Chamberlin v. McCallister & Sanders

36 Ky. 352
CourtCourt of Appeals of Kentucky
DecidedMay 2, 1838
StatusPublished

This text of 36 Ky. 352 (Chamberlin v. McCallister & Sanders) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chamberlin v. McCallister & Sanders, 36 Ky. 352 (Ky. Ct. App. 1838).

Opinion

Chief Justice Robertson

delivered the Opinion of the Court.

ONthe 15th of May, 1833, McCallister & Sanders, associate plasterers, covenanted to plaster, in a prescribed manner, three houses for “P. & J. Chamberlin;” who covenanted on their part, to pay therefor a stipulated price per square yard, in the following manner: first— $275 in a note on J. C. Bucldin, to be assigned by them on request; second — $150 on the completion of the work; third — $150 six months thereafter; scad fourth — the residue in goods from their store. The time of beginning^the work was to be as soon as the carpenters, then working-on the houses, should be “ready.”

After the plastering of one of the houses had been nearly completed, and that of another just begun, Me-Cal-lister and Sanders sent some of their workmen to the third house for the purpose of beginning their work on that also; but the other party, having, for the purpose of ensuring the completion of the whole job within convenient time, employed another mechanic to plaster that house, refused to permit the workmen of McCallister and Sanders to commence working upon it; and thereupon, they abandoned the further prosecution of the work on the other two houses. And on the 26th of November, 1835, they brought this action of covenant to recover damages for an alleged breach of covenant by P. & J. Chamberlin, in their non-payment of the stipulated price for the plastering of the three houses according to their covenant — averring, as an excuse for the non-completion of the work, the fact that they had been prevented, as just stated, from working on one of the houses.

Upon the trial of the case, on an issue on a plea of covenants performed, and on another issue on a plea tra- [353]*353' versing an allegation that the work had been commenced within the time prescribed in the covenant for beginning it — the Circuit Judge instructed the jury that; if they should “ believe that the plaintiffs commenced “ the performance of the work covenanted to be done “ on their part, and were prosecuting the same, in good “ faith, but were interrupted and prevented from doing “ the same by defendants, the'law was for'the plaintiffs, “ and they were entitled to the contract price of the work in the same manner as if the work had been actually done.”

A dec’ll on a covenant by defendants, to pay, at a certain rate, for work to be dono by the p] tls upon its completion — a part in “go'odsfrom their store,”--averring only that part of the work, was performed, & that the plt’fs were prevented by def ts, from fin ishing it.sbows no cause of action as to the non payment in goods; because it does not aver that the amount of work had been ascertained, and notified to the defendants; or that, on request, they had x-efused to unite in ascertaining it, and had nevertheless, refused, on demand at their store, to deliver the goods; or that they had dispensed with these preliminaries.

And thereupon, though the proof showed that the work actually done amounted to only $459 20, and that the plaintiffs in the action had received from the defendants 68, nevertheless the jury returned a verdict for 32 — the balance of the ascertained contract price for the plastering covenanted to be done on all three of the houses, after deducting the $610 68 which had been paid.

The judgment rendered by the Circuit Court on that verdict against the plaintiffs in error (defendants below) is now brought up for revision.

In our opinion the judgment is erroneous on several grounds.

First. The declaration is essentially defective. According to the contract, a part of the price to be paid for the work, exceeding $500, was to be discharged in goods, without any other designation of the time when that amount should be thus paid, than that the job should be first finished, and the entire contract price of it ascertained, and that then the goods should be delivered upon application. To show a cause of action as to the alleged non-payment in goods, it was necessary, therefore, to allege that the quantity of plastering done, or covenanted to be done, had been ascertained and communicated to the plaintiffs in error; or that, upon proper application, they had refused to concur in acts necessary for ascertaining it, and that nevertheless they had af[354]*354terwards, upon application at their store, refused to let the defendants in error have such goods as they had selected, of'the value ofthe sum found to be due in goods; or not*ce balance due, or an offer to ascertain it, and an -application for selected goods, had been dispensed with by some act of the plaintiffs in error. The declaration contains no such averment of any kind. And certainly some such averment was as necessary as it could have been had the declaration averred a perfect performance of all the work, instead of averring, as it did, facts intended to excusethe partial non-performance of it.

Covenants, by plaster 3 houses, by the other to rate pei. square Tic Til & terers, having done a portion two of the houses, were about the third, but bythe otherpare ty: upon which of vori”do and bro’t covenant for the whole am't of tenes satisfied consequence of the delinquency pltfs', in commencing on the house the defts had a right to employ another to do that work, as they did, the plaintiffs were not entitled to any verdict; and as the evidence did conduce to prove such delinquency — instructions—not leaving that question to the jury— ‘that if the plaintiffs commenced-the work X c. and were interrupted and prevented from doing-the same by defendants,pit fs had a right-to recover, &c wore erroneous.

In this respect, therefore, the declaration showed no cause of action, even -if the alleged excuse for non-performance of all the work be deemed equivalent, in judgment of law, to actual and full performance.

Second. The testimony authorizes doubt whether the °ffer to commence the plastering of the third house was made as soon as, by the contract, the plaintiffs,in error had aright to expect and require; and it is, therefore, not Gerta’n though the covenant was entire as to the 'three 'houses, they had not a right to rescind it as to house which they employed another mechanic to plaster. But, waiving-this question as uncertain upon t¡le faC£S jq seems to us that, if the jury had been, as perhaps they may have 'been, satisfied that, in consequence qf the delinquency or delay of the defendants in error, the plaintiffs had a right to employ another person 't° plaster the third house, not only no damages should have been assessed against them on account of that house, but the defendants in error, in that event, would have been entitled to no verdict; and may, in fact, have had no sufficient excuse for not completing †}16 work on the other two houses. And therefore it seems to us that the Circuit Judge erred in instructing íury hypothetically to find a verdict for the entire contract price, without regard to the question whether [355]*355the offer to commence the work on the third house had been made within reasonable time.

Where A cove nants to do cer tain things, e.g.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
36 Ky. 352, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chamberlin-v-mccallister-sanders-kyctapp-1838.