NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-1659-23
CENTURION COMPANIES, INC. and CENTURION CONSTRUCTION, INC.,
Plaintiffs-Respondents,
v.
GALLEN CONTRACTING, INC.,
Defendant-Appellant. _____________________________
Submitted April 30, 2025 – Decided May 27, 2025
Before Judges Mayer and Rose.
On appeal from the Superior Court of New Jersey, Law Division, Bergen County, Docket No. L-3412-23.
Garrity, Graham, Murphy, Garofalo & Flinn, PC, attorneys for appellant (Richard T. Garofalo, on the briefs).
Harold P. Cook, III, attorney for respondents.
PER CURIAM Defendant Gallen Contracting, Inc. (Gallen) appeals from a November 15,
2023 order partially vacating a February 28, 2023 arbitration award in its favor.
Gallen also appeals from a January 12, 2024 order denying its motion for
reconsideration of the November 15 order. We affirm all orders on appeal.
The issue before this court is whether the motion judge properly vacated
a portion of an arbitrator's award entered in favor of Gallen and against two
similarly named corporations, plaintiffs Centurion Companies, Inc.
(Companies) and Centurion Construction, Inc. (Construction) (collectively,
plaintiffs). We recite the relevant facts from the motion record.
Companies is a New Jersey corporation formed on April 22, 2010.
Construction is a New Jersey corporation formed on October 22, 2015.
Construction and Companies share the same office address and same principal.
In April 2016, Construction hired Gallen to perform concrete work for an
automobile dealership in Wayne. Construction and Gallen entered into a written
agreement for the work associated with the project (Wayne Contract). The
Wayne Contract required the parties to submit disputes to mediation, followed
by binding arbitration if mediation failed.
Disputes arose under the Wayne Contract, and Construction fired Gallen.
Gallen then sued Construction. Gallen subsequently amended its complaint,
A-1659-23 2 identifying defendant as "Centurion Construction Inc., a/k/a Centurion
Companies." Gallen's amended complaint failed to assert any specific
allegations against Companies.
Construction moved to compel mediation and binding arbitration, which
the judge granted. Gallen appealed the order compelling mediation and binding
arbitration. Rather than proceed with the appeal, Gallen and Construction
entered into a June 2018 Arbitration Agreement (Arbitration Agreement). The
Arbitration Agreement, entered by the trial court as a consent order, delineated
"[p]laintiff, Gallen Contracting, Inc. and . . . [d]efendants, Centurion
Construction, Inc. and Glen Poppe, [i]ndividually" as the parties participating in
the arbitration. The Arbitration Agreement expressly provided a signature line
for "Centurion Construction, Inc." and the individually named defendant. The
Arbitration Agreement lacked any signature line for "Centurion Companies,
Inc."
The arbitration took place over seven non-consecutive days starting on
June 23, 2021 and ending on March 31, 2022. In an October 25, 2022 letter
opinion, the arbitrator awarded damages to Gallen under the Wayne Contract in
the amount of $408,645 (Award). The arbitrator directed Gallen to prepare a
consent order memorializing the Award.
A-1659-23 3 Three days after issuance of the arbitrator's letter opinion, Construction
objected to the inclusion of "a/k/a Centurian Companies" in any order
memorializing the Award. Construction requested the arbitrator issue a
corrected Award under N.J.S.A. 2A:23B-20, reflecting the entry of the Award
against Construction, not Companies. In relying on this statute, Construction
contended the arbitrator made an evident mistake in his identification of the
parties bound by the Award. Alternatively, Construction asserted the Award
was imperfect in a matter not affecting the merits of the arbitrator's decision.
Gallen objected to any correction or modification of the Award.
After considering oral argument on Construction's request to modify the
Award, the arbitrator sent a revised letter opinion, issuing the Award against
Companies and Construction. The arbitrator found Companies played an active
part in the work associated with the Wayne Contract. Moreover, the arbitrator
concluded he had the discretion to amend Gallen's pleading under the Court
Rules and Rules of Evidence.
On June 27, 2023, plaintiffs filed a verified complaint and order to show
cause to vacate the Award against Companies. Plaintiffs alleged the arbitrator
exceeded his powers, raising the following arguments: Companies was not a
party to the Wayne Contract; Companies did not agree to arbitrate; and
A-1659-23 4 Companies did not sign the Arbitration Agreement. Plaintiffs further asserted
the Award could be modified or corrected without affecting the merits of the
arbitrator's decision. Additionally, plaintiffs claimed the arbitrator made an
evident mistake in entering the Award against both Companies and
Construction.
