Chardon Park v. Great Lakes Crushing, Unpublished Decision (12-30-2004)

2004 Ohio 7221
CourtOhio Court of Appeals
DecidedDecember 30, 2004
DocketNo. 2003-G-2524.
StatusUnpublished
Cited by8 cases

This text of 2004 Ohio 7221 (Chardon Park v. Great Lakes Crushing, Unpublished Decision (12-30-2004)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chardon Park v. Great Lakes Crushing, Unpublished Decision (12-30-2004), 2004 Ohio 7221 (Ohio Ct. App. 2004).

Opinion

OPINION
{¶ 1} Appellants, Marla Parkway, Ltd. ("Marla Parkway"), and Chardon Park, Inc. ("Chardon Park"), appeal from a judgment entry of the Geauga County Court of Common Pleas, denying their claim and awarding damages to appellee, Great Lakes Crushing, Ltd. ("Great Lakes"), on its counterclaim. For the reasons set forth below, we affirm the judgment of the trial court.

{¶ 2} Appellants were, respectively, the owner and developer of a commercial subdivision in Chardon, Ohio. The subdivision land was approximately a 15.5 acre parcel with a twenty foot slope. John DiFini ("Mr. DiFini") owned the property and transferred it to Marla Parkway for development. Mr. DiFini formed Chardon Park to serve as the general contractor for the project. Marla Parkway retained Chagrin Valley Engineering to prepare a development plan consisting of eight to ten commercial sites accessed by a dedicated street running west from State Route 44, sometimes referred to as the Fifth Avenue Extension, in the city of Chardon, Ohio. Chagrin Valley Engineering's December 1999 plans were approved by the city in early 2000.

{¶ 3} Great Lakes was an excavating company which contracted with Chardon Park to make site improvements within the subdivision. Mark M. Belich ("Mr. Belich"), owner of Great Lakes, wanted to bid on the excavation portion of the development project, and he reviewed the improvement plans with Mr. DiFini. In a letter from Great Lakes to Chardon Park, dated May 15, 2000, Great Lakes provided a bid quotation for work to be done on the development scheme.

{¶ 4} The letter stated, "[l]abor only for Chardon Park, Inc. Development, a Roadway Right-of-Way Improvement, to include the following: Sanitary sewer complete[,] Storm sewer complete[,] Excavation and embankment[,] Top soil redistribution[,] Grading for hydro-seeding[,] Right-of-way and retention basin area only[,] Demolition of house and van[,] Erosion control[,] Underdrain installation[,] 304 [limestone] and fabric installed only[,] +/- 1/10 of a foot." The bid quotation noted that the following were excluded: bond fees, inspection fees, material purchases, back charges for material over runs, night work, hydro-seeding or seeding, rock excavation, fine grading for curbs or asphalt, gas, phone, electric cable trenching, right-of-way construction and retention basin, and out lot development. The bid quoted a lump sum price of $162,000, and payment was to be on the percentage complete every thirty days.

{¶ 5} According to the quotation, "[s]igning of this quotation acts as acceptance to the above pricing and terms." The quotation was signed by Mr. DiFini, on behalf of Chardon Park, and by Mr. Belich, on behalf of Great Lakes. As such, this quotation became the contract upon which the instant action and subsequent appeal are based. The contract was less than two pages in length and is exceptionally brief and lacking in detail for a project of this magnitude. It was never supplemented in writing.

{¶ 6} According to Mr. DiFini, the contract meant that Great Lakes would finish the storm sewers, sanitary system, water lines, and all grading, enabling the project to be ready for "proof roll." Mr. DiFini testified that "* * * proof roll is that all the ground must be zero tolerance throughout the whole road area, to be completely compacted and approved by the city, so that they will go to the next phase to put the stone down and do the curb." After that, the gutter and asphalt is put down and the road is completed. Mr. DiFini testified that "all nine yards," including asphalt paving, were to be completed by the end of 2000. Mr. Belich's testimony did not challenge this.

