Charlton v. Scoville

22 N.Y.S. 883, 75 N.Y. Sup. Ct. 348, 52 N.Y. St. Rep. 306, 68 Hun 348
CourtNew York Supreme Court
DecidedApril 13, 1893
StatusPublished
Cited by2 cases

This text of 22 N.Y.S. 883 (Charlton v. Scoville) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charlton v. Scoville, 22 N.Y.S. 883, 75 N.Y. Sup. Ct. 348, 52 N.Y. St. Rep. 306, 68 Hun 348 (N.Y. Super. Ct. 1893).

Opinion

HAIGHT, J.

This action was brought to foreclose a mechanic’s lien. On the 26th day of August, 1890, the plaintiffs entered into a contract in writing with the defendant Charles H. Scoville to furnish the material and construct a dwelling house upon the premises of the defendant Cora I. Scoville for the sum of $3,980. The work was to be done in a workmanlike manner, according to- the plans and specifications attached to the contract, and under the direction and to the satisfaction of F. William Fisher, an architect. Charles H. Scoville was the husband of Cora I. Scoville, and he entered into the contract with her knowledge and consent and for her benefit. The plaintiffs sublet the carpenter work to another person, who commenced work upon the construction of the building on the 22d day of September, and continued work thereon until the 3d day of October, at which time he ceased work upon the premises, leaving the building unfinished. Subsequently this action was brought. The trial court found as facts that the building, as far as it had progressed, had not been constructed in accordance with the provisions of the contract; that improper materials had been furnished, and that the work had not been performed in a workmanlike manner; that on the 30th day of September notice was given to the plaintiffs to remove all labor and materials condemned by the architect, and to provide materials called for in the specifications on or before the 4th day of October at 9 o’clock A. M.; that the plaintiffs' expressed a willingness to remedy the defects, and through their employes did remedy certain defects, but not'all; . that on the 3d day of October they abandoned the work; that thereupon the defendants took possession of the building, had the same torn down at- an expense of $40.50, and reconstructed the same to the point where the building was abandoned, at an expense of $123.50, using therefor the materials of the plaintiffs that were in the building and left upon the grounds, of the value of $318; and ordered judgment [885]*885for the sum of $194.50, being the value of the materials used in the construction, $318, less the cost of rebuilding the same, $123.50. This judgment was ordered upon the theory that the defendants had abandoned the contract on their part after the plaintiffs had committed a breach of the contract on their part; that the defendants, in using the plaintiffs’ material in the new structure, were obliged to pay therefor, less the sum of $123.50, which the defendants had suffered as damages in reconstructing the building to the point where it was abandoned by the plaintiffs. The complaint alleged that on the 2d day of October, 1890, the defendants, without any just cause for so doing, notified the plaintiffs’ workmen to cease work upon the house, and ordered them off the premises, forbidding them coming again upon the land, and that no work had been done or material furnished by the plaintiffs since. The answer admitted that on or about the 2d day of October, 1890, the defendant Charles H. Scoville notified the plaintiffs and their workmen to cease work upon the said house, and that the plaintiffs have done no work and furnished no material since that time; but they deny that he so notified the plaintiffs and their workmen without just cause. It therefore stood admitted upon the pleadings that the plaintiffs and their workmen were ordered to cease work upon the house by the defendants, and the issue left to be tried in reference thereto was whether such order was justified.

Upon the trial the defendants were permitted to give evidence that the plaintiffs and their workmen were not ordered to cease work upon the house, and were not ordered off the premises, but, on the contrary, that they voluntarily abandoned the work. This evidence was taken under the objection that it contradicts the admissions in the answer. The court, however, admitted the «amp, remarking, “If it turns out they are precluded by the pleadings that will end it.” No exception was taken to the ruling. After the evidence was closed an adjournment was taken for a number of days, at which time the case was summed up by the counsel for the respective parties. After the arguments had closed, the defendants’ counsel asked leave to amend his answer so as to deny the allegations in the complaint “that on the 2d day of October, 1890, the defendants notified the plaintiffs’ workmen to cease work upon the said house, and ordered them off the premises, and forbade their again coming upon the lands described in the complaint.” This was objected to by the plaintiffs’ counsel, upon the ground that the evidence had been closed for two weeks, and that the plaintiffs had relied upon the admissions in the answer of the defendants, and, if the answer was amended as requested, there was no opportunity to prove the facts as alleged in the complaint. The court reserved its decision, but in disposing of the case it allowed the amendment of the answer, and found as a fact that the building was abandoned by the plaintiffs, and refused to find the plaintiffs’ request that the defendants notified the plaintiffs’ workmen to cease work upon the house and ordered them off the premises. There would be just cause for complaint on account of these rulings were it not for the fact that the plaintiffs had first opened [886]*886the door and given evidence in support of their allegation. Evidence upon this subject was given as a part of the plaintiffs’ affirmative case, and also upon the rebuttal. The question having thus been tried out, it was within the discretion of the trial court to permit the answer to be amended so as to conform to the evidence given.

As we have seen, the trial court found that the plaintiffs ceased work upon the house and contract, and by this act they forfeited their right to recover any of the installments under the contract thereafter to become payable. The building, as far as it had progressed, became the defendants’. They had, however, paid nothing thereon, and had consequently suffered no damages, unless, as it is claimed, it was so defectively constructed as to make it necessary that it should be torn down. If so, it was but an obstruction upon their premises, which they had a right to tear down, move away, or dispose of as they saw fit. It was torn down at an expense of $40.50. The building was reconstructed according to the original plans and specifications. It cost $123.50 to reconstruct it to the point where it was abandoned by the plaintiffs. This the trial court found was a proper item of damages to be deducted from the plaintiffs’ claim. We are at a loss to understand upon what theory this item can be allowed, for, as we have seen, the defendants had paid nothing upon the building, and had suffered no damages further than the expense of tearing down the defective structure. We are aware of no rule that would require the plaintiffs to rebuild the building to that point. The value of the plaintiffs’ material upon the premises that was used by the defendants in the new structure was $318. From this sum there should be deducted the expense of tearing down the building, $40.50, and the plaintiffs should have recovered a judgment for the balance.

The plaintiffs were awarded judgment upon the theory that the defendants had abandoned the contract on their part. Their right to recover cannot be maintained unless this theory is supported by the evidence. And this brings us to a consideration of the defendants’ appeal. Section 4 of the contract provides that—

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Co. v. Cronan
161 P. 692 (Oregon Supreme Court, 1916)
Midtown Contracting Co. v. Goldsticker
165 A.D. 264 (Appellate Division of the Supreme Court of New York, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
22 N.Y.S. 883, 75 N.Y. Sup. Ct. 348, 52 N.Y. St. Rep. 306, 68 Hun 348, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charlton-v-scoville-nysupct-1893.