The judge heard arguments on plaintiffs' order to show cause to vacate the
Award as to Companies. In a November 15, 2023 order and attached rider, the
judge vacated the Award as against Companies. The judge found "[t]he record
and facts presented reveal[ed] that [Companies] was not a party to the
arbitration." He explained "the [a]rbitrator, despite being provided with the
[Arbitration] Agreement and controlling case law, disregarded said submission
and instead proceeded with arbitration" against both Construction and
Companies. Thus, the judge found "the [a]rbitrator exceeded his power and
lacked authority to issue an award against an entity not a party on a claim never
submitted."
The judge, citing N.J. Tpk. Auth. v. Loc. 196, I.F.P.T.E., 190 N.J. 283,
294 (2007), explained controlling law permitted the vacatur of an arbitration
award "if it is contrary to existing law or public policy." In citing this case, the
judge concluded "[t]here [wa]s a clear and indisputable public policy in ensuring
A-1659-23 5 that arbitration agreements are entered into voluntarily and that parties are aware
that they are waiving their 'time-honored right to sue.'" Ibid. The judge
determined "[Gallen] did not properly advise [Companies] with notice of any
claim against them and therefore [Companies] did not have a fair opportunity to
defend." Accordingly, the judge found "confirmation of the arbitration award
in this matter [was] contrary to clearly established public policy."
Gallen moved for reconsideration, which the judge denied in a January 12,
2024 order.
On appeal, Gallen argues the judge erred in vacating the Award against
Companies. Gallen further asserts the judge erred in denying its motion for
reconsideration. We disagree.
I.
We first consider Gallen's argument that the judge erred in vacating the
Award against Companies. We review a judge's decision to confirm or vacate
an arbitration award de novo. Sanjuan v. Sch. Dist. of W. N.Y., 256 N.J. 369,
Free access — add to your briefcase to read the full text and ask questions with AI
NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-1659-23
CENTURION COMPANIES, INC. and CENTURION CONSTRUCTION, INC.,
Plaintiffs-Respondents,
v.
GALLEN CONTRACTING, INC.,
Defendant-Appellant. _____________________________
Submitted April 30, 2025 – Decided May 27, 2025
Before Judges Mayer and Rose.
On appeal from the Superior Court of New Jersey, Law Division, Bergen County, Docket No. L-3412-23.
Garrity, Graham, Murphy, Garofalo & Flinn, PC, attorneys for appellant (Richard T. Garofalo, on the briefs).
Harold P. Cook, III, attorney for respondents.
PER CURIAM Defendant Gallen Contracting, Inc. (Gallen) appeals from a November 15,
2023 order partially vacating a February 28, 2023 arbitration award in its favor.
Gallen also appeals from a January 12, 2024 order denying its motion for
reconsideration of the November 15 order. We affirm all orders on appeal.
The issue before this court is whether the motion judge properly vacated
a portion of an arbitrator's award entered in favor of Gallen and against two
similarly named corporations, plaintiffs Centurion Companies, Inc.
(Companies) and Centurion Construction, Inc. (Construction) (collectively,
plaintiffs). We recite the relevant facts from the motion record.
Companies is a New Jersey corporation formed on April 22, 2010.
Construction is a New Jersey corporation formed on October 22, 2015.
Construction and Companies share the same office address and same principal.
In April 2016, Construction hired Gallen to perform concrete work for an
automobile dealership in Wayne. Construction and Gallen entered into a written
agreement for the work associated with the project (Wayne Contract). The
Wayne Contract required the parties to submit disputes to mediation, followed
by binding arbitration if mediation failed.
Disputes arose under the Wayne Contract, and Construction fired Gallen.
Gallen then sued Construction. Gallen subsequently amended its complaint,
A-1659-23 2 identifying defendant as "Centurion Construction Inc., a/k/a Centurion
Companies." Gallen's amended complaint failed to assert any specific
allegations against Companies.
Construction moved to compel mediation and binding arbitration, which
the judge granted. Gallen appealed the order compelling mediation and binding
arbitration. Rather than proceed with the appeal, Gallen and Construction
entered into a June 2018 Arbitration Agreement (Arbitration Agreement). The
Arbitration Agreement, entered by the trial court as a consent order, delineated
"[p]laintiff, Gallen Contracting, Inc. and . . . [d]efendants, Centurion
Construction, Inc. and Glen Poppe, [i]ndividually" as the parties participating in
the arbitration. The Arbitration Agreement expressly provided a signature line
for "Centurion Construction, Inc." and the individually named defendant. The
Arbitration Agreement lacked any signature line for "Centurion Companies,
Inc."
