CFS Forming Structures Co. v. Flintco, Inc.

393 F. App'x 136
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 16, 2010
Docket13-70006
StatusUnpublished
Cited by1 cases

This text of 393 F. App'x 136 (CFS Forming Structures Co. v. Flintco, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CFS Forming Structures Co. v. Flintco, Inc., 393 F. App'x 136 (5th Cir. 2010).

Opinion

*138 PER CURIAM: *

This contract dispute arises out of a construction contract to build a conference center in San Marcos, Texas. Defendant-Appellant Flintco, Inc. (“Flintco”) is a general contractor who contracted with Plaintiff-Appellee CFS Forming Structures, Inc. (“CFS”) to perform concrete work on the conference center and an adjacent hotel. During the course of construction, Flintco sent CFS a “cure” letter, pursuant to their subcontract, which directed CFS to “commence” installation of concrete work. Ten days later, asserting that installation had not commenced, Flintco terminated its subcontract with CFS and hired another concrete subcontractor. CFS sued Flintco for breach of contract, and Flintco counterclaimed for breach of contract. A jury returned a verdict for CFS and against Flintco. Flintco properly moved, post-verdict, for a judgment as a matter of law (“JMOL”), which the district court denied. Flintco then timely filed a notice of appeal, asserting that the district court abused its discretion in instructing the jury and erred in denying Flintco’s motion for JMOL. We affirm.

I. FACTS AND PROCEEDINGS

The subcontract at issue was signed on February 6, 2007. It provided that CFS’s work was to occur on or before the date specified in the “master project schedule.” This term was not defined in the subcontract, and no date for work completion was specified. The subcontract also contained a “time is of the essence” provision. Crucially, paragraph 9 of the subcontract also gave CFS the right to “cure” any noncompliance under the subcontract for “failure] or refus[al] to proceed with or properly perform Work as directed by FLINTCO____” Specifically, the subcontract stated that “FLINTCO shall notify Subcontractor in writing of Subcontractor’s failure to comply. If FLINTCO determines that Subcontractor has not remedied and cured the event(s) of default within three (3) days of written notification, then FLINTCO may ... terminate this Subcontract....”

Central to the organization and coordination of the overall construction project was the “master project schedule,” which the district court held to be the “critical path method” schedule (the “CPM”). This CPM scheduled the project’s tasks, specifying both commencement and completion dates, and arranged the sequence of each task so that, as necessary, it would occur before, during, or after other tasks. “Noncritical” tasks were those that, if delayed or not timely completed, would not delay the project’s ultimate completion date; “critical” tasks were those whose delayed or untimely completion would delay the project. The CPM was updated and re-issued by Flintco monthly as tasks were completed or not completed; a particular task’s status could shift between noncritical and critical.

The bid documents that predated the subcontract’s execution contained a baseline schedule outlining the subtasks and the project completion date. This was reissued on February 22, 2007, with new interim dates and a project completion date of October 14, 2008. This completion date never changed during the course of the nine interim CPM updates that CFS received between the subcontract’s execution and its termination by Flintco on October 9, 2007. Completion dates for some tasks did change, however, including, for *139 example, CFS’s slab work, which was eventually scheduled to be completed by October 25th. After construction commenced, there were multiple alterations to the CPM schedule issued by Flintco, which pushed back CFS’s schedule several times. Accordingly, CFS could not and did not commence or complete its work either as originally scheduled or by the updated schedule.

Because of delays attendant on the installation of concrete by CFS, Flintco became concerned about meeting the project’s ultimate deadline and being able to proceed with other components of the project, such as structural steel installation. Attributing the delay in concrete floor installation to what Flintco considered to be CFS’s dilatory performance, Flintco’s project manager sent CFS a “cure letter” on September 28, 2007, which directed that CFS “commence” operations on the “conference center slab on grade” task. The cure letter stated that the slab work was scheduled to be completed by October 8. Immediately after sending the letter, the project manager left on vacation. As soon as it received the letter, CFS “commenced” the slab work by laying down vapor barriers, applying pest control, grading the site, and the like. It also scheduled concrete pours for October 10 and 11. Importantly, CFS put on evidence at trial that the cure letter’s October 8 completion date came from an older CPM update and that the CPM date in effect on September 28 was actually October 25.

The project manager returned from vacation on October 8 and was authorized by Flintco to terminate CFS’s subcontract on October 9. He did so by letter, stating that, because “no significant carton form operation has taken place” Flintco deemed CFS to have refused to commence work under the subcontract.

At the jury charge conference before commencement of the jury trial on the parties’ opposing breach of contract claims, the opposing parties’ lawyers disagreed on the appropriate structure of the jury charge. Flintco wanted the court to use a so-called Mustang Pipeline 1 charge (“Mustang Charge”) which would ask disjunctively (1) whether either party was in breach, and (2), if so, which breach occurred first. Flintco also objected to the fact that the court’s proposed jury charge would ask if CFS was in breach at the time of the Flintco cure letter, September 28, rather than at the time of the subcontract’s termination, October 9.

The district court denied these objections and submitted the jury charge without Flintco’s proposed changes. The court also held as a matter of law that the CPM in effect on September 28 was the “master project schedule” for purposes of CFS’s putative breach, ruling that this date was the only reasonable candidate. Flintco argued that the February baseline schedule should be the master schedule, but the court discounted this, reasoning that heavy rain delays in the spring, which in turn had delayed the beginning of construction, as well as the fact that the CPM updates effected multiple changes in interim task completion dates, rendered the February schedule untenable.

The submitted jury charge read:

Question 1: Do you find that CFS was in compliance with the master project schedule on September 28? If “No” proceed to question 2; if yes, proceed to question 3.
Question 2: Do you find that CFS satisfied the notice in the “cure letter” of September 28 by commencing opera *140 tions? If yes, proceed to question 3; if “no” proceed to question 4.
Question 3: What amount of money would compensate CFS for Flinteo’s termination?
Question 4: What amount of money would compensate Flintco for CFS’s breach?

The jury found that CFS was not in breach of the subcontract on September 28 and awarded it damages for Flintco’s unjustified termination.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
393 F. App'x 136, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cfs-forming-structures-co-v-flintco-inc-ca5-2010.