Centurion Group v. hrh/atlas Construction, No. Cv 99 0172425 (Oct. 23, 2001)

2001 Conn. Super. Ct. 14527
CourtConnecticut Superior Court
DecidedOctober 23, 2001
DocketNo. CV 99 0172425
StatusUnpublished

This text of 2001 Conn. Super. Ct. 14527 (Centurion Group v. hrh/atlas Construction, No. Cv 99 0172425 (Oct. 23, 2001)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Centurion Group v. hrh/atlas Construction, No. Cv 99 0172425 (Oct. 23, 2001), 2001 Conn. Super. Ct. 14527 (Colo. Ct. App. 2001).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
This case involves a dispute between a subcontractor and a general contractor which was tried by an attorney trial referee. The plaintiff is The Centurion Group, LLC, which had a contract with the defendant, CT Page 14528 HRH/ATLAS Construction, Inc. (Atlas), the general contractor, to perform plumbing, heating, air conditioning and fire protection services in connection with a major renovation to the Central Connecticut Coast YMCA. This building is owned by State Street Bridgeport Limited Partnership (State Street), and is located at 651 State Street in Bridgeport. The other defendants are State Street, and Liberty Mutual Insurance Company (Liberty Mutual). Liberty Mutual furnished a payment bond in the amount of $6,625,000, in which Atlas is the principal and Liberty Mutual is the surety.

The revised complaint against Atlas, which is dated July 16, 1999, is in two counts. In the first count, the plaintiff alleges that it performed services and supplied material in accordance with its written contract with Atlas dated April 16, 1998, but that it withdrew from further work on the project on October 16, 1998, because the defendant had refused to make timely payments for its work and materials as called for in the contract. The plaintiff also alleges that it is owed a balance of $284,492.47 on the contract. In the second count, the plaintiff alleges that it is owed that same amount under the theory of unjust enrichment. The third and fourth counts are directed against the owner, State Street, and the surety, Liberty Mutual, respectively, and claim that these defendants have failed to pay the plaintiff what it is owed.

The defendant Atlas denied the material allegations of the complaint and filed several special defenses. In the first special defense, this defendant alleges that the work performed by the plaintiff was defective and incomplete. In the second special defense, it is claimed that the plaintiff wrongfully abandoned the project. In the third special defense, the defendant alleges that the plaintiff cannot recover under the theory of unjust enrichment because it had an express written contract with the defendant.

The defendant Atlas also filed a counterclaim alleging that the plaintiff breached the contract in a number of ways, including failing to furnish necessary materials and manpower, interfering with the timely performance of work by other subcontractors, abandoning the job, and failing to properly supervise the project, all of which obliged the defendant to expend money to hire other subcontractors to finish the project and to correct the plaintiff's faulty workmanship.

The defendant State Street denied the material allegations of the complaint and filed a special defense claiming it was not liable to the plaintiff to the extent it had paid its general contractor, Atlas. The bonding company, Liberty Mutual, denied that it owed any money to the plaintiff and filed special defenses. In the first such defense, Liberty Mutual claims that the work performed by the plaintiff was done in an CT Page 14529 unworkmanlike and incomplete fashion. In the second special defense, this defendant claims that the plaintiff wrongfully abandoned the project.

The case was referred to Attorney Bernadette Coomaraswamy, an attorney trial referee, in accordance with General Statutes § 52-434(a) and Practice Book § 19-2. The referee submitted a report dated March 20, 2001, finding that: (1) the contract did not provide that the general contractor, Atlas, was obliged to pay the plaintiff only after it received payment from the owner, a "pay when paid" theory, but rather the contract obliged Atlas to pay the plaintiff by the 25th day of the month after receipt of a monthly requisition submitted by the plaintiff; (2) the plaintiff did not wrongfully withdraw from the project on October 16, 1998, but, to the contrary, left because Atlas did not make timely payments to the plaintiff; (3) the work performed by the plaintiff was not defective or unworkmanlike; (4) construction delays involving the vent system and shower units were not attributable to the plaintiff but were occasioned by change orders and involvement by the Connecticut Housing and Finance Authority; (5) the plaintiff did not prove his claim for "lost profits," as it obtained a new job on the day after it left the Bridgeport YMCA project; and (6) the plaintiff is entitled to prejudgment interest as authorized by General Statutes § 37-3a because Atlas and Liberty Mutual had wrongfully withheld payment to the plaintiff when it was due.

