Certainty Construction LLC v. Robert L Davis

CourtMichigan Court of Appeals
DecidedMay 25, 2023
Docket361276
StatusUnpublished

This text of Certainty Construction LLC v. Robert L Davis (Certainty Construction LLC v. Robert L Davis) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Certainty Construction LLC v. Robert L Davis, (Mich. Ct. App. 2023).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

CERTAINTY CONSTRUCTION, LLC, UNPUBLISHED May 25, 2023 Plaintiff-Appellant/Cross-Appellee,

v No. 361276 Washtenaw Circuit Court ROBERT L. DAVIS, LC No. 20-000696-CB

Defendant-Appellee/Cross-Appellant, and

MORTGAGE ELECTRONIC REGISTRATION SYSTEMS, INC.,

Defendant-Appellee/Cross-Appellee, and

LEVEL ONE BANK,

Defendant.

Before: PATEL, P.J., and CAVANAGH and REDFORD, JJ.

PER CURIAM.

In this contract dispute, Certainty Construction, LLC argues that the trial court erred by vacating the arbitrator’s award of attorney’s fees and his determination that the construction lien was valid. Because there was nothing on the face of the arbitrator’s award that evinced an error of law, we find that the trial court exceeded its reviewing authority and erred by vacating the attorney’s fees award. But because Certainty Construction discharged its construction lien, we find any argument on the validity of the construction lien moot. We also reject Robert L. Davis’s argument on cross-appeal that the trial court erred by affirming the arbitrator’s dismissal of the slander of title claim. We affirm in part, reverse in part, and remand for further proceedings consistent with this opinion.

-1- I. BACKGROUND

Davis hired Certainty Construction to build an addition onto and remodel a residential home in Ann Arbor, Michigan. The terms of the project were outlined in the parties’ contract. The six-month project was scheduled to begin on April 1, 2020, at a total cost of $257,415.75. The project was funded by defendant Level One Bank, and secured by a $526,500 future advance mortgage in favor of Level One and Mortgage Electronic Registration Systems, Inc. (MERS). The contract incorporated a proposal that itemized the work to be performed including, in pertinent part: (1) $10,800 for demolition, (2) $31,000 for excavation,1 (3) $2,500 for permits, and (4) $29,000 for management, administration fee, and profit.

In the event of a contract dispute, the parties were obligated to submit the dispute to an agreed-upon single mediator. But if the parties were unable to resolve the dispute through mediation, then the parties were required to submit the dispute to binding arbitration. If one of the parties defaulted, the non-defaulting party was entitled to declare in writing that the contract was in default “and proceed against the defaulting party for the recovery of all damages incurred as a result . . . including a reasonable attorney’s fee.” The non-defaulting party was further authorized to “state his intention to comply with the contract and proceed with specific performance.” If the defaulting party failed to cure within 15 days of the notice, the contract would be terminated. If Davis defaulted, Certainty Construction was entitled to cease work. If Davis failed to cure within 15 days, the contract would be terminated, “and the full contract amount and any additional amount due that is outstanding shall be [sic] continue to be owed.” If Certainty Construction defaulted and failed to cure within 15 days, Davis had the option to terminate and Certainty Construction retained the right to claim payment for all work executed.

Due to COVID-19 restrictions, the project was delayed and did not start until May 6, 2020. On June 2, 2020, Certainty Construction discovered that McTaggart was not licensed to perform construction services, and had Davis execute an agreement relieving Certainty Construction of liability related to the work completed by McTaggart, including “any issues that could potentially arise in future work completed by Certainty Construction as a result of any latent defect in workmanship of McTaggart Masonry.” Thereafter, the owner of Certainty Construction failed to return Davis’s calls and texts from June 3, 2020 through June 8, 2020 and allegedly removed his equipment from the work site.

