Certainteed Gypsum Nc, Inc. v. Duke Energy Progress, LLC

2018 NCBC 90
CourtNorth Carolina Business Court
DecidedAugust 28, 2018
Docket17-CVS-395
StatusPublished

This text of 2018 NCBC 90 (Certainteed Gypsum Nc, Inc. v. Duke Energy Progress, LLC) is published on Counsel Stack Legal Research, covering North Carolina Business Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Certainteed Gypsum Nc, Inc. v. Duke Energy Progress, LLC, 2018 NCBC 90 (N.C. Super. Ct. 2018).

Opinion

CertainTeed Gypsum NC, Inc. v. Duke Energy Progress, LLC, 2018 NCBC 90.

STATE OF NORTH CAROLINA IN THE GENERAL COURT OF JUSTICE SUPERIOR COURT DIVISION PERSON COUNTY 17 CVS 395

CERTAINTEED GYPSUM NC, INC.,

Plaintiff,

v. OPINION & FINAL JUDGMENT DUKE ENERGY PROGRESS, LLC,

Defendant.

1. THIS MATTER came on for trial without a jury before the undersigned

commencing on July 9, 2018. The Court now issues its Opinion & Final Judgment.

Brooks, Pierce, McLendon, Humphrey, & Leonard, LLP by Jim W. Phillips, Jr., Brian C. Fork, and Kimberly M. Marston, for Plaintiff.

Smith, Anderson, Blount, Dorsett, Mitchell & Jernigan, LLP by Donald H. Tucker, Jr. and Isaac A. Linnartz, for Defendant.

Gale, Judge.

I. INTRODUCTION

2. This litigation involves disputes between Plaintiff CertainTeed Gypsum

NC, Inc. (“CTG”), a wallboard manufacturer, and Defendant Duke Energy Progress,

LLC (“DEP”), a public utility that operates plants to produce electricity, arising from

their Second Amended and Restated Supply Agreement (“2012 Agreement”),

regarding supply and acceptance of synthetic gypsum, a byproduct of coal-fired

electric power plants and a raw material used to manufacture wallboard. The parties

define the synthetic gypsum that meets the contractual specifications as “Gypsum

Filter Cake.” 3. CTG and DEP first entered into a supply agreement in 2004 (“2004

Agreement”). At that time, DEP was planning to install flue gas desulfurization

systems that would produce synthetic gypsum at its coal-fired plants in Roxboro,

North Carolina (“Roxboro Plant”) and Mayo, North Carolina (“Mayo Plant”), and CTG

was seeking to build its first wallboard-manufacturing plant in the Southeast United

States. CTG and DEP executed the Amended and Restated Supply Agreement in

2008 (“2008 Agreement”) following CTG’s decision to delay construction of its plant

because of the 2008 economic downturn commonly referred to as the “Great

Recession.” The parties executed the 2012 Agreement when CTG was constructing

its plant. The Court may refer to the 2004 Agreement, the 2008 Agreement, and the

2012 Agreement collectively as the “Supply Agreements.”

4. A drop in natural gas prices has required DEP to decrease utilization of

its coal-fired plants, resulting in its decreased production of synthetic gypsum. This

decreased production has resulted in a dispute as to the quantity term of the 2012

Agreement, which has led to other disputes as to the terms and obligations of the

2012 Agreement.

5. The parties’ disputes fall within four principal categories. The parties

disagree: (1) as to the Minimum Monthly Quantity (“MMQ”), of Gypsum Filter Cake

that DEP is required to supply and CTG is required to accept, including whether

Gypsum Filter Cake means only synthetic gypsum produced at DEP’s Roxboro Plant

and Mayo Plant; (2) whether DEP has met its contractual obligation to use

“commercially reasonable efforts” to maintain a stockpile (“Stockpile”) of 250,000 net dry tons of Gypsum Filter Cake and to furnish a replenishment plan (“Replenishment

Plan”) now that the Stockpile has fallen below that volume; (3) whether DEP is now

excused from its contractual obligations because its performance is inconsistent with

its primary purpose as a regulated public utility (“Primary Purpose”); and (4) if DEP’s

performance is not excused, whether CTG will be limited to an exclusive optional

remedy of terminating the 2012 Agreement and recovering liquidated damages if

DEP discontinues its supply obligation as defined by the 2012 Agreement.

II. PROCEDURAL HISTORY

6. CTG initiated this action on June 30, 2017, by filing a Complaint, which

sought only a declaratory judgment of the quantity term in the 2012 Agreement. (See

Compl., ECF No. 19.)

7. On August 11, 2017, DEP filed its Notice of Designation As Mandatory

Complex Business Case under N.C. Gen. Stat. § 7A-45.4. (ECF No. 6.) On August

11, 2017, this matter was designated as a mandatory complex business case by the

Chief Justice. (ECF No. 1.) On August 14, 2017, the matter was assigned to the

undersigned. (ECF No. 2.)

8. On August 24, 2017, CTG moved for summary judgment prior to the

close of the pleadings, contending that it was entitled to its requested declaration as

a matter of law based on the clear contract language of the 2012 Agreement. (ECF

No. 11.)

