CertainTeed Corp. v. Russell

883 So. 2d 1266, 2003 WL 21488751
CourtCourt of Civil Appeals of Alabama
DecidedJune 27, 2003
Docket2010877
StatusPublished
Cited by7 cases

This text of 883 So. 2d 1266 (CertainTeed Corp. v. Russell) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CertainTeed Corp. v. Russell, 883 So. 2d 1266, 2003 WL 21488751 (Ala. Ct. App. 2003).

Opinion

On September 11, 1998, Carolyn Russell and her husband brought an action alleging breach-of-contract claims, various breach of-implied-warranty claims, negligence claims and a claim under the Alabama Extended Manufacturer's Liability Doctrine ("AEMLD") for damage to their newly constructed house in Muscle Shoals caused by a black sooty residue that began to accumulate shortly after Russell1 moved in to the house. The complaint alleged that the black sooty residue had been caused by the decomposition of defective ductwork insulation manufactured by CertainTeed Corporation, a Pennsylvania corporation, that was distributed throughout the house through the air handler of the house's heating, ventilating, and air-conditioning ("HVAC") system.2 Russell and her husband sued CertainTeed and an additional defendant, Allen's Air Conditioning, Inc. ("Allen's"), the company that had installed the HVAC system that contained the CertainTeed ductwork insulation. CertainTeed answered and asserted various affirmative defenses, including the statute of limitations; Allen's answered and asserted a cross-claim against CertainTeed based upon alleged defects in CertainTeed's products that Allen's had installed.

On June 16, 2001, CertainTeed and Allen's each moved for a summary judgment. *Page 1268 After conducting a hearing, the trial court entered a summary judgment as to the Russells' breach-of-contract and breach of implied-warranty-of-habitability claims against CertainTeed and Allen's, but it denied the summary-judgment motions as to all remaining claims.

On November 29, 2001, the trial court entered an order dismissing, with prejudice, the claims of Russell's husband, pursuant to a stipulation between him and the defendants. The case was then tried to a jury over the course of three days. Under court supervision, the jury inspected Russell's house, in its unrepaired condition.

At the close of the presentation of Russell's evidence, CertainTeed moved for a judgment as a matter of law ("JML"), pursuant to Rule 50, Ala. R. Civ. P., on all of Russell's claims against it. In its motion for a JML, CertainTeed contended that Russell's claim under the AEMLD was time-barred, because, it argued, claims predicated on the AEMLD must be brought within two years of the time the cause of action accrues pursuant to § 6-2-38(l), Ala. Code 1975. Citing Rumford v. Valley PestControl, Inc., 629 So.2d 623 (Ala. 1993), CertainTeed contended that the two-year limitations period had begun to run when Russell discovered the damage to her home. In its motion, CertainTeed noted that Russell had testified that she had discovered the damage in January 1996, and it contended that her AEMLD claim had therefore accrued at that time; however, it noted, the AEMLD claim was not brought until September 1998. CertainTeed further contended in its motion for a JML, that, to the extent that Russell had asserted a claim for negligence, that claim was subsumed under the AEMLD claim; therefore, it argued, she was barred from asserting a claim of negligence as a separate cause of action. As to Russell's claims of breach of an implied warranty of merchantability and breach of an implied warranty of fitness for a particular purpose, CertainTeed contended that those claims were barred because of the lack of privity between Russell, the ultimate consumer of the product, and CertainTeed, the initial manufacturer of the allegedly defective product. CertainTeed cited §§ 7-2-314 and 7-2-315, Ala. Code 1975, as authority for its argument that Russell's breach-of-implied-warranty claims were barred, and it contended that the language contained in those statutes required privity of contract in order for a purchaser to recover damages based on a breach-of-implied-warranty claim. The trial court granted CertainTeed's motion for a JML with respect to Russell's negligence claim, but it denied all other relief sought.

