Chase v. Hatch

4 Rob. 89
CourtThe Superior Court of New York City
DecidedMarch 15, 1866
StatusPublished
Cited by2 cases

This text of 4 Rob. 89 (Chase v. Hatch) is published on Counsel Stack Legal Research, covering The Superior Court of New York City primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chase v. Hatch, 4 Rob. 89 (N.Y. Super. Ct. 1866).

Opinion

By the Court,

Jones, J.

It will be perceived that one of the findings by the court below is, That about the 18th September, 1856, the plaintiff entered upon the possession of the premises mentioned in the complaint, and commenced the erection of a dwelling house thereon, in conformity with said agreement, and continued the work thereon, until about the latter part of February, 1857, when he suspended said work and did not resume the same.” And another finding is, that the plaintiff violated his contract with the defendant’s testator by the total suspension of all work, and by the non-completion of said house on the 1st of May, 1857, the'day limited by the contract for its completion.

The question then arises, what is the effect of this breach of contract by the plaintiff ?

At common law, under the cases of Champlin v. Rowley, (18 Wend. 193,) Harmony v. Bingham, (12 N. Y. Rep. 99,) Smith v. Brady, (17 id. 173,) Tompkins v. Dudley, (25 id. 272,) and Catlin v. Tobias, (26 id. 217,) the plaintiff was guilty of a breach of his contract, and having failed to fully perform the condition precedent to his right to receive the deed, by omitting to erect the building by the day limited, he could neither bring an action for damages based on the defendants’ refusal to deliver the deed, nor an action on the quantum meruit, for the work actually performed, and materials actually .furnished; but the defendant, under the authority of Jackson v. Moncrief, (5 Wend. 26;) Wright v. Moore, (21 [97]*97id. 230,) could at law bring an action of ejectment, to recover possession of the property.

The defendants having peaceably obtained possession, there is no necessity for them to bring the possessory action of ejectment.

The remedy of the plaintiff, if he has any, is in equity. (Wright v. Moore, 21 Wend. 230.) The plaintiff has in fact brought an action in equity, to obtain possession and protect such rights and interests as he claims to have. He claims that in equity there is a principle, to the effect that time is not an essential part of a contract; that in this case time would not in equity be regarded as of the essence.of the contract, and consequently, although he has not performed by the time limited, he is yet entitled to relief in equity.

It is true it is stated in many English and American cases that in a contract for the sale and purchase of land, the time limited for the completion of the sale and purchase is not in general regarded in equity as an essential part of the contract.

I do not, however, understand this doctrine to extend so far as to enable a party to obtain relief against non-performance by the day, in cases where he shows neither any good reason for such non-performance, nor any peculiar equity.

Chancellor Kent, in Benedict v. Lynch, (1 John. Ch. 370, cited from pages 375, 376, 379,) observes: “It may then be laid down as an acknowledged rule in courts of equity, that when the party who applies for a specific performance has omitted to execute his part of the contract, by the time appointed, without being able to assign any sufficient justification or excuse for his delay, and when there is nothing in the acts or conduct of the other party that amounts to an acquiesence in that delay, the court will not compel a specific performance. The notion that a party may be utterly regardless of his stipulated payments, and that a Court of Chancery will almost at any time relieve him from the penalty of his gross negligence, is very injurious to good morals, to a lively sense of obligation, to the sanctity of contracts, and to the character [98]*98of the court.. It would be against all my impressions of equity to help those who show no equitable title to relief.”

He 'then, after remarking that it was formerly supposed that the time fixed on for the completion of the contract was quite immaterial, proceeds to review the cases, and after such review observes: From the review which I have taken of the

cases, the general principle appears to be perfectly established, that time is a circumstance of decisive importance in these contracts, but it may be waived by the conduct of the party; that it is incumbent on the plaintiff calling for a specific performance, to show that he has used due diligence, or if not, that his negligence arose from some just cause, or has been acquiesced in.”

There is no case, (not even those where it is asserted that time is not of the essence of the contract,) which does not require the plaintiff to show at least thus much, to entitle himself to relief.

In the case at bar, the plaintiff does not bring himself within these principles.

The court below has not found as a fact, nor does the testimony satisfactorily show, that there was any excuse for the delay ; nor does there appear to be any special equity.

It is true, the defendant swears he was sick, from 5th or 6th April, till after May 1st. This, however, could not excuse the suspension of the work, .from the latter part of February to the 5th of April, a period of six or seven weeks. Non constat but that if he had prosecuted the work diligently during that period, he would have finished the work before he was taken sick. Nor does it appear how sick he was ; he may not have been so sick as to prevent him from finishing the house through the agency of others; He does not swear he was, and he does not testify that this sickness prevented him from completing. All this is to be inferred from the. bare fact that he was sick. I think the fact does not justify the inference,

It is also true, that the defendant testifies that he proceeded as fast as the weather would permit, and with as many men [99]*99as could work then to advantage, considering the weather up to the time he was taken sick. At fol. Ill he testifies that he was going on with the work all the time, except when the weather prevented, from the 29th of March to April 6. As I understand this testimony, he says, that he went on with the work up to the 29th of March, .and that it was only from the 29 th of March to April 6 th, that the weather prevented its prosecution.

The court below found that he absolutely ceased work in the latter part of February,- a month prior to March 29. This finding is in direct conflict with the plaintiff’s testimony at fol. Ill and 130. With the discredit cast by this finding on the plaintiff’s testimony on this material point, the court, on appeal, should attach but slight importance to the evidence of sickness.

The testimony at folio 111, seems to me, to dispose of the excuse arising from the weather. That testimony shows that the only delay caused by the weather was eight days, from March 29 to April 6. Thus there is over a month of total suspension left unaccounted for. This unexcused delay of one month; leads to the conclusion that the assigned cause, of weather and sickness, did not prevent the performance, but that some motive which was not disclosed led to the nonperformance, and that the weather and sickness were first thought of as excuses when this action was commenced.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tregre v. Carter Packet Co.
61 So. 379 (Supreme Court of Louisiana, 1913)
West v. His Creditors
8 Rob. 123 (Supreme Court of Louisiana, 1844)

Cite This Page — Counsel Stack

Bluebook (online)
4 Rob. 89, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chase-v-hatch-nysuperctnyc-1866.