The arbitration took place over seven non-consecutive days starting on
June 23, 2021 and ending on March 31, 2022. In an October 25, 2022 letter
opinion, the arbitrator awarded damages to Gallen under the Wayne Contract in
the amount of $408,645 (Award). The arbitrator directed Gallen to prepare a
consent order memorializing the Award.
A-1659-23 3 Three days after issuance of the arbitrator's letter opinion, Construction
objected to the inclusion of "a/k/a Centurian Companies" in any order
memorializing the Award. Construction requested the arbitrator issue a
corrected Award under N.J.S.A. 2A:23B-20, reflecting the entry of the Award
against Construction, not Companies. In relying on this statute, Construction
contended the arbitrator made an evident mistake in his identification of the
parties bound by the Award. Alternatively, Construction asserted the Award
was imperfect in a matter not affecting the merits of the arbitrator's decision.
Gallen objected to any correction or modification of the Award.
After considering oral argument on Construction's request to modify the
Award, the arbitrator sent a revised letter opinion, issuing the Award against
Companies and Construction. The arbitrator found Companies played an active
part in the work associated with the Wayne Contract. Moreover, the arbitrator
concluded he had the discretion to amend Gallen's pleading under the Court
Rules and Rules of Evidence.
On June 27, 2023, plaintiffs filed a verified complaint and order to show
cause to vacate the Award against Companies. Plaintiffs alleged the arbitrator
exceeded his powers, raising the following arguments: Companies was not a
party to the Wayne Contract; Companies did not agree to arbitrate; and
A-1659-23 4 Companies did not sign the Arbitration Agreement. Plaintiffs further asserted
the Award could be modified or corrected without affecting the merits of the
arbitrator's decision. Additionally, plaintiffs claimed the arbitrator made an
evident mistake in entering the Award against both Companies and
Construction.
The judge heard arguments on plaintiffs' order to show cause to vacate the
Award as to Companies. In a November 15, 2023 order and attached rider, the
judge vacated the Award as against Companies. The judge found "[t]he record
and facts presented reveal[ed] that [Companies] was not a party to the
arbitration." He explained "the [a]rbitrator, despite being provided with the
[Arbitration] Agreement and controlling case law, disregarded said submission
and instead proceeded with arbitration" against both Construction and
Companies. Thus, the judge found "the [a]rbitrator exceeded his power and
lacked authority to issue an award against an entity not a party on a claim never
submitted."
The judge, citing N.J. Tpk. Auth. v. Loc. 196, I.F.P.T.E., 190 N.J. 283,
294 (2007), explained controlling law permitted the vacatur of an arbitration
award "if it is contrary to existing law or public policy." In citing this case, the
judge concluded "[t]here [wa]s a clear and indisputable public policy in ensuring
A-1659-23 5 that arbitration agreements are entered into voluntarily and that parties are aware
that they are waiving their 'time-honored right to sue.'" Ibid. The judge
determined "[Gallen] did not properly advise [Companies] with notice of any
claim against them and therefore [Companies] did not have a fair opportunity to
defend." Accordingly, the judge found "confirmation of the arbitration award
in this matter [was] contrary to clearly established public policy."
Gallen moved for reconsideration, which the judge denied in a January 12,
2024 order.
On appeal, Gallen argues the judge erred in vacating the Award against
Companies. Gallen further asserts the judge erred in denying its motion for
reconsideration. We disagree.
I.
We first consider Gallen's argument that the judge erred in vacating the
Award against Companies. We review a judge's decision to confirm or vacate
an arbitration award de novo. Sanjuan v. Sch. Dist. of W. N.Y., 256 N.J. 369,
381 (2024). New Jersey law "favors arbitration as a means of settling disputes."
Badiali v. N.J. Mfrs. Ins. Grp., 220 N.J. 544, 556 (2015). An arbitration award
may be "vacated only when it has been shown that a statutory basis justifies that
action." Yarborough v. State Operated Sch. Dist. of Newark, 455 N.J. Super.
