Chamberlain, Hrdlicka, White, Williams & Aughtry, P.C. v. ESL Ventures, LLC

Court of Appeals of Texas·Decided August 20, 2024·No. 01-23-00106-CV·Published

Opinion

Opinion issued August 20, 2024

In The

Court of Appeals

For The

First District of Texas

ESL Ventures $700,000. The trial court rendered judgment on the verdict and awarded attorney’s fees to ESL Ventures as well. The law firm now appeals.

We affirm.

BACKGROUND

Contract Dispute

ESL Ventures consults with businesses on how to reduce their expenses. It entered into a contract with Chamberlain Hrdlicka to identify ways in which the law firm could reduce its information technology and telecommunications expenses.

The contract essentially contemplated two stages of consulting. In the first stage, ESL Ventures would prepare and present a baseline report identifying the law firm’s existing information technology and telecommunications expenses. In the second stage, ESL Ventures would prepare and present a recommendation report identifying specific changes the law firm could implement to reduce its expenses. As part of this process, ESL Ventures would identify alternative vendors and solicit bids for their services, which would be incorporated into the recommendation report. ESL Ventures’ compensation would be based on the savings realized by the firm.

In recognition of the possibility that circumstances might change and require the law firm to change course on short notice, the contract allowed the firm to terminate ESL Ventures’ services before it had fully performed under the contract. This early termination provision provided for the payment of different fees

depending on how much work ESL Ventures had performed. If the law firm terminated the contract before ESL Ventures presented the baseline report, the firm was required to pay “an early termination fee equal to 5% of the annual expenditure or $20,000 for each project, whichever is less.” If the law firm terminated the contract after ESL Ventures presented the baseline report but before it presented the recommendation report, the firm was required to pay “an early termination fee equal to 10% of the annual expenditure or $40,000 for each project, whichever is less.” Finally, if the law firm terminated the contract after ESL Ventures presented the recommendation report, the firm was required to pay “an early termination fee equal to 50% of the projected savings for each project” during a specified period of time. The early termination fees set out in the contract ensured that ESL Ventures would be compensated for its work to some degree if the contract was not completed.

It is undisputed that Chamberlain Hrdlicka terminated the contract early. The parties’ dispute centers on which early termination fee applies. The law firm maintains that ESL Ventures had presented the baseline report but not the recommendation report. ESL Ventures insists that it had already presented the recommendation report when Chamberlain Hrdlicka terminated the contract. Under the law firm’s recitation of events, the second early termination fee of “10% of the annual expenditure or $40,000 for each project, whichever is less,” applies. Whereas,

in ESL Ventures’ reckoning, the third early termination fee of “50% of the projected savings for each project” applies and it is owed hundreds of thousands of dollars.

Directed Verdict

The parties tried their competing positions to a jury. After the parties rested, ESL Ventures moved for a directed verdict “on just the issue of liability on failure to comply with the agreement,” specifically, with its “early termination provision.” ESL Ventures argued that it was undisputed that Chamberlain Hrdlicka had terminated the contract early but had not paid ESL Ventures anything under the early termination provision. Thus, ESL Ventures argued, only the issue of damages should be submitted to the jury with respect to the law firm’s breach of the contract. The trial court agreed, granted the directed-verdict motion, and found the firm liable.

Jury Charge

The charge instructed the jury that the trial court had determined “as a matter of law” that the law firm “failed to comply with the agreement.” In conjunction with this instruction, the charge asked the jury to find what amount of money, if any, would fairly and reasonably compensate ESL Ventures for its damages resulting from the law firm’s failure to comply with the agreement. The charge further instructed that “the damages should be measured by the early termination fee” provision of the agreement without specifying which particular subpart of the early termination provision applied. The charge posed no other contract questions.

Closing Arguments

In their closing arguments, the parties essentially hewed to their respective positions. ESL Ventures noted that the trial court had granted a directed verdict on liability and argued that it had presented the recommendation report before the contract was terminated, thus entitling it to “half of the savings” during the contractually specified period. According to ESL Ventures, this amounted to either $757,134 or $829,149, depending on how the law firm’s savings were calculated.

Chamberlain Hrdlicka, in contrast, argued that to be entitled to the damages being sought, ESL Ventures had to show the jury that it had presented the recommendation report and that a recommendation was successfully implemented. “That’s the language in the contract, and that did not happen. There was no presentation here,” let alone a recommendation implemented, according to the firm. Chamberlain Hrdlicka further argued that ESL Ventures was not entitled to any damages, but that any conceivable award would be governed by the subpart of the early termination provision that required payment of a fee of $40,000 at most.

Jury Verdict

The jury found that ESL Ventures was entitled to $700,000 in damages. In order to award this amount of damages under the contract, the jury implicitly found that ESL Ventures had presented its recommendation report and therefore was entitled to an early termination fee of 50% of the corresponding projected savings.

Final Judgment

The trial court entered judgment on the verdict, awarding ESL Ventures $700,000 in damages. The issue of attorney’s fees was reserved for the trial court, which awarded ESL Ventures $83,412.50 as well as contingent appellate fees.

DISCUSSION

Issues on Appeal

At the outset, we must emphasize the limited nature of the issues on appeal.

Of note, Chamberlain Hrdlicka does not challenge the legal or factual sufficiency of the evidence. Nor has the firm raised a challenge to the trial court’s jury charge.

Instead, Chamberlain Hrdlicka raises three other issues. In its first and primary issue, the law firm argues that when the trial court directed a verdict on liability, the court found that ESL Ventures had presented a baseline report but not a recommendation report and that the law firm therefore had breached the contract by failing to pay “an early termination fee equal to 10% of the annual expenditure or $40,000 for each project, whichever is less.” Consequently, Chamberlain Hrdlicka maintains that the jury was not authorized to award more than $40,000 in damages, and the law firm requests that we reverse the trial court’s judgment on this basis.

In addition to reversing the trial court’s judgment, Chamberlain Hrdlicka requests that we render a take-nothing judgment on ESL Ventures’ contract claim, arguing that ESL Ventures failed to request an explicit finding that it had presented

the recommendation report and thereby waived any award of damages under its theory of the case and likewise waived recovery of the lesser amount of $40,000 by not seeking it below. In the alternative, the law firm asks that we remand the case to the trial court for the entry of a judgment in the amount of $40,000 in conformity with the directed verdict (subject to a $20,000 offset the law firm claims it is due).

Free access — add to your briefcase to read the full text and ask questions with AI

Chamberlain, Hrdlicka, White, Williams & Aughtry, P.C. v. ESL Ventures, LLC, (Tex. Ct. App. 2024).

Chamberlain, Hrdlicka, White, Williams & Aughtry, P.C. v. ESL Ventures, LLC (Chamberlain, Hrdlicka, White, Williams & Aughtry, P.C. v. ESL Ventures, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lone Star Cement Corporation v. Fair
467 S.W.2d 402 (Texas Supreme Court, 1971)
Kourosh Hemyari v. Stephens
355 S.W.3d 623 (Texas Supreme Court, 2011)