Charleston Shipyards, Inc. v. Motor Vessel Poling Bros. V

188 F. Supp. 71, 1960 U.S. Dist. LEXIS 3261
CourtDistrict Court, E.D. South Carolina
DecidedOctober 10, 1960
DocketNo. 1092
StatusPublished

This text of 188 F. Supp. 71 (Charleston Shipyards, Inc. v. Motor Vessel Poling Bros. V) is published on Counsel Stack Legal Research, covering District Court, E.D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charleston Shipyards, Inc. v. Motor Vessel Poling Bros. V, 188 F. Supp. 71, 1960 U.S. Dist. LEXIS 3261 (southcarolinaed 1960).

Opinion

Y/YCHE,. District Judge.

This action came on for trial before me, sitting by designation in admiralty, on July 19, 1960. It was brought to recover sums allegedly due for services rendered and materials furnished by Charleston Shipyards, Inc., to the Motor Vessel Poling Brothers V while in the Port of Charleston.

Early in May, 1958, the Motor Vessel Poling Brothers V came into the Port of Charleston in a leaking condition. A few days after arrival, while attempting to proceed from the Cooper River up the Wan do River, she began to take in a great deal of water and was beached by her master on the eastern shore of the [73]*73Cooper River. The vessel obtained the services of Salmons Dredging Company to pump it out and remove it from where it was beached. When the vessel was floated, she was brought to the dock of Charleston Shipyards, Inc., on the western shore of the Cooper River. At the request of the master of the vessel and the representatives of the owner, the shipyard furnished gasoline pumps for use in refloating the vessel, together with labor, tugs and other services relating to the refloating and to the mooring of the vessel at its dock. Thereafter, again at the request of the master, the vessel was placed on the drydock of the shipyard where a survey was conducted by a surveyor employed by the owner and by others representing the owner. As a result of this survey it was determined that certain work would have to be performed on the ship’s bottom and on the engines, motors, electrical equipment and other parts of the vessel. The shipyard was requested to do this work and the items of work to be performed were specifically designated by the master and representatives of the owner of the vessel.

While the ship was on its drydock, the shipyard performed such repair services on the bottom as it was requested to do and then placed the vessel alongside its dock to proceed with other designated repairs. After some of these repairs had been completed, the shipyard informed the owner that it would not continue with the repair work unless some assurance was given in respect to the payment for the services that had been and were to be performed. The owner gave no satisfactory assurance in this respect, but stated that it would send a representative to Charleston to discuss the situation. The shipyard then informed the owner that until further arrangements were made it would do no more work on the vessel and would furnish no services therefor. After this notification by the shipyard and before the representative of the owner came to Charleston, the vessel remained at the shipyard’s dock, with its master and crew aboard in full charge and control of the vessel. During the existence of this situation, the vessel filled with water and sank to the bottom alongside the dock.

Upon arriving in Charleston, the representative of the owner discussed the situation with officers of the shipyard but would give no assurance that payment would be made for the work performed or for any additional work on the vessel, including the raising and refloating of the same. The vessel in its sunken condition was blocking the dock and preventing the use thereof by other prospective customers of the shipyard. The master and crew abandoned the vessel and the owner did nothing whatsoever to remedy the situation.

It was testified by James J. Sheeran that before the sinking, the gasoline pumps were removed by the shipyard from the vessel, although prior thereto, during a long distance telephone conversation he had had with L. Louis Green, III, an understanding was reached that the situation in relation to the vessel would not be changed until Sheeran’s arrival in Charleston. Green agreed that he had had a long distance telephone conversation with Sheeran at the time referred to, during which he had told Sheeran that the shipyard would do no work on the vessel and furnish no services to it until Sheeran arrived in Charleston, but that the vessel would be allowed to remain temporarily at the dock where it then lay. After this conversation, the shipyard removed the gasoline pumps, which required constant attention of one or more men, and substituted automatic pumps which required only an occasional cheek by the crew of the vessel. Green said that this change was consistent with his advice to Sheeran that the shipyard would furnish no labor or services to the vessel until satisfactory arrangements were made by the-owner to assure payment for the services.

In my opinion, the shipyard was-, under no obligation to perform any service for the vessel after it notified the-owner that it would not do so until payment was assured. Certainly, the ship,[74]*74yard was entitled to be assured of payment for any services that it undertook to perform and there was no reason for the owner to expect it to continue its efforts to repair the vessel or furnish other service to it without any assurance of payment. If the shipyard allowed the vessel to use any of the shipyard’s pumps after this notification, it did so gratuitously and without obligation. There was no obligation on the shipyard to continue to supply and man gasoline pumps and the responsibility to protect the vessel from sinking rested upon the master and crew in the use of whatever facilities were available. Furthermore, there has been no showing that the automatic pumps which were upon the vessel when it sunk were not functioning properly or were inadequate for their intended use, or that the gasoline pumps would have prevented the sinking.

The libel sets forth four separate bases for recovering the total sum of $22,150, and Bosul Shipping Corporation, as owner of the vessel, has interposed a cross-libel asking for damages in the sum of $50,000. I will separately discuss the libellant’s bases for recovery and the cross-libel of Bosul Shipping Corporation.

The first item of claim of the shipyard is that, at the instance and request of the master of the vessel and of the agent and representative of the owners, certain .'repairs to the hull, machinery and superstructure of the vessel and certain. services, material, supplies, labor, dry dockage and other necessaries were furnished of the reasonable value of $5,-160. The Answer of the respondent admits that certain repairs and services were furnished to the vessel but denies that the value of the same was $5,160. At the trial, the shipyard placed in evidence an itemized statement showing the various services performed and the charges therefor, which statement contáined a certificate signed by the master of the vessel that the work had been authorized to be performed by the shipyard, and that the same had been completed satisfactorily. Louis. L. Green, III, Vice President of Charleston Shipyards, Inc., testified that the charges shown in the statement were reasonable and proper and that no part of the same had been paid. No contradictory evidence on the subject was offered by the respondent. Upon the evidence before me, I am of the opinion that the libellant is entitled to recover this sum of $5,160.

The second item of claim advanced by the shipyard is for raising, floating, cleaning and otherwise caring for the vessel after it sank at the dock of the shipyard. It is asserted by the shipyard that the reasonable charge for this service was $15,000, which amount of charge the shipyard attempted to support by showing that Salmons Dredging Company had offered to perform this service for the sum of $15,000, but no agreement in respect thereto was ever reached.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
188 F. Supp. 71, 1960 U.S. Dist. LEXIS 3261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charleston-shipyards-inc-v-motor-vessel-poling-bros-v-southcarolinaed-1960.