Chapman v. Bent

65 P. 959, 6 Cal. Unrep. 740, 1901 Cal. LEXIS 1248
CourtCalifornia Supreme Court
DecidedJuly 24, 1901
DocketL. A. No. 987
StatusPublished
Cited by2 cases

This text of 65 P. 959 (Chapman v. Bent) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chapman v. Bent, 65 P. 959, 6 Cal. Unrep. 740, 1901 Cal. LEXIS 1248 (Cal. 1901).

Opinion

HAYNES, C.

Action for work, labor and services. The plaintiff had findings and judgment, and defendant appeals from the judgment and from an order denying a new trial.

In April, 1899, the defendant entered into a contract with the South Mountain Water Company to construct for it a pipe-line near Eedland's. On June 1st he entered into a contract with one George Nolan, in writing, to haul the pipe and cement necessary to construct it from the railroad, and distribute it along the line, for the first part of the line, to a specified point, at the price of $1.15 per ton, and for the remainder—the longer haul—at $1.50 per ton; Nolan “to stand all breakages in handling and hauling” the pipe. The plaintiff, D. D. Chapman, was consulted by Nolan in determining the terms upon which the contract should be taken, but, so far as known to Bent, had no interest in it, except that when Nolan commenced work under his contract, about June 9th, Chapman put on several teams, and did hauling thereon for Nolan upon the terms specified in the contract between [742]*742Nolan and defendant. The contract between defendant and the water company required the pipe-line to be completed on or before August 1st. Nolan, as well as Chapman, put on several teams, but about the last of June defendant became convinced that, unless more teams were put on, the pipe would not be hauled in time .to complete the line within the time limited therefor. Defendant thereupon notified Nolan to put on more teams, and was told that he could not find them, and Nolan thereupon authorized defendant to procure them, and to pay for them at the rate of six dollars per day, the teams so procured to be first paid for out of the money that would be due to him under his contract. Defendant thereupon advertised for teams, and procured sufficient, in conjunction with the teams of Nolan and the plaintiff, to complete the hauling on July 31st. The plaintiff claims that about the last of June or first day of July he quit working for Nolan, and thereafter worked for Mr. Bent; and this action is prosecuted to recover therefor. The action is upon a quantum meruit for work, labor and services in furnishing teams for the defendant for hauling water-pipes, alleged to be of the value of $750. The court found the value to be $456, and gave judgment therefor.

When suit was commenced, the defendant demanded a bill of particulars of plaintiff’s claim, and it was furnished, showing the number of teams furnished by plaintiff each day from July 1st to July 26th, both days included. ' The plaintiff testified, in substance, that he was working for Nolan up to the 1st of July, and after that he worked for Mr. Bent; that he sent word to Mr. Bent by two of his teamsters, Reynolds and Dutch, that, if he wanted him to team, he would have to pay for it himself; that next morning, June 29th, he thought, he saw Mr. Bent, and told him he would have nothing more to do with Nolan, and, if he did any more hauling, he must pay for it himself, and that Bent said he would if he (plaintiff) did the work; that plaintiff continued to work, and put on three more teams, and kept on working until the job was finished. Upon cross-examination he testified that he did not suppose that he could compel Bent to pay for the work he had already done, but that he asked him if he could not see that he got his pay for that, and that Bent agreed to pay him for what he had already done if Nolan would give an order, and [743]*743that Bent said he would get an order, and that he commenced' work for Bent on the 1st of July; that he had been hauling for Nolan by the ton, but he had no understanding with Bent as to whether he should be paid by the day or the ton, but supposed he was to work by the day, and did not know whether he worked by the day or the ton; that he changed his mind about working for Nolan because Nolan was going to Mexico with his outfit, and Bent was hiring other teams at six dollars per day, and that he knew Bent had obtained an order from Nolan. Reynolds testified that plaintiff sent him to Bent with a message “that, unless Bent would pay him for hauling, that he would not haul any more”; and Bent said he would pay him; that he did not want him to quit hauling. This witness was cross-examined at considerable length, and his attention was called to his deposition taken in the case, and, among other things, the following: “ Q. State what message you delivered. A. Mr. Chapman told me to tell Mr. Bent that, unless he would secure his pay for hauling, he wouldn’t haul any more, but would take his teams off.” Daniel Leibee, called for the defendant, testified that on or about July 16th he was trying to see Bent to get a job of hauling, but did not find him; that Chapman told him he could go on with his team at $6 per day, and said, “My teams are hauling by the ton.” The defendant, testifying in his own behalf, testified: That at the time he made his contract with Nolan, Nolan said that Chapman was trying to back out of the whole thing now. That Chapman undertook to explain, but Bent said that it did not concern him, as his bid was from Nolan. That Nolan then said, “Of course, Chapman and I are working together on it.” That he (Bent) could not state the exact words, but that he was given to understand that they expected to put on an equal number of teams; and that Chapman, as Mr. Nolan expected to go away to Mexico, would have a general supervision of the work. That the work was commenced .June 9th, but it soon began to drag, and he sent Mr. French to Chapman repeatedly to tell him “that he must put on the teams that he led us to believe he would, or else tell us he would not.” That he came near forfeiting half of his contract on account of the delay in hauling. That he then arranged with Nolan to get teams by the day; to pay six dollars for four-horse teams, and to [744]*744pay them first of -all out of moneys due to Nolan. That on July 5th or 6th he met two of Chapman’s teams as he was driving along the road in his buggy, and the teamsters told him that Chapman wanted to see him, and he asked, What about? and they said, “He wants to know where his pay is coming from”; and that he replied he would see him. That he did not say that he would pay him, or be responsible for his pay. That he drove over to see Chapman the next day, and he said he wanted to make some arrangement by which he (Bent) would guarantee his pay. That he (Bent) said: “What is the matter with Nolan?” That Chapman replied: “Nolan is all right, but he is going to Mexico, and I don’t want to chase him for a year or two to get my money to come through him. I want you to secure it. I want you tó guarantee it.” That witness replied: “I can’t do that, Mr Chapman. I have no contract with you. My deal is with Mr. Nolan.” That Chapman then said: “Then I will have to take off my teams, because I won’t run any risk.” That witness replied: “I don’t want you to do that. Why don’t you get an order from him?” He replied: “I ean’t get an order from him.” That witness said: “I will. Perhaps I can help you get an order”; and Chapman replied: “If you can, get an order, so that I am safe, I will go on and haul.” That witness telephoned for an order, and received it on the 8th or 9th. It was dated July 7th. That two or three days after that he passed Chapman on the róad, and told him that he got the order, and Chapman replied, “All right,” and both drove on, neither stopping the horses. That about ten days afterward Chapman asked whether the order covered the board of his teamsters and his blacksmith, and Mr. Bent replied that he did not know; that he had to pay him out of the money due Nolan when he and Nolan have agreed upon the amount; and that Chapman replied: ‘All right.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

De la Rosa v. Sucrerie Centrale Coloso de Porto Rico
9 P.R. Fed. 424 (D. Puerto Rico, 1917)
Gage v. Billing
108 P. 664 (California Court of Appeal, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
65 P. 959, 6 Cal. Unrep. 740, 1901 Cal. LEXIS 1248, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chapman-v-bent-cal-1901.