On the evening before the conclusion of the trial, Allen's was dismissed as a party defendant on Russell's motion. At the close of all of the evidence, CertainTeed again moved for a JML. The trial court denied the motion. The jury returned a verdict in favor of Russell, assessing damages of $5,850. The trial court, on December 7, 2001, entered a judgment on the jury verdict.

On January 2, 2002, CertainTeed moved to renew its motion for a JML and sought, in the alternative, a new trial, restating the grounds it had relied upon in its motions for a JML filed at the close of Russell's evidence and that the close of all the evidence; CertainTeed also claimed that the trial court had erroneously allowed the introduction of inadmissible evidence and that the verdict rendered by the jury was contrary to law so as to warrant a new trial. On January 3, 2002, Russell moved for an additur, alleging that insufficient damages were awarded; in the alternative, she sought a new trial based on alleged discrimination in CertainTeed's use of peremptory challenges to potential jurors and *Page 1269 alleged juror misconduct. The parties consented of record, pursuant to Rule 59.1, Ala. R. Civ.P., to allow the trial court until April 23, 2002, to rule on all pending postjudgment motions. On April 18, 2002, the trial court granted Russell's postjudgment motion to the extent it sought a new trial; it denied all other relief requested by the parties. CertainTeed appealed from the order granting a new trial (see § 12-22-10, Ala. Code 1975), contending, among other things, that the trial court erred in denying its motions for a JML.3 Russell cross-appealed, challenging the trial court's denial of her request for an additur.

We first consider the correctness of the trial court's denial of CertainTeed's motions for a JML. On review of a ruling on a motion for a JML, an appellate court applies the same standard as the trial court applied in initially deciding the motion. That standard is "materially indistinguishable from the standard by which we review a summary judgment." Hathcock v. Wood,815 So.2d 502, 506 (Ala. 2001). It must first be determined whether there was substantial evidence, when viewed in the light most favorable to the nonmovant, to warrant submitting the issue to the jury for determination. City of Birmingham v. Sutherland,834 So.2d 755 (Ala. 2002). In Fleetwood Enterprises, Inc. v.Hutcheson, 791 So.2d 920 (Ala. 2000), our Supreme Court stated that "`[s]ubstantial evidence is evidence of such weight and quality that fair-minded persons in the exercise of impartial judgment can reasonably infer the existence of the fact sought to be proved.'" 791 So.2d at 923 (quoting West v. Founders LifeAssurance Co. of Florida, 547 So.2d 870, 871 (Ala. 1989)).

The trial court denied CertainTeed's motion for a JML filed at the close of Russell's evidence, except as to Russell's claim of negligence. At the conclusion of all the evidence, CertainTeed again moved for a JML. Because CertainTeed elected to offer evidence in its own defense after the trial court had denied its motion for a JML at the close of Russell's evidence, we review the trial court's denial of CertainTeed's motion for a JML based on the record at the close of all the evidence. See "Committee Comments on 1973 Adoption" of Rule 50, Ala. R. Civ. P.;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Franklin v. Mitchell, 2091053 (ala.civ.app. 9-2-2011)
87 So. 3d 573 (Court of Civil Appeals of Alabama, 2011)
Dremak v. Iovate Health Sciences Group, Inc.
801 F. Supp. 2d 993 (S.D. California, 2011)
In Re Hydroxycut Marketing & Sales Practices Lit.
801 F. Supp. 2d 993 (S.D. California, 2011)
Mosley v. Wyeth, Inc.
719 F. Supp. 2d 1340 (S.D. Alabama, 2010)
Choice Builders v. Complete Landscape Serv.
955 So. 2d 437 (Court of Civil Appeals of Alabama, 2006)
Gordon v. Acrocrete, Inc.
400 F. Supp. 2d 1310 (S.D. Alabama, 2005)
Dolgencorp, Inc. v. Pounders
912 So. 2d 523 (Court of Civil Appeals of Alabama, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
883 So. 2d 1266, 2003 WL 21488751, Counsel Stack Legal Research, https://law.counselstack.com/opinion/certainteed-corp-v-russell-alacivapp-2003.