A-1659-23 6 136, 139 (App. Div. 2018) (quoting Bound Brook Bd. of Educ. v. Ciripompa,
228 N.J. 4, 11 (2017)).
The New Jersey Arbitration Act (Act), N.J.S.A. 2A:23B-1 to -36, governs
agreements to arbitrate. Under the Act, a court may vacate an arbitration award
if: (1) it "was procured by corruption, fraud, or other undue means"; (2) the
arbitrator was biased, corrupt, or engaged in prejudicial misconduct; (3) the
arbitrator unjustifiably refused to postpone a hearing, refused to consider
material evidence, or conducted the hearing in an inappropriate and substantially
prejudicial manner; (4) the arbitrator exceeded their powers; (5) there was no
agreement to arbitrate; or (6) the arbitration was conducted without proper
notice. N.J.S.A. 2A:23B-23(a).
Additionally, an arbitration award may be modified or corrected if: (1) it
contained "an evident mathematical miscalculation or . . . mistake in the
description of a person, thing, or property"; (2) "the arbitrator made an award
on a claim not submitted to" arbitration and it can "be corrected without
affecting the merits of the decision"; or (3) "the award is imperfect in a matter
of form not affecting the merits of the decision." N.J.S.A. 2A:23B-24(a). "[T]he
standard for modification set forth in N.J.S.A. 2A:23B-24(a)(2)
. . . has two mandatory components: that the award includes 'a claim not
A-1659-23 7 submitted to the arbitrator and the award may be corrected without affecting the
merits of the decision upon the claims submitted.'" Rappaport v. Pasternak, 260
N.J. 230, 254 (2025) (quoting N.J.S.A. 2A:23B-24(a)(2)).
Here, the judge vacated a portion of the Award because: (1) Companies
was not a party to the Arbitration Agreement; (2) the arbitrator exceeded his
power in issuing an award against a nonparty; and (3) the Award violated public
policy.
Arbitration is "a creature of contract." Fawzy v. Fawzy, 199 N.J. 456, 469
(2009) (quoting Kimm v. Blisset, LLC, 388 N.J. Super. 14, 25 (App. Div.
2006)). "[S]tate contract-law principles . . . govern . . . whether a valid
agreement to arbitrate exists." Hojnowski v. Vans Skate Park, 187 N.J. 323, 342
(2006). "[T]he duty to arbitrate, and the scope of arbitration, are dependent
solely upon the parties' agreement." Singer v. Commodities Corp. (U.S.A.), 292
N.J. Super. 391, 402 (App. Div. 1996) (quoting Cohen v. Allstate Ins. Co., 231
N.J. Super. 97, 100-01 (App. Div. 1989)). "In this context, the arbitrator's
powers are limited by the agreement of the parties and an arbitrator may not
exceed the scope of the powers granted to him or her by the parties." Kimm,
388 N.J. Super. at 25. Courts "may not rewrite a contract to broaden the scope
of arbitration." Garfinkel v. Morristown Obstetrics & Gynecology Assocs.,
A-1659-23 8 P.A., 168 N.J. 124, 132 (2001) (quoting Yale Materials Handling Corp. v. White
Storage & Retrieval Sys., Inc., 240 N.J. Super. 370, 374 (App. Div. 1990)).
Here, the Arbitration Agreement is clear and unambiguous. The
Arbitration Agreement bound Gallen and Construction only. Companies was
never a party to the Arbitration Agreement. Even the signature line for the
Arbitration Agreement reflected the document was signed only by Construction.
Nothing in the Arbitration Agreement indicated Companies agreed to mediation
or arbitration of disputes arising under the Wayne Contract because Companies
was not a party to that agreement.
"[A]s a general rule an action on a contract cannot be maintained against
a person who is not a party to it." Comly v. First Camden Nat'l Bank & Tr. Co.,
22 N.J. Misc. 123, 127 (1944). To enforce a contract against a nonparty, there
must be some basis to impose liability against the nonparty, including, for
example, demonstrating that the nonparty is an alter ego of the party to the
contract, the nonparty assumed the contract, the nonparty is a third-party
beneficiary of the contract, or the nonparty is equitably estopped under the
doctrines of waiver and estoppel. Hirsch v. Amper Fin. Servs., LLC, 215 N.J.
174, 188 (2013).
A-1659-23 9 Gallen failed to present any of these theories to the arbitrator in support
of the entry of the Award as against Companies, a nonparty to the Wayne
Contract and the Arbitration Agreement. Nor did Gallen raise the theories
before the judge in opposition to Construction's application to modify or correct
the Award. Gallen raised these issues for the first time on appeal. We decline
to address issues raised for the first time on appeal unless they involve the trial
court's jurisdiction or concern matters of great public interest. Zaman v. Felton,
219 N.J. 199, 226-27 (2014) ("declin[ing] to consider questions or issues not
properly presented to the trial court"). Gallen's newly raised arguments do not
satisfy the jurisdictional or public interest exceptions.