9. On September 21, 2017, the Court heard argument on Plaintiff’s Motion

for Summary Judgment. On September 28, 2017, the Court provided an informal oral ruling that it would deny Plaintiff’s Motion for Summary Judgment because it

found the relevant contract provisions to be ambiguous, requiring the Court to

consider extrinsic evidence to determine the intent of the parties.

10. The parties proceeded with expedited discovery. The Court has noted

that the parties have consistently acted in an exemplary and professional manner to

move forward to an early trial and have only sought court intervention when their

manifest good-faith efforts were able to narrow but not fully resolve disputes as to

the scope or timing of discovery. Their conduct throughout the litigation is a clear

example of the highest standards of professionalism to which trial lawyers should

aspire.

11. On January 29, 2018, with leave of the Court, CTG filed its Amended

Complaint to expand its request for declaratory judgment and seek additional relief,

including compensatory damages, specific performance, and attorneys’ fees and costs.

(ECF No. 53.) CTG now asks the Court to declare that:

a. DEP is required to supply the MMQ of 50,000 Net Dry Tons of

Gypsum Filter Cake for the entire term of the 2012 Agreement,

subject to minor fluctuations permitted under Section 3.1;

b. DEP’s supply obligation is not limited to Gypsum Filter Cake

produced at its Roxboro Plant and Mayo Plant, and, as necessary,

DEP may be required to obtain Gypsum Filter Cake from

alternative sources at its own expense; c. DEP is contractually obligated to use commercially reasonable

efforts to maintain the Stockpile at 250,000 net dry tons of

Gypsum Filter Cake and that the Replenishment Plan DEP

prepared based on DEP’s improper interpretation of the MMQ did

not meet its contractual obligation; and

d. CTG continues to have the election to pursue specific performance

rather than termination in the event DEP takes actions that

would trigger the optional termination remedy.

(See Am. Compl. ¶¶ 71, 128.)

12. When filing its Amended Complaint on January 29, 2018, CTG also

moved for a preliminary injunction. The Court was not required to hear this motion

after being advised that the parties had reached an interim agreement, and the Court

provided an expedited peremptory trial date.

13. On March 16, 2018, DEP filed its Answer to Plaintiff’s Amended

Complaint and Counterclaim, to which it later added a request for attorneys’ fees and

costs. (See ECF No. 91.) DEP asks the Court to declare that:

a. DEP’s supply obligation is limited to Gypsum Filter Cake

produced at its Roxboro Plant and Mayo Plant even if that

production is less than the contractual MMQ, (Countercl. ¶ 25,

ECF No. 124);

b. DEP is now excused from any supply obligation because its

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walton v. City of Raleigh
467 S.E.2d 410 (Supreme Court of North Carolina, 1996)
Lane v. Scarborough
200 S.E.2d 622 (Supreme Court of North Carolina, 1973)
Barrett Kays & Associates, P.A. v. Colonial Building Co.
500 S.E.2d 108 (Court of Appeals of North Carolina, 1998)
Century Communications, Inc. v. Housing Authority of Wilson & Site, Inc.
326 S.E.2d 261 (Supreme Court of North Carolina, 1985)
MCB LTD. v. McGowan
359 S.E.2d 50 (Court of Appeals of North Carolina, 1987)
Northington v. Michelotti
464 S.E.2d 711 (Court of Appeals of North Carolina, 1995)
Joyner v. Adams
361 S.E.2d 902 (Court of Appeals of North Carolina, 1987)
Heater v. Heater
280 S.E.2d 19 (Court of Appeals of North Carolina, 1981)
Davis v. McRee
263 S.E.2d 604 (Supreme Court of North Carolina, 1980)
Crider v. Jones Island Club, Inc.
554 S.E.2d 863 (Court of Appeals of North Carolina, 2001)
Lynn v. Lynn
689 S.E.2d 198 (Court of Appeals of North Carolina, 2010)
Weyerhaeuser Company v. Carolina Power & Light Co.
127 S.E.2d 539 (Supreme Court of North Carolina, 1962)
Howell v. Smith
128 S.E.2d 144 (Supreme Court of North Carolina, 1962)
Cordaro v. Singleton
229 S.E.2d 707 (Court of Appeals of North Carolina, 1976)
Stovall v. Stovall
698 S.E.2d 680 (Court of Appeals of North Carolina, 2010)
Haynie v. Cobb
698 S.E.2d 194 (Court of Appeals of North Carolina, 2010)
In Re the Foreclosure of a Deed of Trust From Hall
708 S.E.2d 174 (Court of Appeals of North Carolina, 2011)
WakeMed v. Surgical Care Affiliates, LLC
778 S.E.2d 308 (Court of Appeals of North Carolina, 2015)
N. & W. Overall Co. v. Holmes
119 S.E. 817 (Supreme Court of North Carolina, 1923)
Prince v. . McRae
84 N.C. 674 (Supreme Court of North Carolina, 1881)

Cite This Page — Counsel Stack

Bluebook (online)
2018 NCBC 90, Counsel Stack Legal Research, https://law.counselstack.com/opinion/certainteed-gypsum-nc-inc-v-duke-energy-progress-llc-ncbizct-2018.