The attorney trial referee concluded that: (1) the plaintiff sustained damages because the defendant Atlas had breached the subcontract in question by not paying the plaintiff the amounts due it in a timely fashion; and (2) Atlas did not prove its counterclaim because the plaintiff's work was not defective and the plaintiff did not wrongfully abandon the project. The referee recommended that judgment enter in favor of the plaintiff for $284,390, plus prejudgment interest from October 16, 1998, the date when payment was due the plaintiff.1

The attorney trial referee filed an amended report on April 20, 2001, in response to requests by both the plaintiff and State Street, in which she acknowledged that it was State Street that was holding $72,000 in escrow, not Liberty Mutual, as originally stated. Thus, State Street's liability is limited to $72,000, and the defendants Atlas and Liberty Mutual are responsible for $212,390 of the recommended award to the plaintiff of $284,390.

The attorney trial referee filed an additional report dated May 17, 2001, in response to a request by Atlas for "findings," purportedly as authorized by Practice Book § 19-9. As the referee correctly pointed out, this request for "findings" should be filed before an attorney trial referee's report is rendered, not afterwards. Nevertheless, the referee CT Page 14530 said she would respond to this request by Atlas for findings, and then made the following clarifications: (1) under the terms of the contract between the plaintiff and Atlas, the plaintiff was entitled to payment for both labor and material upon its submitting of requisitions, not just for labor; (2) the defendant Atlas breached its contract with the plaintiff by not making timely payments; and (3) the fact that the plaintiff accepted some late payments from Atlas did not amount to the plaintiff's waiving its right to get paid on time in accordance with the contract.

The defendant Atlas filed objections2 dated April 11, 2000, to the attorney trial referee's report. The defendant claims that the attorney trial referee erred in that: (1) Atlas was not awarded a credit of $40,427.81 for payments made to the plaintiff's subcontractors; (2) the referee misinterpreted the contract and the prior course of dealings regarding when payment was due the plaintiff; (3) the referee failed to find that the plaintiff wrongfully abandoned the project and thus breached its contract with Atlas; (4) the plaintiff waived its right to receive monthly payments because it accepted late payments; (5) the sum of $29,465 was awarded to the plaintiff which represents a "double recovery;"3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Presidential Capital Corp. v. Reale
652 A.2d 489 (Supreme Court of Connecticut, 1994)
Killion v. Davis
776 A.2d 456 (Supreme Court of Connecticut, 2001)
L. F. Pace & Sons, Inc. v. Travelers Indemnity Co.
514 A.2d 766 (Connecticut Appellate Court, 1986)
Wilcox Trucking, Inc. v. Mansour Builders, Inc.
567 A.2d 1250 (Connecticut Appellate Court, 1989)
Beizer v. Goepfert
613 A.2d 1336 (Connecticut Appellate Court, 1992)
Foley v. Huntington Co.
682 A.2d 1026 (Connecticut Appellate Court, 1996)
John M. Glover Agency v. RDB Building, LLC
760 A.2d 980 (Connecticut Appellate Court, 2000)
Aunyx Corp. v. Canon U. S. A., Inc.
507 U.S. 973 (Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
2001 Conn. Super. Ct. 14527, Counsel Stack Legal Research, https://law.counselstack.com/opinion/centurion-group-v-hrhatlas-construction-no-cv-99-0172425-oct-23-connsuperct-2001.