We also reject Gallen's assertion the judge erred in determining the
arbitrator exceeded the scope of his authority. "The scope of an arbitrator's
authority depends on the terms of the contract between the parties." Cnty. Coll.
of Morris Staff Ass'n v. Cnty. Coll. of Morris, 100 N.J. 383, 391 (1985). "[A]n
arbitrator may not disregard the terms of the parties' agreement, nor may he [or
she] rewrite the contract for the parties." Ibid. "[A]n arbitrator exceeds his [or
her] powers when he [or she] ignores the limited authority that the contract
confers." Ibid. "[W]here an arbitration award does not draw its essence from
the . . . agreement, it will not be enforced by the courts." Id. at 392 (quoting
A-1659-23 10 Belardinelli v. Werner Cont'l Inc., 128 N.J. Super. 1, 7 (App. Div. 1974)). "[I]n
the absence of an express agreement by the parties about the scope of the
arbitrator's duties, ordinarily the arbitrator is limited to resolving the dispute in
question." Kimm, 388 N.J. Super. at 25-26.
We agree with the judge's conclusion that the arbitrator exceeded the
scope of his authority by entering the Award against Companies. In his revised
letter opinion, the arbitrator acknowledged Construction and Companies were
"two separate and distinct entities." He also recognized only Gallen and
Construction signed the Wayne Contract. Despite these findings, the arbitrator
expanded the clear and unambiguous terms of the Wayne Contract to
Companies, a nonparty.
We also agree the judge properly vacated the Award because Gallen did
not provide notice that it was asserting claims against Companies as well as
"[N]otice is vital as a matter of fundamental fairness." Block v. Plosia,
390 N.J. Super. 543, 552 (App. Div. 2007). Parties are "entitled to reasonable
notice" of claims "before . . . stepp[ing] into the arbitration ring." Id. at 556.
The Act specifically requires some measure of fair notice. Id. at 552 (quoting
N.J.S.A. 2A:23B-2(a)). An arbitrator may not issue an award "in the absence of
A-1659-23 11 indicia that all parties to the arbitration have reasonable advance notice" of the
claim. Id. at 545.
Here, Gallen never gave Companies notice that it intended to hold
Companies responsible for the claims arising under the Wayne Contract. The
arbitrator's revised letter opinion was the first time the issue of Companies'
liability was specifically addressed. On this record, the arbitrator's entry of the
Award against Companies was "without any prior notice to [Companies] and
without affording it any opportunity to meet that cause of action either legally
or factually." R. Wilson Plumbing & Heating, Inc. v. Wademan, 246 N.J. Super.
615, 617 (App. Div. 1991).
Companies was entitled to notice that Gallen intended to hold it liable for
Construction's conduct under the Wayne Contract. Because Companies lacked
such notice, the judge correctly concluded the arbitrator exceeded his authority
in entering the Award against Companies and properly vacated the award as
against Companies.
II.
We next consider Gallen's argument the judge erred in denying its motion
for reconsideration. Again, we disagree.
A-1659-23 12 We review orders on motions for reconsideration under Rule 4:49-2 for
abuse of discretion. Pitney Bowes Bank, Inc. v. ABC Caging Fulfillment, 440
N.J. Super. 378, 382 (App. Div. 2015). See also D'Atria v. D'Atria, 242 N.J.
Super. 392, 401 (Ch. Div. 1990). Abuse of discretion "arises when a decision
was 'made without a rational explanation, inexplicably departed from
established policies, or rested on an impermissible basis.'" Flagg v. Essex Cnty.
Prosecutor, 171 N.J. 561, 571 (2002). Reconsideration is appropriate if (a) "the
[c]ourt has expressed its decision based upon a palpably incorrect or irrational
basis,'" or (b) "it is obvious that the [c]ourt either did not consider, or failed to
appreciate the significance of probative, competent evidence." Palombi v.
Palombi, 414 N.J. Super. 274, 288 (App. Div. 2010) (quoting D'Atria, 242 N.J.
Super. at 401).
Here, the judge did not rule on "a palpably incorrect or irrational basis" or
fail to consider "the significance of probative, competent evidence." Ibid.
Because we are satisfied the judge properly vacated the Award as to Companies,
the judge did not abuse his discretion in denying Gallen's motion for
reconsideration.
A-1659-23 13 To the extent we have not addressed any of Gallen's remaining arguments,
they are without sufficient merit to warrant discussion in a written opinion. R.
2:11-3(e)(1)(E).
Affirmed.
A-1659-23 14