Certainteed Gypsum Nc, Inc. v. Duke Energy Progress, LLC

2018 NCBC 90
North Carolina Business Court·Decided August 28, 2018·No. 17-CVS-395·Published

Opinion

CertainTeed Gypsum NC, Inc. v. Duke Energy Progress, LLC, 2018 NCBC 90.

STATE OF NORTH CAROLINA IN THE GENERAL COURT OF JUSTICE SUPERIOR COURT DIVISION

PERSON COUNTY 17 CVS 395

CERTAINTEED GYPSUM NC, INC., Plaintiff,

v.

OPINION & FINAL JUDGMENT

DUKE ENERGY PROGRESS, LLC,

Defendant.

1. THIS MATTER came on for trial without a jury before the undersigned commencing on July 9, 2018. The Court now issues its Opinion & Final Judgment.

Brooks, Pierce, McLendon, Humphrey, & Leonard, LLP by Jim W.

Phillips, Jr., Brian C. Fork, and Kimberly M. Marston, for Plaintiff.

Smith, Anderson, Blount, Dorsett, Mitchell & Jernigan, LLP by Donald H. Tucker, Jr. and Isaac A. Linnartz, for Defendant.

Gale, Judge.

I. INTRODUCTION

2. This litigation involves disputes between Plaintiff CertainTeed Gypsum NC, Inc. (“CTG”), a wallboard manufacturer, and Defendant Duke Energy Progress, LLC (“DEP”), a public utility that operates plants to produce electricity, arising from their Second Amended and Restated Supply Agreement (“2012 Agreement”), regarding supply and acceptance of synthetic gypsum, a byproduct of coal-fired electric power plants and a raw material used to manufacture wallboard. The parties define the synthetic gypsum that meets the contractual specifications as “Gypsum Filter Cake.”

3. CTG and DEP first entered into a supply agreement in 2004 (“2004 Agreement”). At that time, DEP was planning to install flue gas desulfurization systems that would produce synthetic gypsum at its coal-fired plants in Roxboro, North Carolina (“Roxboro Plant”) and Mayo, North Carolina (“Mayo Plant”), and CTG was seeking to build its first wallboard-manufacturing plant in the Southeast United States. CTG and DEP executed the Amended and Restated Supply Agreement in 2008 (“2008 Agreement”) following CTG’s decision to delay construction of its plant because of the 2008 economic downturn commonly referred to as the “Great Recession.” The parties executed the 2012 Agreement when CTG was constructing its plant. The Court may refer to the 2004 Agreement, the 2008 Agreement, and the 2012 Agreement collectively as the “Supply Agreements.”

4. A drop in natural gas prices has required DEP to decrease utilization of its coal-fired plants, resulting in its decreased production of synthetic gypsum. This decreased production has resulted in a dispute as to the quantity term of the 2012 Agreement, which has led to other disputes as to the terms and obligations of the 2012 Agreement.

5. The parties’ disputes fall within four principal categories. The parties disagree: (1) as to the Minimum Monthly Quantity (“MMQ”), of Gypsum Filter Cake that DEP is required to supply and CTG is required to accept, including whether Gypsum Filter Cake means only synthetic gypsum produced at DEP’s Roxboro Plant and Mayo Plant; (2) whether DEP has met its contractual obligation to use “commercially reasonable efforts” to maintain a stockpile (“Stockpile”) of 250,000 net dry tons of Gypsum Filter Cake and to furnish a replenishment plan (“Replenishment Plan”) now that the Stockpile has fallen below that volume; (3) whether DEP is now excused from its contractual obligations because its performance is inconsistent with its primary purpose as a regulated public utility (“Primary Purpose”); and (4) if DEP’s performance is not excused, whether CTG will be limited to an exclusive optional remedy of terminating the 2012 Agreement and recovering liquidated damages if DEP discontinues its supply obligation as defined by the 2012 Agreement.

II. PROCEDURAL HISTORY 6. CTG initiated this action on June 30, 2017, by filing a Complaint, which sought only a declaratory judgment of the quantity term in the 2012 Agreement. (See Compl., ECF No. 19.)

7. On August 11, 2017, DEP filed its Notice of Designation As Mandatory Complex Business Case under N.C. Gen. Stat. § 7A-45.4. (ECF No. 6.) On August 11, 2017, this matter was designated as a mandatory complex business case by the Chief Justice. (ECF No. 1.) On August 14, 2017, the matter was assigned to the undersigned. (ECF No. 2.)

8. On August 24, 2017, CTG moved for summary judgment prior to the close of the pleadings, contending that it was entitled to its requested declaration as a matter of law based on the clear contract language of the 2012 Agreement. (ECF No. 11.)

9. On September 21, 2017, the Court heard argument on Plaintiff’s Motion for Summary Judgment. On September 28, 2017, the Court provided an informal oral ruling that it would deny Plaintiff’s Motion for Summary Judgment because it found the relevant contract provisions to be ambiguous, requiring the Court to consider extrinsic evidence to determine the intent of the parties.

10. The parties proceeded with expedited discovery. The Court has noted that the parties have consistently acted in an exemplary and professional manner to move forward to an early trial and have only sought court intervention when their manifest good-faith efforts were able to narrow but not fully resolve disputes as to the scope or timing of discovery. Their conduct throughout the litigation is a clear example of the highest standards of professionalism to which trial lawyers should aspire.

