Chakeres v. Merchants & Mechanics Federal Savings & Loan Ass'n

192 N.E.2d 323, 117 Ohio App. 351, 24 Ohio Op. 2d 131, 1962 Ohio App. LEXIS 618
CourtOhio Court of Appeals
DecidedJune 8, 1962
Docket585
StatusPublished
Cited by7 cases

This text of 192 N.E.2d 323 (Chakeres v. Merchants & Mechanics Federal Savings & Loan Ass'n) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chakeres v. Merchants & Mechanics Federal Savings & Loan Ass'n, 192 N.E.2d 323, 117 Ohio App. 351, 24 Ohio Op. 2d 131, 1962 Ohio App. LEXIS 618 (Ohio Ct. App. 1962).

Opinion

*352 Kerns, J.

This is an appeal on questions of law from a judgment of the Court of Common Pleas of Clark County rendered upon a jury verdict for the defendants in an action by the plaintiff to recover for damages to his building allegedly caused by the defendants while constructing a party wall upon adjoining property.

Hereinafter, the plaintiff-appellant, Phillip Chakeres, will be referred to as “Chakeres”; the defendant-appellee, Merchants & Mechanics Federal Savings & Loan Association, will be referred to as “Merchants”; and defendant-appellee, Bank Building & Equipment Corporation of America, which specializes in the construction of banks, will be referred to as the ‘ ‘ Contractor. ’ ’

For some time prior to December 23, 1953, Chakeres and Merchants owned adjoining buildings in downtown Springfield which were divided by a common wall partially located on the property of each.

On December 23, 1953, Merchants and Contractor entered into a contract for the demolition of the building on Merchant’s property, and for the construction of a new bank building.

Demolition started on March 29,1954, and excavation for the foundation of the new bank was commenced on May 6,1954. The excavation was completed on May 11, 1954.

Thereafter, on June 28, 1954, Chakeres and Merchants entered into a party wall agreement which provides in part as follows:

“(A) First Party [Merchants] agrees at its own expense to immediately remove the present party wall between said premises, and to build a new party wall, 12 inches in thickness, on the dividing line between said parcels of land, one-half thereof on the land of each of the parties hereto, and also to build a foundation base therefor of not to exceed 4 feet in width, and one-half thereof to be on the land of each of said parties.

“Said wall shall be constructed of concrete for the basement, and shall extend to a height of three floors above the basement, and the wall for said three floors shall consist of brick masonry filled in between reinforced concrete pillars, and said wall shall extend from the front or west end of said premises *353 eastwardly for a distance of 104 feet and 8 inches, and with an extension thereof of 17 feet for the basement only.

“(B) Second Parties [Chakeres] will immediately make snch arrangements in and upon their property, in the way of supports and shoring of their building as may be necessary to support the floors and other portions thereof during the removal of the present party wall, and other parts of the north wall of Second Parties which will require removal in order to permit of the construction of the new wall referred to in item A above, and such shoring and other precautionary measures for the protection of the building on Second Parties’ premises shall be done at the expense of Second Parties.

“(C) Both of the parties shall have the equal rights to the use of said wall, upon its completion, for the support of their own structures and the enjoyment of their respective properties.

6 ( * # #

“(E) Inasmuch as the construction of the new wall by First Party, for the distance and in the manner hereinbefore set forth, will require in addition to the removal of the old party wall, the removal of certain foundation work now installed on the property of Second Parties, and which is located entirely on the property of Second Parties and is used for the support of certain buildings now located thereon, it is agreed that Second Parties shall likewise promptly install the necessary shoring of the buildings on their property, and that First Party will remove said present foundations at its own expense and construct the wall thereon as hereinbefore provided, and further that it will, if Second Parties will agree thereto, while said work is in progress, extend the wall over the eastern most distance of 17 feet thereof hereinbefore referred to, to such height as may be necessary to provide a support for the present structures of Second Parties thereon, and will likewise, if Second Parties consent thereto, pay the cost of roofing that part of Second Parties’ one floor structure, which now extends eastwardly beyond the original 50-foot party wall above referred to, and for the full length of the current extension of the party wall from said point eastwardly as hereinbefore provided, and in such manner as will afford surface water drainage for *354 and from such new roof, and such drainage to run in an easterly direction.

( Í * # # > ?

Pursuant to the agreement, Chakeres had his building shored by a local contractor on July 1, 1954. On July 3, 1954, Contractor, pursuant to a revised contract with Merchants, then proceeded to remove the old wall and construct a new party wall. On July 14, 1954, while the work was being done by Contractor, Chakeres’ building collapsed into the excavation which had been made on May 11,1954. As a result thereof, the present action was commenced on June 21, 1956. Judgment was entered on October 29, 1959, and a motion for new trial overruled on March 6, 1961.

The party wall agreement has been set forth herein at some length because it apparently had a crucial effect upon the jury’s determination as disclosed by answers to the following interrogatories :

Interrogatory No. 2. “Does the jury find that the plaintiff and the defendant, Merchants and Mechanics Federal Savings and Loan Association, entered into a party wall agreement on the 28th day of June, 1954, by which agreement the Merchants and Mechanics Federal Savings and Loan Association was to remove the party wall between the plaintiff and the defendant’s premises and to build a new party wall dividing said parcels of land:”

Answer: (By all 12) “Yes.”

Interrogatory No. 3-A. “If your answer to interrogatory No. 2 was yes, did any acts or omissions by the plaintiff, in shoring his building, cause it to collapse?”

Answer: (By 9) “Yes.”

Interrogatory No. 3-B. “If your answer to interrogatory No. 3-A was yes, state what acts or omissions by the plaintiff caused plaintiff’s building to collapse.”

Answer: (By 9) “Improper shoring.”

Interrogatory No. 21. “Was the defendant, Merchants and Mechanics Federal Savings and Loan Association, guilty of any negligence?”

Answer: (By all 12) “No.”

In the present appeal, nineteen assignments of error have *355 been filed, the first of which is that the trial court erred in granting each defendant four peremptory challenges.

Section 2313.44, Revised Code, provides:

“In addition to the challenges for cause under Sections 2313.42 and 2313.43 of the Revised Code, each party peremptorily may challenge four jurors.”

Under statutes which allow a specific number of challenges to “each party,” the majority view is that those who have identical interests or defenses are to be considered as one party and therefore only collectively entitled to the number of challenges allowed to one party by the statute. 136 A. L. R., 418.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoke v. Miami Valley Hosp.
2020 Ohio 3387 (Ohio Court of Appeals, 2020)
Premier Therapy, L.L.C v. Childs
2016 Ohio 7934 (Ohio Court of Appeals, 2016)
O'Loughlin v. Mercy Hospital Fairfield
2015 Ohio 152 (Ohio Court of Appeals, 2015)
Lambert v. Wilkinson, 2007-A-0032 (6-13-2008)
2008 Ohio 2915 (Ohio Court of Appeals, 2008)
Bernal v. Lindholm
727 N.E.2d 145 (Ohio Court of Appeals, 1999)
LeFort v. Century 21-Maitland Realty Co.
512 N.E.2d 640 (Ohio Supreme Court, 1987)
Nieves v. Kietlinski
258 N.E.2d 454 (Ohio Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
192 N.E.2d 323, 117 Ohio App. 351, 24 Ohio Op. 2d 131, 1962 Ohio App. LEXIS 618, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chakeres-v-merchants-mechanics-federal-savings-loan-assn-ohioctapp-1962.