{¶ 7} Appellants allege in their appellate brief that "[a]ll work was to be done according to Chardon city code and subject to final approval by the city." This requirement was stated on the improvement plans, upon which the contract was based. Those plans were reviewed by Mr. Belich in the presence of Mr. DiFini. Further, both Mr. Belich and Mr. DiFini testified that all construction and materials had to comply with Chardon city code. However, this requirement was not separately contained within or referenced by the contract. Mr. DiFini admitted that he was not familiar with the city code.

{¶ 8} Chardon Park hired Pat Salango ("Mr. Salango"), a registered surveyor with thirty-five years of experience, to survey the property and lay out and stake the improvements. According to Mr. Salango's testimony, he staked the center line of the right-of-way first and then located sewer crossovers, catch basins, and manholes.

{¶ 9} Great Lakes began work on the site on June 23, 2000, working until August 2000. Great Lakes had many no shows beginning August 18, 2000, and only returned to the project for a few days in October 2000, last working on October 19, 2000.

{¶ 10} Mr. Salango testified that after he initially staked the project, he was called back to do additional staking. According to Mr. Salango, this is common because "* * * earthmovers really play havoc to these stakes that you put in the centerline of the road. They either knock them out, cover them up, dig them up, so forth * * *." Mr. Salango testified that the only reason the center line of the road was re-staked was because Great Lakes removed or knocked out the stakes. He also stated that neither Great Lakes nor any of its employees ever contacted him to question the accuracy of his staking.

{¶ 11} Mr. Salango became aware that the elevation of a catch basin and storm sewer was not correct. Mr. Salango testified that when he originally staked the project, he staked the inlet on the side of the road which would lead into the catch basin for a storm sewer. He was not able to stake the outlet from the catch basin to the pipe because, on that day, Great Lakes was moving a lot of dirt in the area to which the catch basin emptied. Thus, Mr. Salango was not able to stake the exact sewer location. When he returned the next day, despite the lack of a stake indicating the elevation of the outlet, the basin had already been completed. Great Lakes did not admit any evidence challenging this.

{¶ 12} Quality Control Inspection, Inc. ("QCI") was the designated agent for monitoring and documenting the progress of the improvements in the city. A QCI inspector was required to be on site when right-of-way improvements were made. The inspector had a duty to document his observations in daily work reports and submit them to the Public Service Department.

{¶ 13} On August 10, 2000, an inspector noted an improperly installed catch basin and errors in the original drawings. As a result, Mr. Belich had expressed some concern about the accuracy of the staking to Mr. DiFini. Chardon Park agreed with Great Lakes to hire Aztech Engineering and Surveying ("Aztech") to confirm the accuracy of the staking. In November 2000, Aztech provided the services of Ralph W. Gromley ("Mr. Gromley"), a registered surveyor. Mr. Gromley testified that he found the stakes and the grades in existence to be installed according to the prints. According to Mr. Gromley, some occasional stakes were missing, but he testified that "* * * as anyone would know in the contracting business that as work goes along equipment can bump a stake or hit a stake or a stone gets pushed up against it and it gets pushed out. * * * Let's say if we put in a hundred stakes, I would say 80 to 85 percent of the stakes stay for every time that you stake." Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

V.C. v. O.C.
2021 Ohio 1491 (Ohio Court of Appeals, 2021)
Estie Invest. Co. v. Braff
2018 Ohio 4378 (Ohio Court of Appeals, 2018)
Gerston v. Parma VTA, L.L.C.
2018 Ohio 2185 (Ohio Court of Appeals, 2018)
MacDowell v. Decarlo, Unpublished Decision (1-24-2007)
2007 Ohio 249 (Ohio Court of Appeals, 2007)
Mulchin v. Zzz Anesthesia, Inc., Unpublished Decision (11-3-2006)
2006 Ohio 5773 (Ohio Court of Appeals, 2006)
Galay v. Ohio Dept. of Transp., Unpublished Decision (8-10-2006)
2006 Ohio 4113 (Ohio Court of Appeals, 2006)
Kimbler v. Kimbler, Unpublished Decision (5-23-2006)
2006 Ohio 2695 (Ohio Court of Appeals, 2006)
Mentor v. Csx Transp., Unpublished Decision (7-1-2005)
2005 Ohio 3386 (Ohio Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 7221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chardon-park-v-great-lakes-crushing-unpublished-decision-12-30-2004-ohioctapp-2004.