neither party to recover against the other.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ABERCROMBIE & FITCH STORES INC. v. PENN SQUARE MALL LIMITED PARTNERSHIP
2018 OK CIV APP 56 (Court of Civil Appeals of Oklahoma, 2018)
Nail Ex Rel. Nail v. Oklahoma Children's Memorial Hospital
1985 OK 101 (Supreme Court of Oklahoma, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
1975 OK CIV APP 9, 538 P.2d 217, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chase-v-paul-holt-drilling-inc-oklacivapp-1975.