Chase v. Hogan

3 Abb. Pr. 57
New York Supreme Court·Decided February 15, 1867·Published

Opinion

By the Court*—Jones, J.

It will be perceived that one of the findings by the court below is, “ That about 18th September, 1856, plaintiff entered upon the possession of the premises mentioned in the complaint and commenced the erection of a dwelling-house thereon in conformity with said agreement, and continued his work thereon until about the latter part of February, 1857, when he suspended such work and did not resume the sameand another finding is, that plaintiff violated his [65] contract with defendants’ testator by the total suspension of all work, and by the non-completion of said.house, on the first of May, 1857, the day limited by the contract for its completion.

The question then arises, What is the effect of this breach of contract by plaintiff?

At common law (under the cases of Champlin v. Rowley, 18 Wend., 193 ; Harmon v. Bingham, 12 N. Y., 99; Smith v. Brady, 17 N. Y., 173; Tompkins v. Dudley, 25 N. Y, 172; Culter v. Tobias, 26 N. Y, 217), the plaintiff was guilty of a breach of his contract, and having failed to fully perform the condition precedent to his right to receive the deed, by omitting, to erect the building by the day limited, he could neither bring an action for damages based on the defendant’s refusal to deliver the deed, nor an action on a quantum meruit for the wrork actually performed and the materials actually furnished; but on the contrary defendants (under the authority of Jackson v. Moncrief, 5 Wend., 26; Wright v. Moore, 21 Wend., 230), could at law bring an action of ejectment to recover possession of the property. Defendants having peaceably obtained possession, there is no necessity for them to bring the possessory action of ejectment. The remedy of the plaintiff, if he has any, is in equity. (Wright v. Moore, 21 Wend., 230).

The plaintiff has in fact .brought an action in equity to obtain, preserve and protect such rights and interests as he claims to have. .

He claims that in equity there is a principle to the effect that time is not an essential part of a contract; that in this case time would not in equity be regarded as of the essence of the contract, and consequently although he has not performed by the time limited, he is yet entitled to relief in equity.

It is true it is stated in many English and American cases that in a contract for the sale and purchase of land, the time limited for the completion of the sale and purchase is not in general regarded in equity as an essential part of the contract. I do not, however, understand this doctrine to extend so far as to enable a party to obtain relief against non-performance by the day in cases where he shows neither any good reason for such non-performance, nor any peculiar equity.

Chancellor Kent, in Benedict v. Lynch (1 Johns. Ch., 370) cited [66] from pages 375, 376, 379), observes: “It may then be laid down as an acknowledged rule in courts of equity, that where the party who applies for a specific performance, has omitted to execute his' part of the contract by the time appointed, without being able to assign any sufficient justification or excuse for his delay, and when there is nothing in the acts or conduct of the other party that amounts to an acquiescence in that delay, the court will not. compel a specific performance. The notion that a party may be utterly regardless of 'his stipulated payments, and that a court of chancery will almost at any time relieve him from the penalty of Ms gross negligence is very injurious to good morals, to a lively sense of obligation to the sanctity of contracts, and to the character of tMs court. It would be against all my impressions of equity to help those who show no equitable title to relief.”

He then, after remarking that it was formerly supposed that the time fixed on for the completion of the contract was quite immaterial, proceeds to review the cases, and after such review observes: “From-the review which I have taken of the eases, “ the general principle appears to be perfectly established that “ time is a circumstance of decisive importance in these con-- “ tracts, but it may be waived by the conduct of the parties; “ that it is incumbent on the plaintiff calling for a specific per- •“ form anee to shew that he has used due diligence, or if not, •“ that Ms negligence arose Mom some just cause,' qr has been 151 acquiesced in.”

There is no case, not even those where it is insisted that -time is not of the escence ‘of the contract wliich does not require the plaintiff to show at least this much,_ to entitle himself to relief. ' •

In the case at bar the plaintiff does not bring himself within these principles.

The court below has not found as a fact, nor does the testimony satisfactorily show, that there- was any excuse for the delay, nor does there appear to be any specific equity.

It is true the plaintiff swears he was sick from 5th or 6th April till after Hay 1st. This, however, could not excuse the suspension of the work Mom the latter part of February to the .5th of -ipril, a period of six or seven weeks. Non constat, but [67] that if he had prosecuted the work diligently during that period, he would have finished the work before he"'was taken sick. Nor does it appear how sick he was; he may not have been so sick as to'prevent him from finishing the house through the agency of others; he does not swear he was, and he does not testify that his sickness prevented Mm from completing. All tin's is left to be inferred horn the bare fact that he was sick. I think the fact does not justify the inference.

It is also true that the plaintiff testifies that he proceeded as fast as the weather would permit, “and with as many men as could work there to advantage, considering the weather, up to the time he was taken sick. At folio 111, he testifies that he was going on with the work all the time except when the weather prevented, from the 29th of March to April 6.

As I understand this testimony, he says that he went on with the work up to the 29th March, and that it was only from the 29th March to April 6th, that the weather prevented its prosecution.

The court below found that he absolutely ceased work in the latter part of February,- a month prior to March 29th. This finding is in direct conflict with the plaintiff’s testimony at folios 111 and 130.

With the discredit cast by this finding on plaintiff’s testimony on°tMs material point, the court on appeal should attach but slight importance to the evidence of sickness.

The testimony at folio 111, seems to me" to disprove the excuse arising from the weather. .

That testimony shews that the only delay caused by the weather was eight days from March 29 to April 6. Thus there is over a month of total suspension left unaccounted for. This unexcused delay of one month leads to the conclusion that the assigned causes, of weather and sickness, did not prevent the performance, but that some motive, which was not disclosed, led to the non-performance, and that the weather and sickness were first thought of Avhen this action was commenced.

Free access — add to your briefcase to read the full text and ask questions with AI

Chase v. Hogan, 3 Abb. Pr. 57 (N.Y. Super. Ct. 1867).

3 Abb. Pr. 57 (Chase v. Hogan) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Harmony v. . Bingham
12 N.Y. 99 (New York Court of Appeals, 1854)
Smith v. . Brady
17 N.Y. 173 (New York Court of Appeals, 1858)
Jackson ex dem. Shipley v. Moncrief
5 Wend. 26 (New York Supreme Court, 1830)
Waterbury v. Sturtevant
18 Wend. 188 (New York Supreme Court, 1837)
Wright v. Moore
21 Wend. 230 (New York Supreme Court, 1839)
Benedict v. Lynch
1 Johns. Ch. 370 (New York Court of Chancery, 1815)