Chaffin v. Nichols

211 Ill. App. 109, 1918 Ill. App. LEXIS 360
Appellate Court of Illinois·Decided April 5, 1918·Published·Cited by 3 cases

Opinion

Mb. Justice McBride

delivered the opinion of the court.

It appears from the record in this case that on about the 23rd day of August, 1912, the defendants Nichols & Brown entered into an agreement with the City of Flora, Illinois, for the construction and building of a system of sanitary sewers, with an outlet for the same. At the time of the entering into said contract the defendants Nichols & Brown were required to give bond for the performance of the same, for the protection of the city and of those furnishing labor and materials in the construction of said sewer. The t defendants Nichols & Brown, with the Globe Surety Company of Kansas City, Missouri, entered into a bond in which bond the obligees are named as “Are held and firmly bound unto the City of Flora, in Clay county, Illinois, a municipal corporation under the laws of the State of Illinois, and to all persons who may become entitled to liens under the contract hereinafter mentioned.” This bond was conditioned for the performance of the covenants in said agreement entered into for the construction of said sewer, and also that the said Nichols & Brown shall duly and promptly pay and discharge all indebtedness that may be incurred by them in carrying out the said contract, and shall complete the same free from all liens as in said contract provided. And it was further stipulated in said bond, following the conditions aforesaid: “It is expressly understood, stipulated and agreed that the conditions of this bond shall extend to and be held as also made for the use and benefit of all persons who may become entitled to liens under said contract, under the provisions of the laws of the State of Illinois, and that this bond may be sued upon the same as if to them in proper person.” After the execution of said agreement and bond the defendants Nichols & Brown entered upon the performance of their contract, purchased material, employed labor and in time completed the contract and the sewer was accepted by the City of Flora.

It further appears from the record that Nichols & Brown had some difficulty in meeting their obligations while engaged in the construction of said sewer; and at times were unable to meet the payments for labor and materials. That in order to meet the demands Nichols & Brown, by their foreman, issued to persons performing labor and furnishing material due bills, or as they term them “time slips.” The appellant purchased from those furnishing labor and material a great many of these due bills, being about four hundred sixty in number, and each of said due bills was duly assigned by the person to whom it was issued to the appellant, and that by this means he purchased due bills to the amount of ■$-. The appellee gave notice, in writing, to the city officials, in proper manner, of the said claims that were due and owing for work and material furnished upon said sewer, which notice was duly filed with the clerk of the said City of Flora. The said claims were duly acknowledged by Nichols & Brown. Thereafter the City of Flora had a settlement with Nichols & Brown, in which settlement it was found that there was due and owing to Nichols & Brown, upon said contract, a balance of $4,699.37. Other claims besides those of appellee were filed and a payment was made by the City of Flora of 44 per cent out of the balance due to Nichols & Brown. This suit was instituted by appellee upon the bond above described to recover the balance due him upon the liens established as above stated. Judgment was rendered in favor of the appellee and against Nichols & Brown and the appellant for debt in the amount of $17,000 and costs of suit, to be discharged upon the payment of $5,722.11 damages and costs. This appeal is prosecuted by the Globe Surety Company only.

The declaration in this case was in the usual form of declarations upon bonds of this character and the breach assigned was that defendants Nichols & Brown purchased of divers persons, naming them, goods, wares and merchandise, and that others, naming them, performed labor in and about the construction of the sewer above described. That said sewer was completed and accepted by said city and that there was due the said persons furnishing such labor and materials for said sewer the several amounts specified, which the said Nichols & Brown promised to pay to the said parties respectively but failed so to do; that the several persons to whom the respective amounts were due, for a valuable consideration, duly assigned their said claims to the plaintiff and that the plaintiff thereafter gave notice, in writing, to the city officials of his claims aforesaid, and of the failure of Nichols & Brown to pay the same. The defendants entered a motion and obtained a rule for a bill of particulars and then filed the following pleas:

The first plea states that said claims in the declaration mentioned were paid by plaintiff out of money and funds in his possession that belonged to defendants Nichols & Brown, and were advanced by them to the plaintiff for such purpose.

The second plea denies that the plaintiff is the owner of the several claims, or any of them, set forth in the declaration, and that said claims were purchased by plaintiff out of money in his possession belonging to defendants Nichols & Brown while he was acting as their agent.

The third plea was one of set-off, alleging an indebtedness owing to Nichols & Brown by the plaintiff to a greater amount than that claimed by the plaintiff; and set forth that this amount was obtained by plaintiff in notes which were converted to plaintiff’s use and in cash received by him.

The fourth plea denies that the several persons in the declaration mentioned assigned to the plaintiff their right to the said claims, as alleged in the declaration.

Plaintiff traversed the first, second and fourth pleas and filed a replication to the fourth plea, upon which issue was joined.

Free access — add to your briefcase to read the full text and ask questions with AI

Chaffin v. Nichols, 211 Ill. App. 109, 1918 Ill. App. LEXIS 360 (Ill. Ct. App. 1918).

211 Ill. App. 109 (Chaffin v. Nichols) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In re Marriage of Davis
2022 IL App (1st) 210623 (Appellate Court of Illinois, 2022)
People ex rel. Vancil Motor Co. v. Weaver
40 N.E.2d 83 (Appellate Court of Illinois, 1942)
Sperry & Hutchinson Co. v. Siegel, Cooper & Co.
225 Ill. App. 540 (Appellate Court of Illinois, 1922)