Chalmers v. Concrete Bob, Inc.

335 P.3d 1288, 265 Or. App. 551, 2014 Ore. App. LEXIS 1296
CourtCourt of Appeals of Oregon
DecidedSeptember 17, 2014
Docket121112429; A153075
StatusPublished

This text of 335 P.3d 1288 (Chalmers v. Concrete Bob, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chalmers v. Concrete Bob, Inc., 335 P.3d 1288, 265 Or. App. 551, 2014 Ore. App. LEXIS 1296 (Or. Ct. App. 2014).

Opinion

TOOKEY, J.

Plaintiff homeowner appeals a general judgment in favor of defendant construction contractor following a bench trial on plaintiffs claim for breach of a contract to lay a concrete foundation for a garage and perform other concrete work. Plaintiff, who contended at trial that defendant’s work was not performed in accordance with the contract or in a workmanlike manner, asserts that the trial court committed legal error in concluding that plaintiff failed to prove specific contractual terms and damages. “We review the interpretation of a contract as a matter of law, but where the trial court’s interpretation depends on factual determinations, we accept those determinations if supported by any competent evidence.” Eden Gate, Inc. v. D&L Excavating & Trucking, Inc., 178 Or App 610, 617, 37 P3d 233 (2002) (internal quotation marks omitted). Because we are unable to determine whether the trial court’s interpretation of the contract depended on legal or factual determinations, we vacate the judgment on plaintiffs claim for breach of contract and remand for further proceedings.

The parties entered into a contract for defendant to perform concrete work on plaintiffs property, including a concrete foundation for a garage, flatwork, and steps to the existing house. Defendant’s bid shows that the work was to be completed for $10,000 and that plaintiff paid defendant $5,000 in advance.

In her complaint, plaintiff averred that defendant’s work was not performed in accordance with the contract or in a workmanlike manner. At trial, plaintiff submitted evidence that the construction plans called for a stem wall foundation to be placed five feet from the fence and that defendant had placed a monolithic (single pour) foundation 10 feet from the fence. In addition, plaintiff submitted an inspection report indicating that defendant’s work failed to pass inspection, violated certain code provisions, and was deficient in several respects. Finally, plaintiffs expert testified that the total cost to demolish, haul, and repour the concrete was $22,500, and plaintiff submitted a bid to do [553]*553that work for $21,000.1 However, plaintiff submitted no evidence regarding the cost to repair any particular deficiency.

Defendant filed an answer with counterclaims for breach of contract and unjust enrichment.2 In its answer, defendant averred that it had performed the work in accordance with the contract and to plaintiffs specifications, specifically stating that the garage foundation “was placed in the location where Plaintiff wanted it and told [defendant’s representative] to place it.” At trial, defendant’s representative testified that plaintiff called him to ask if he could get the bid lower than $12,000, that he had suggested a monolithic pour, and that plaintiff had accepted his bid as a monolithic pour. He did not agree that the foundation was supposed to be five feet from the property line; he testified that the set of plans that he received did not have the measurements on it. Defendant’s representative also refuted certain aspects of the inspection report and testified that he was prevented from fixing some of the problems that were brought to his attention. Defendant submitted no evidence as to damages.

In a written opinion and order, the trial court ruled as follows:

“The Court finds that there was a contract between the Parties to have concrete work performed for Plaintiff by Defendant for a sum of $10,000. That work included concrete work for a garage foundation, flatwork and steps to the house. Beyond those facts, both Plaintiff and Defendant failed to establish any other specific terms of the contract by a preponderance of the evidence. In particular, the parties failed to establish that there was an agreement between the parties regarding a specific location for the foundation [554]*554or an agreement regarding the type of pour and foundation (stem wall and footing or slab on grade single pour). The evidence did establish that Defendant failed to perform certain work in a workmanlike manner, thus breaching the contract. Notably, the steps to the house were of a poor quality, below any acceptable standard. Additionally, Defendant placed a portion of the concrete in a location that prevented the gate that allowed vehicles entry to the intended garage from fully opening.
“While the Court finds that there was a breach of the contract as noted above, Plaintiff failed to prove damages related to that particular work. Plaintiff submitted one exhibit with a proposal dated October 16, 2010 for a complete demolition and reconstruction of the work at a price of $21,000. That estimate was not broken down in any way. Defendant failed to prove damages as well. Defendant failed to offer evidence to support payment of the full amount of the contract in light of the problems with the work, particularly the stairs and area of driveway near the gate. Given the limited evidence offered by Plaintiff and Defendant, any attempt to assign damages would be speculative. The Court finds in favor of Defendant on Plaintiffs claim for breach of contract and in favor of Plaintiff on Defendant’s claim for breach of contract.”

On appeal,3 plaintiff first notes that the trial court, in its opinion and order, did not differentiate between its conclusions of law and findings of fact. Plaintiff then contends that the trial court committed legal error “in failing to find that the facts in the record constituted a contract including the implied warranty to perform the work in a workmanlike manner, to follow the plans and specifications, and to comply with all applicable building codes.” According to plaintiff, the trial court erred by “specifically finding that there was insufficient evidence to show an agreement between the parties regarding a specific location for the foundation”; “in finding only two particular breaches of the construction agreement”; and in determining that plaintiff failed to prove damages.

We agree with plaintiff that the trial court did not set out its conclusions of law and findings of fact in a clear [555]*555manner. However, we do not assume, as plaintiff appears to do, that the trial court committed legal error in construing the contract; rather, we observe that the trial court’s opinion is internally inconsistent. In its letter opinion, the trial court first stated that “Plaintiff and Defendant failed to establish any other specific terms of the contract by a preponderance of the evidence [,]” indicating that there were no proven terms of the contract besides two terms. That statement is inconsistent with the trial court’s later statement “that Defendant failed to perform certain work in a workmanlike manner, thus breaching the contract.” Accordingly, we conclude that we are unable to discern whether the trial court made the challenged determinations as a matter of law or as a matter of fact.

We faced a similar issue in Rennick v. Jackson & Coker, 95 Or App 72, 74, 767 P2d 478 (1989), a case involving a contract “in which plaintiffs allege [d] that defendant breached its contract to locate a physician to work as their employe [e.]” At the close of the evidence, the trial court struck the plaintiffs’ claim for lost profits on the ground that the evidence “would only support a speculation, not a finding of fact.” Id. (internal quotation marks omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rennick v. Jackson & Coker
767 P.2d 478 (Court of Appeals of Oregon, 1989)
Bruer's Contract Cutting v. National Council On Compensation Insurance
841 P.2d 690 (Court of Appeals of Oregon, 1992)
Eden Gate, Inc. v. D&L Excavating & Trucking, Inc.
37 P.3d 233 (Court of Appeals of Oregon, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
335 P.3d 1288, 265 Or. App. 551, 2014 Ore. App. LEXIS 1296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chalmers-v-concrete-bob-inc-orctapp-2014.