Charles William Massie, III v. Inexco Oil Company

798 F.2d 777, 92 Oil & Gas Rep. 134, 1986 U.S. App. LEXIS 29009
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 27, 1986
Docket85-4724
StatusPublished
Cited by11 cases

This text of 798 F.2d 777 (Charles William Massie, III v. Inexco Oil Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charles William Massie, III v. Inexco Oil Company, 798 F.2d 777, 92 Oil & Gas Rep. 134, 1986 U.S. App. LEXIS 29009 (5th Cir. 1986).

Opinion

W. EUGENE DAVIS, Circuit Judge:

Defendant appeals a judgment ordering the partial cancellation of its mineral lease. *778 We disagree with the district court’s interpretation of the lease and reverse.

I.

The genesis of this litigation comes from a mineral lease granted to Inexco Oil Company by Charles William Massie. The lease, dated October 14, 1977, contains a typical habendum clause which grants Inexco a primary term of three years, but allows extension of the lease’s life beyond the primary term by production of minerals or by “any other manner” provided for in the lease. 1 One such “other manner” is the right to make as many attempts to discover minerals “after the primary term and after beginning operations for the drilling of a well” as Inexco pleases so long as the operations are conducted in good faith and no more than ninety days expire between stopping work on one well and commencing work on another (continuous operations clause). 2

The parties agree that the lease’s primary term ended on October 13, 1980. Before that date, Inexco drilled four wells on the leased property. Production was established only by the third well at a depth of approximately 13,448 feet. The fourth well was spudded on October 3, 1980, but was lost shortly after the primary term ended. Within ninety days of this loss, Inexco spudded a fifth well on Massie’s land but ceased drilling on April 29, 1981; no other wells were drilled on the Massie lease. But on July 25, 1980, Inexco began drilling a well on an adjacent tract covered by a separate mineral lease. This well was completed as a producer on November 6, 1980, at a depth of approximately 14,298 feet. On April 23, 1981, before drilling operations on the Massie lease had ceased, a unit was formed (effective March 10, 1981) that included this well and a substantial portion of the land covered by the Massie lease.

After formation of the unit, Massie filed this diversity suit seeking cancellation of the lease. Massie argues that cancellation is required by paragraph XXXIII of the lease which provides:

Notwithstanding anything to the contrary herein contained, any acreage which may be held by Lessee, its successors or assigns, at the end of the primary term by the production of oil, gas or other hydrocarbon minerals under the terms and conditions provided in this lease shall be held only to a depth of one hundred (100) feet below the stratigraphic equivalent of the base of the deepest horizon from which Lessee, its successors or assigns, shall have established production of oil, gas or other hydrocarbon minerals in paying quantities during the primary term. Lessor reserves all oil, gas and other hydrocarbon minerals below the aforesaid depth after the end of the primary term of this lease, and this lease shall terminate as to all lower depths.

Placing emphasis on the second sentence, Massie contends that paragraph XXXIII is *779 an absolute depth termination clause. Massie argues that the continuous operations clause cannot be used to hold the lease after the primary term, but can only be used to drill to depths which were earned by production established at the end of the primary term. Under his interpretation, when the primary term ended on October 13, 1980, the lease terminated as to all depths below 13,548 feet, the depth at which Inexco established production before October 13, 1980, plus one hundred feet; therefore, Inexco can drilí'to any depth so long as it is above 13,548 feet.

Inexco complains that Massie’s interpretation nullifies its rights under the continuous operations clause to hold the lease after the primary term by continuous operations. Emphasizing the first sentence of paragraph XXXIII, Inexco concludes that this paragraph applies only when acreage is held beyond the primary term solely by production. Inexco asserts that the second sentence, upon which Massie. relies, refers back to and is limited by the first sentence. As Inexco interprets paragraph XXXIII, the termination clause was not triggered until April 29, 1981, when it ceased drilling the fifth well on the leased property; its continuous operations served to hold the entire lease under the continuous operations clause until that date. Inexco argues that once its operations ceased on April 29, 1981, the Massie lease was held solely by production and paragraph XXXIII terminated its rights to all horizons 100 feet below the deepest production established on that date or 14,398 feet.

The district court, in a careful opinion, agreed with Massie’s interpretation of the lease with one significant modification. The court found that paragraph XXXIII operated as an absolute depth cutoff only when production was established before the end of the primary term; the court concluded that if production were established during the primary term, the continuous operations clause could be used to hold the lease after the primary term as to depths above the strata at which production was established, but could not be used to hold the lease below that level. But, if production is not established at the conclusion of the primary term, the district court concluded that paragraph XXXIII is inapplicable and all horizons can be maintained by continuous operations. Because Inexco did establish production before October 13, 1980, the court held that paragraph XXXIII terminated Inexco’s rights in the lease to all depths below 13,548 feet. 614 F.Supp. 880. Inexco now brings this appeal to restore rights under the lease to minerals between 13,548 and 14,398 feet.

II.

The interpretation of a contract is a question of law, Chevron U.S.A., Inc. v. Belco Petroleum Corp., 755 F.2d 1151 (5th Cir.), cert. denied, — U.S.—, 106 S.Ct. 140, 88 L.Ed.2d 116 (1985), and we conduct a de novo review of the district court’s interpretation of the Massie lease. In undertaking this review, we follow the substantive law of Louisiana.

Under Louisiana law, codal provisions applicable to ordinary leases are applicable to mineral leases. La.Rev.Stat. Ann. § 31:2 (West 1975); Bouterie v. Kleinpeter, 258 La. 605, 247 So.2d 548 (La.1971). The articles on contract construction require that we determine the intent of the parties as expressed in the lease without rendering any part of the instrument meaningless. La.Civ. Code Arts. 2045, 2050 (West Supp. 1986). Where the words are “clear, explicit, and lead to no absurd consequences, the meaning and intent of the parties must be sought within the four corners of the instrument and cannot be explained or contradicted by parole evidence.” Texaco, Inc. v. Newton and Rosa Smith Charitable Trust, 471 So.2d 877, 881 (La.App. 2d Cir.1985). After reviewing the Massie lease, we find it clear and unambiguous, but conclude that the district court erroneously rejected Inexco’s interpretation of the lease.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
798 F.2d 777, 92 Oil & Gas Rep. 134, 1986 U.S. App. LEXIS 29009, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charles-william-massie-iii-v-inexco-oil-company-ca5-1986.