Charles Orlando & Sons v. J. B. Talley & Co.

162 So. 2d 142, 1964 La. App. LEXIS 1444
CourtLouisiana Court of Appeal
DecidedMarch 2, 1964
DocketNo. 1280
StatusPublished
Cited by1 cases

This text of 162 So. 2d 142 (Charles Orlando & Sons v. J. B. Talley & Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charles Orlando & Sons v. J. B. Talley & Co., 162 So. 2d 142, 1964 La. App. LEXIS 1444 (La. Ct. App. 1964).

Opinion

HENRY F. TURNER, Judge pro tem.

Plaintiff, a partnership composed of Frank, Vincent and Charles Orlando, brought this suit for $11,576.74 alleged to be due under a contract under which it had agreed, to furnish and deliver sand to defendant on a state project at Bayou des [143]*143Allemands, in Lafourche and St. Charles Parishes. The contract, dated December 5, 1960, provides in the pertinent clause:

“Seller agrees to sell to Purchaser, and Purchaser agrees to buy from Seller approximately 225,000 cubic yards of select sand or ‘Select Barrow Item’ on project, which Seller is to deliver to that portion of the approaches to Bayou des Allemands Bridge, here in the State of Louisiana, better known as State Project #5-07-31 and 5-08-21, and Federal A Project #F-216(14), in accordance with the following terms and conditions.
“(a) Seller will furnish and deliver ‘Select Barrow Item’, or Select Sand as specified or called for in the State Projects #5-07-31 and 5-08-21 and Federal A Project #F-216(14) for the State of Louisiana; said project is the approach to Bayou des Alle-mands Bridge, bearing Item #1-4-5. All spreading, grading, and compaction to be performed by the Purchaser and at no time is this contract to be interpreted in any way other than a sale of said ‘Select Barrow Item’ at a site to be designated by Purchaser.
“(g) Seller agrees to haul or deliver an average of 2500 cubic yards per day — this average to be computed on work days only and excluding acts of God and any other unforeseen circumstances beyond control of Seller. It is agreed that the Seller shall deliver not less than 1500 cubic yards per day and if the Seller does deliver less than an average of 1500 cubic yards per day beginning from date of work order until completion of the project, then the Purchaser shall pay $1.04 per cubic yard instead of $1.10 per cubic yard.
“Provided that if the sand which is presently being delivered has to be rewashed or processed, purchaser will bear the expenses, for that. If it becomes necessary to stock-pile or relay same he will also bear this expense. Purchaser has the option of doing the above himself at his expense.”

The contract ran from its date, the plaintiff having delivered pursuant to it from that time, to October 5, 1961, a total of 305 days. By stipulation of the parties, plaintiff delivered a total of 188,231 cubic yards of sand; 181,231 were delivered pursuant to the contract under which plaintiff seeks to recover.

This suit is to recover for sand delivered to the defendant pursuant to the contract at the price of $1.10 per cubic yard, the defendant having paid plaintiff at the lower rate, contending that less than 1500 cubic yards per day were delivered to him.

The Court below decided in favor of plaintiff. Because one sentence in paragraph (g) of the contract provided that seller should work a minimum of six days per week, and the next sentence in paragraph (g) provided for computation of the average amount delivered, he concluded that only six days per week should be counted in determining whether the minimum of 1500 cubic yards per day was met. He also excluded 31 days because of rain, high water, Hurricane Carla and the lack of personnel of defendant on the job. Thirty-two days were omitted for delay caused by investigation by the State as to certain specifications as to quality of sand delivered having been met. Ninety-eight more days were excluded because the State was testing the sand of plaintiff, and it could not be delivered to the job site before having been tested and approved by engineer for the State.

The defendant has appealed the judgment of the Trial Court contending that the lower Court erred in finding that the plaintiff had delivered the minimum of 1500 cubic yards per day pursuant to the contract. The Trial Judge found that from December 5, 1960 to October 5, 1961, there were a total of 305 calendar days. From this figure he subtracted 43 days, as non-work days (no [144]*144doubt Sundays), leaving a total of 262 working days in that period of time. He found, based on the testimony of the engineer for the State of Louisiana, who had kept a day-to-day diary on the project, which diary was filed in evidence, that no hauling was done for 98 days because the State of Louisiana was testing the sand to be hauled. He found that no hauling was done on 32 days because the State of Louisiana halted the project because of alleged irregularities to be investigated and that no hauling was done for 31 days because of rain, high water, Hurricane Carla and no personnel of defendant on the job site. Subtracting these days, he found that there were only 101 days available to plaintiff as working days. Of course, that number of days divided into the amount of sand hauled would qualify plaintiff to collect the higher price, or $1.10 per cubic yard. The defendant contends that the 43 days (Sundays) should not have been deducted and that the 98 days delay due to the State of Louisiana’s testing of the sand were also improperly deducted.

Conceding that the 43 days (Sundays) deducted were a proper exclusion, if we disallow the 98 days delay caused by the State testing the sand, plaintiff has not met its requirements under the contract. We think the lower Court erred in making both deductions.

Prior to the contract sued upon and as far back as July 26, 1960, this plaintiff and defendant had contracted for the sale and purchase of sand, which contract of July 26, 1960 was amended by an addendum on November 28, 1960. Sand during this period of time was sold by the plaintiff and delivered to the defendant and both parties were thoroughly familiar with the conditions and procedures necessary to be met in order to have the sand tested, delivered and placed on the job site.

While we have studied the entries made in the daily diary kept by the engineer for the State, we are unable to determine therefrom how many days were lost by plaintiff’s inability to haul and deliver sand caused by the State’s testing. However, conceding 98 days were lost due to the testing, it is our opinion that the contract does not allow exclusion of non-work days and days on which defendant was prevented by unforeseen circumstances beyond his control, from delivering in computing the number of average cubic yards plaintiff has delivered for purposes of determining the price to be paid. It will be noted that the first sentence of paragraph (g) of the contract provision quoted above contains an express provision for the exclusion of certain days in determining the amount of sand (2500 cubic yards per day average) to be purchased under the contract. The second sentence (providing for 1500 cubic yards per day average), with which we are concerned, contains no such provision, and we cannot write such a provision into it in the absence of any indication by the parties that such was their intention. There is nothing in this contract or in the testimony of the parties, as to their understanding of it, to indicate that they believed at the time of its execution that such an exclusion should be applicable to the provision or determination of price. We are, thus, constrained to find that the requirement of delivery of 1500 cubic yards per day was to be computed on the total number of days for which the contract was to run with the risk on the seller for its inability to meet this minimum requirement in order to receive a higher price. Having taken this view, it is obvious that 1500 cubic yards per day were not delivered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Orlando v. Talley
164 So. 2d 354 (Supreme Court of Louisiana, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
162 So. 2d 142, 1964 La. App. LEXIS 1444, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charles-orlando-sons-v-j-b-talley-co-lactapp-1964.