Channel Dry, Inc. v. Haver

590 N.E.2d 868, 70 Ohio App. 3d 197, 1990 Ohio App. LEXIS 5268
CourtOhio Court of Appeals
DecidedNovember 5, 1990
DocketNo. 1-89-56.
StatusPublished
Cited by9 cases

This text of 590 N.E.2d 868 (Channel Dry, Inc. v. Haver) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Channel Dry, Inc. v. Haver, 590 N.E.2d 868, 70 Ohio App. 3d 197, 1990 Ohio App. LEXIS 5268 (Ohio Ct. App. 1990).

Opinion

Guernsey, Judge.

This is an appeal by the plaintiff, Channel Dry, Inc., from a judgment of the Court of Common Pleas of Allen County in an action brought against the *199 defendant, George Haver, for money damages for breach of contract. Other defendants in the original action on an account for labor and materials and for foreclosure of plaintiffs mechanic’s lien were dismissed at the time the complaint was amended to seek only money damages for breach of contract. In that second amended complaint plaintiff alleged the execution on December 7,1987, of a written contract between the parties whereby the plaintiff was to furnish labor and materials for home repairs in the total agreed amount of $8,588; that the defendant made a down payment of $2,588; that plaintiff commenced providing services pursuant to the contract but that defendant wrongfully prevented plaintiff from finishing work thereon; and that the defendant has, upon demand, refused to pay the $6,000 balance due on the contract to plaintiff’s damages in that amount.

After trial the lower court filed its decision and judgment entry wherein it found, among other things not material to our decision, that the purpose of the contract was to correct water problems in the crawl space of defendant’s home; that the contract was executed and down payment made as aforesaid; that plaintiff commenced work according to the contract on December 9,1987, and was discharged by the defendant on December 19, 1987, the defendant claiming that the plaintiff had not complied with the terms of the contract; and that after the defendant repudiated the contract he contracted with another contractor to complete the work contemplated by the contract for the sum of $4,980.

The trial court specifically found, in pertinent part, “that the defendant was not justified in terminating the contract”; “that the workmanship of the plaintiff’s employees was not below standard and was proper for the type of work in this particular instance”; and “that from the plaintiff’s own evidence that the cost of material, if plaintiff would have been permitted to complete the job, would have been One Thousand Dollars ($1000.00) and their actual total cost for labor and materials if plaintiff would have been allowed to complete the job would have been approximately Two Thousand Five Hundred Dollars ($2,500.00).” (Emphasis added.) At another place in its judgment entry the trial court made the ambivalent and conflicting finding “that the actual costs to the plaintiff if the contract would have been completed, including material and labor, was Two Thousand Five Hundred Dollars ($2,500.00).”

The court observed “that generally the rule for the measure of damages is that the party whose contract has been breached without his fault is entitled to fair and reasonable compensation for his loss”; “that [u]nder such circumstances the Court can award what will fairly and reasonably compensate the plaintiff from a loss resulting from defendant’s breach, including a reasonable *200 amount for services performed, including work, labor and material; or, award an amount of damages that will fairly and reasonably compensate the plaintiff for its actual loss resulting from the breach of the contract, which puts the plaintiff in the position in which he would have been if the contract had been fully performed”; and that “this action should have been more appropriately filed in the Lima Municipal Court”; “[h]owever, since filed in the court of equity, the court feels obligated to do equity.”

The court quoted the following provision of the written contract:

“ARBITRATION In the event any dispute shall arise between the parties to this contract as to the respective duties, rights and liabilities thereunder, it is hereby agreed that such dispute shall be referred to the Better Business Bureau, Inc. for arbitration, and the decision of the arbitrators shall be final and binding on said parties.”

The trial court then found and observed:

“The Court finds that the defendant George Haver, notified the plaintiff relative to the cancellation of the contract on December 19, 1987. At this point there was a ‘dispute’. Plaintiff’s reply through its attorney dated December 22, 1987 (see Plaintiff’s Exhibit 1) did not refer at all to any arbitration, but only referred to the ‘ability to sue you to reclaim the damages caused by the wrongful rescission of your contract’. The court finds that the plaintiff, who prepared the contract and inserted the provision of arbitration, made no effort to resolve the matter through ‘arbitration,’ which was mandatory and a condition precedent herein. Possibly, if this would have been done by the plaintiff, the matter would have been resolved.”

Based on the foregoing findings, observations and conclusions, the trial court found “that it would not be just to award plaintiff the sum of Six Thousand Two Hundred Forty-two and 81/100 Dollars ($6,242.81), which is its alleged lost profits when the plaintiff itself did not attempt to comply with the mandatory arbitration provisions which would have possibly eliminated this case entirely,” and “rather than dismiss the proceedings due to plaintiff’s failure to comply with the mandatory arbitration provisions or attempt to do so prior to filing the instant case, the Court herein, in the interests of justice and equity, finds that the plaintiff is entitled to reasonable damages as a result of defendant’s breach,” and “plaintiff is granted judgment against the defendant in the sum of Two Thousand Dollars ($2,000.00).”

This is the judgment from which this appeal was taken by plaintiff. The defendant has taken no cross-appeal nor has he made any cross-assignments of error. The plaintiff assigns prejudicial error of the trial court “when it applied an equitable standard to the contract damages, which is an action at law.”

*201 We have not been favored by the filing of a transcript of the trial court proceedings (other than a partial transcript as to a discussion at trial regarding arbitration), so we must accept the findings of fact of the trial court as they appear in its journal entry of judgment as having been supported by the evidence, although we may disagree with the trial court’s conclusions of law or its mixed conclusions of law and fact appearing in its entry.

It thus appears that the trial court was confronted with a situation where under a contract between the parties the plaintiff was to provide labor and materials to complete a specific job for a fixed sum due from the defendant and was then prevented from completing that job by the unjustified action of the defendant constituting a breach of the contract. For that breach the plaintiff was entitled to and did maintain an action at law in the court of common pleas for its damages arising from the breach. Wall v. Dayton Federation Co. (1929), 121 Ohio St. 334, 168 N.E. 847. In these circumstances the damage award was governed by the appropriate application of the principles of law set forth in the paragraphs of the syllabus to Allen, Heaton & McDonald, Inc. v. Castle Farm Amusement Co. (1949), 151 Ohio St. 522, 86 N.E.2d 782, reading:

“1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

E. Liverpool v. Buckeye Water Dist.
2010 Ohio 3170 (Ohio Court of Appeals, 2010)
Tucker v. Young, Unpublished Decision (3-6-2006)
2006 Ohio 1126 (Ohio Court of Appeals, 2006)
Burke & Associates, Inc. v. Koinonia Homes, Inc.
735 N.E.2d 479 (Ohio Court of Appeals, 1999)
Austin v. Squire
691 N.E.2d 1085 (Ohio Court of Appeals, 1997)
Rock v. Merrill Lynch, Pierce, Fenner & Smith, Inc.
606 N.E.2d 1054 (Ohio Court of Appeals, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
590 N.E.2d 868, 70 Ohio App. 3d 197, 1990 Ohio App. LEXIS 5268, Counsel Stack Legal Research, https://law.counselstack.com/opinion/channel-dry-inc-v-haver-ohioctapp-1990.