11. On January 29, 2018, with leave of the Court, CTG filed its Amended Complaint to expand its request for declaratory judgment and seek additional relief, including compensatory damages, specific performance, and attorneys’ fees and costs. (ECF No. 53.) CTG now asks the Court to declare that:

a. DEP is required to supply the MMQ of 50,000 Net Dry Tons of Gypsum Filter Cake for the entire term of the 2012 Agreement, subject to minor fluctuations permitted under Section 3.1;

b. DEP’s supply obligation is not limited to Gypsum Filter Cake produced at its Roxboro Plant and Mayo Plant, and, as necessary, DEP may be required to obtain Gypsum Filter Cake from alternative sources at its own expense;

c. DEP is contractually obligated to use commercially reasonable efforts to maintain the Stockpile at 250,000 net dry tons of Gypsum Filter Cake and that the Replenishment Plan DEP prepared based on DEP’s improper interpretation of the MMQ did not meet its contractual obligation; and d. CTG continues to have the election to pursue specific performance rather than termination in the event DEP takes actions that would trigger the optional termination remedy.

(See Am. Compl. ¶¶ 71, 128.)

12. When filing its Amended Complaint on January 29, 2018, CTG also moved for a preliminary injunction. The Court was not required to hear this motion after being advised that the parties had reached an interim agreement, and the Court provided an expedited peremptory trial date.

13. On March 16, 2018, DEP filed its Answer to Plaintiff’s Amended Complaint and Counterclaim, to which it later added a request for attorneys’ fees and costs. (See ECF No. 91.) DEP asks the Court to declare that:

a. DEP’s supply obligation is limited to Gypsum Filter Cake produced at its Roxboro Plant and Mayo Plant even if that production is less than the contractual MMQ, (Countercl. ¶ 25, ECF No. 124);

b. DEP is now excused from any supply obligation because its continued supply of Gypsum Filter Cake is inconsistent with its

Primary Purpose as a regulated public utility, (Countercl. ¶ 25);

and

c. If DEP’s supply obligation is not otherwise excused, the remedy of termination with the recovery of liquidated damages pursuant to Section 6.3 of the 2012 Agreement becomes CTG’s exclusive remedy once DEP takes a contractually-defined action that triggers that section. (Countercl. ¶ 32.)

14. On May 9, 2018, DEP moved for partial judgment on the pleadings as to its request that the Court declare that CTG would be limited to an exclusive remedy once the termination remedy of Section 6.3 of the 2012 Agreement is triggered. After briefing, the Court orally advised the parties that it would reserve its consideration of this issue until trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Certainteed Gypsum Nc, Inc. v. Duke Energy Progress, LLC, 2018 NCBC 90 (N.C. Super. Ct. 2018).

2018 NCBC 90 (Certainteed Gypsum Nc, Inc. v. Duke Energy Progress, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Walton v. City of Raleigh
467 S.E.2d 410 (Supreme Court of North Carolina, 1996)
Lane v. Scarborough
200 S.E.2d 622 (Supreme Court of North Carolina, 1973)
Barrett Kays & Associates, P.A. v. Colonial Building Co.
500 S.E.2d 108 (Court of Appeals of North Carolina, 1998)
Century Communications, Inc. v. Housing Authority of Wilson & Site, Inc.
326 S.E.2d 261 (Supreme Court of North Carolina, 1985)
MCB LTD. v. McGowan
359 S.E.2d 50 (Court of Appeals of North Carolina, 1987)
Northington v. Michelotti
464 S.E.2d 711 (Court of Appeals of North Carolina, 1995)
Joyner v. Adams
361 S.E.2d 902 (Court of Appeals of North Carolina, 1987)
Heater v. Heater
280 S.E.2d 19 (Court of Appeals of North Carolina, 1981)
Davis v. McRee
263 S.E.2d 604 (Supreme Court of North Carolina, 1980)
Crider v. Jones Island Club, Inc.
554 S.E.2d 863 (Court of Appeals of North Carolina, 2001)
Lynn v. Lynn
689 S.E.2d 198 (Court of Appeals of North Carolina, 2010)
Weyerhaeuser Company v. Carolina Power & Light Co.
127 S.E.2d 539 (Supreme Court of North Carolina, 1962)
Howell v. Smith
128 S.E.2d 144 (Supreme Court of North Carolina, 1962)
Cordaro v. Singleton
229 S.E.2d 707 (Court of Appeals of North Carolina, 1976)
Stovall v. Stovall
698 S.E.2d 680 (Court of Appeals of North Carolina, 2010)
Haynie v. Cobb
698 S.E.2d 194 (Court of Appeals of North Carolina, 2010)
In Re the Foreclosure of a Deed of Trust From Hall
708 S.E.2d 174 (Court of Appeals of North Carolina, 2011)
WakeMed v. Surgical Care Affiliates, LLC
778 S.E.2d 308 (Court of Appeals of North Carolina, 2015)
N. & W. Overall Co. v. Holmes
119 S.E. 817 (Supreme Court of North Carolina, 1923)
Prince v. . McRae
84 N.C. 674 (Supreme Court of North Carolina, 1881)