On June 9, 2020, Davis’s attorney sent a letter to Certainty Construction alleging that it “committed various contract breaches including improper draw requests directly to Level One Bank.” Davis claimed that Certainty Construction appeared to have “abandoned the project altogether” by removing its equipment and not performing any work “for at least a week.” As a result, Davis declared the contract terminated by Certainty Construction’s uncured default. Davis

1 The contract reflected that Davis “selected his own contractor for excavation, foundation and flatwork at a cost of $31,000.” Davis hired McTaggart Masonry for the excavation, foundation, and flatwork. The contract stated that “Certainty Construction will not warranty [sic] [McTaggart’s] work; however, it is assumed that [McTaggart] will be licensed and insured, and will warrant his own work.”

-2- allegedly had another contractor “lined up” and demanded that Certainty Construction “allow the process to play out without interference.”

Certainty Construction refuted Davis’s claims. It maintained that the draw requests followed the protocol and denied that it abandoned the project. Certainty Construction maintained that any delay was due to a dispute regarding Davis’s “insistence on continuing to utilize McTaggart Masonry after it was discovered that the company was not licensed” that prompted the execution of an “indemnity clause.” Certainty Construction proposed that it either (1) complete the full contract, (2) finish the minimal portion of demolition work left and receive payment of $55,490 for the additional funds paid to McTaggart, profit and labor income, remuneration for business defamation and potential loss of future work,2 or (3) cease all work until the matter is resolved in a court of law. For the next six weeks, the parties engaged in a back-and-forth dispute.

On July 8, 2020, Certainty Construction filed a construction lien against the subject property with the Washtenaw County Register of Deeds. The lien asserted that the contract amount was $72,018.62, that total payments were $31,353.12, and the lien claim was for $40,665.50. Two weeks later, Certainty Construction filed this action, asserting claims for breach of contract and foreclosure of construction lien. Davis filed a counterclaim against Certainty Construction, alleging claims for breach of contract, common law and statutory slander of title, and tortious interference with Davis’s contract with Level One Bank. The parties stipulated to stay the proceedings pending arbitration.

During the arbitration proceedings, Davis filed a motion for summary disposition seeking dismissal of Certainty Construction’s lien foreclosure claim because the contract did not include the mandatory language in MCL 570.1114(a) and (b) of the Construction Lien Act (CLA), MCL 570.1101, et seq. Following a hearing, the arbitrator issued a detailed opinion concluding that the contract substantially complied with MCL 570.1114 and thus denied Davis’s motion. But the arbitrator denied the motion without prejudice, affording Davis an opportunity to submit further case law in support of his arguments. Davis moved for reconsideration, citing additional unpublished case law. The arbitrator found the unpublished case law unpersuasive and denied the motion for reconsideration.

Following a 4-day evidentiary hearing, the arbitrator awarded Certainty Construction $85.14 in damages for work performed but unpaid and $16,000 in attorney’s fees incurred due to Davis’s default. Pursuant to MCL 570.1107(1), the arbitrator found that Certainty Construction was entitled to a construction lien in the amount of $85.14 and ordered that the lien be amended to the correct amount within 30 days. The arbitrator denied all of Davis’s counterclaims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Jackson v. Thompson-McCully Co.
608 N.W.2d 531 (Michigan Court of Appeals, 2000)
B & B Investment Group v. Gitler
581 N.W.2d 17 (Michigan Court of Appeals, 1998)
Washington v. Washington
770 N.W.2d 908 (Michigan Court of Appeals, 2009)
Alan Custom Homes, Inc v. Krol
667 N.W.2d 379 (Michigan Court of Appeals, 2003)
Fette v. Peters Construction Co
871 N.W.2d 877 (Michigan Court of Appeals, 2015)
Garrett v. Washington
886 N.W.2d 762 (Michigan Court of Appeals, 2016)
Pirgu v. United Services Automobile Association
884 N.W.2d 257 (Michigan Supreme Court, 2016)
City of Ann Arbor v. American Federation of State Employees Local 369
771 N.W.2d 843 (Michigan Court of Appeals, 2009)
Wells Fargo Bank v. Country Place Condominium Ass'n
848 N.W.2d 425 (Michigan Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Certainty Construction LLC v. Robert L Davis, Counsel Stack Legal Research, https://law.counselstack.com/opinion/certainty-construction-llc-v-robert-l-davis-michctapp-2023.