Charles H. Sword v. Wilson Rains

575 F.2d 810, 61 Oil & Gas Rep. 339, 1978 U.S. App. LEXIS 11298
CourtCourt of Appeals for the Tenth Circuit
DecidedMay 8, 1978
Docket76-1872
StatusPublished
Cited by1 cases

This text of 575 F.2d 810 (Charles H. Sword v. Wilson Rains) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charles H. Sword v. Wilson Rains, 575 F.2d 810, 61 Oil & Gas Rep. 339, 1978 U.S. App. LEXIS 11298 (10th Cir. 1978).

Opinion

McWILLIAMS, Circuit Judge.

This case concerns an oil and gas lease. Charles H. Sword, the owner of 160 acres of land in Meade County, Kansas, entered into an oil and gas lease for a primary term of one year commencing July 23, 1971. Sword subsequently executed an extension of the lease whereby the primary term of the lease was extended an additional three months, from July 23, 1972, to October 23, 1972. The landowners adjacent to Sword also executed oil and gas leases. All the leases, including Sword’s eventually were assigned to and became vested in Wilson Rains and Arthur W. Skaer, and others, who will hereinafter be referred to as Rains.

On September 23,1972, Rains commenced a test well on Sword’s land. On October 7, 1972, a drill stem test indicated the presence of gas. Total depth was reached on October 15, 1972, on which date casing was set. By November 8, 1972, the well was completed, was flowing gas, and was ready for pipeline connection except for final open flow testing.

Rains next began efforts to market the gas. These efforts will be considered later and need not at this point be detailed. It is sufficient here to simply note that Rains made contact with Panhandle Eastern Pipe Line Company, and others, as possible purchasers of the gas. Negotiations with Panhandle ensued, resulting in the signing of a contract for the sale of the gas on June 6, 1973. Thereafter Rains commenced operations to lay a pipeline to Panhandle’s gathering system, some .7 miles distant. On *812 August 20, 1973, gas deliveries to Panhandle commenced. In the fall of 1974 a twenty-year gas purchase contract with Panhandle was finalized.

On October 23, 1973, Sword, a citizen of California, commenced the present action in the United States District Court for the District of Kansas. Jurisdiction was based on diversity. The action sought to have the oil and gas lease executed by Sword declared terminated and to quiet title to the land in Sword. It was Sword’s theory of the case that the oil and gas lease had expired under its own terms because of the failure of Rains to comply with certain lease deadlines. Rains had entered into a unitization agreement with landowners adjacent to the Sword land, and Sword also sought in the present proceeding to have the unitization agreement set aside.

Trial of the case was to the court. The trial court entered detailed findings of fact and conclusions of law which held, in essence, that the unitization agreement was valid, and that, under the “continuous operation” clause in the oil and gas lease, the lease had not expired and that there had been no breach thereof by Rains. Accordingly, the trial court entered judgment dismissing Sword’s claims “on the merits.”

On appeal, Sword does not challenge that part of the trial court’s judgment upholding the unitization agreement. He does, however, seek reversal of the judgment insofar as it dismissed his quiet title claim.

As previously mentioned, the oil and gas lease under consideration was for a primary period of one year, commencing July 23, 1971. On June 21, 1972, the lease was extended for a period of three months to October 23, 1972. Specifically, the extension agreement provided that said term of said lease shall be and is hereby extended, with the same tenor and effect as if such extended term had been expressed in such lease, for a period of three months from the date of the said expiration thereof and as long thereafter as oil or gas (including casing lead gas) is produced from any well on the land covered by said lease; . . . ”

As indicated, Rains commenced drilling on the leased premises on September 23, 1972. This occurred within the primary term of the lease, as extended. By October 23, 1972, the expiration date of the primary term of the lease, as extended, Rains had completed his test drilling and had discovered gas in paying quantities. The well itself was substantially completed by November 8, 1972, and then shut down, because of adverse weather.

The habendum clause of the Sword lease provides for a primary term of one year from its date, which was later extended for an additional three months, “and as long thereafter as oil or gas, . . . and oth-

er minerals may be produced from said leased premises or operations for the drilling or production thereof are continued as hereinafter provided.”

Section 7 of the lease, the so-called “continuous drilling” provision, reads as follows:

7. It is expressly agreed that if the lessee shall commence operations for the drilling of a well at any time while its lease is in force this lease shall remain in force and its terms shall continue for so long as such operations are prosecuted and, if production results therefrom, then so long as such production may continue.

Under the terms of the lease, then, if Rains commenced drilling a well within the primary term of the lease, as extended, which he did on September 22, 1972, the lease shall remain in force and continue “for so long as such operations are prosecuted,” and if there be production, “so long as such production may continue.”

Under Kansas law, in the absence of a continuous operations clause, there must be actual production within the primary period of the lease, and without such production, the lease will expire by its own terms. Home Royalty Association v. Stone, 199 F.2d 650 (10th Cir. 1952). However, a “continuous operation” clause extends the lease for so long as the lessee-operator exercises due diligence in equipping the well and getting it into production, which includes the marketing of the gas. Christian- *813 son v. Champlin Refining Co., 169 F.2d 207 (10th Cir. 1948). To the same effect, see Tate v. Stanolind Oil & Gas Company, 172 Kan. 351, 240 P.2d 465 (1952). In Tate, the Kansas Supreme Court spoke as follows:

From this provision [a continuous operations clause], standing alone, it clearly appears that even though a well is only commenced during the primary term, it may be completed thereafter with reasonable diligence and dispatch. Obviously if on completion of drilling operations oil or gas is found in paying quantities the lessee, under this clause, is not expressly required to produce or market the oil or gas immediately. And, of course, that might be wholly impossible. He would, however, be required to do so within a reasonable time. But even if the drilling clause reasonably could be interpreted as requiring both production and marketing immediately upon completion of the well it is nevertheless clear the necessity therefor was extended beyond the fixed primary term.
******
It is impossible to lay down an accurate general rule with respect to what constitutes production or marketing within reasonable time in every case. Whether either has been so obtained must be left to the particular facts of cases as they arise.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
575 F.2d 810, 61 Oil & Gas Rep. 339, 1978 U.S. App. LEXIS 11298, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charles-h-sword-v-wilson-rains-ca10-1978.