Central Trust Co. v. Bridges

57 F. 753, 6 C.C.A. 539, 1893 U.S. App. LEXIS 2205
CourtCourt of Appeals for the Sixth Circuit
DecidedAugust 1, 1893
DocketNo. 88
StatusPublished
Cited by32 cases

This text of 57 F. 753 (Central Trust Co. v. Bridges) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Trust Co. v. Bridges, 57 F. 753, 6 C.C.A. 539, 1893 U.S. App. LEXIS 2205 (6th Cir. 1893).

Opinion

TAFT, Circuit Judge,

after stating the facts as above, delivered the opinion of the court:

The Central Trust Company, after answering the bill of McBee & Co., challenged the jurisdiction of the circuit court to entertain [762]*762it, by a motion to dismiss, and the denial of its motion is one of its assignments of error. The jurisdiction was sustained by Judge Key in the court below on the ground that the bill was ancillary to the bill of the Central Trust Company against the Marietta & North Georgia Railway Company. It was said by him that, as the bill of the Central Trust Company prayed the court to take possession of and sell the property in which McBee and other lien claimants asserted an interest, and thus prevented the latter from pursuing their usual remedy against the property in the state courts, they must have the right to appeal to the federal court to save their rights and protect their interests, either by enjoining the trust company from proceeding under its bill, or by adjusting ’ priorities between them and the trust company, even if the lien claimants, as between themselves and the Knoxville Southern Railroad Company, might not have;, had the requisite citizenship to entitle the court originally to take jurisdiction of McBe'e’s bill as an independent bill in equity. We think this was a correct view of the law under the decisions both of the circuit and supreme courts of the United States. See Conwell v. Canal Co., 4 Biss. 195; Minnesota Co. v. St. Paul Co., 2 Wall. 609; Krippendorf v. Hyde, 110 U. S. 276, 4 Sup. Ct. Rep. 27; Pacific R. Co. v. Missouri Pac. Ry. Co., 1 McCrary, 647, 3 Fed. Rep. 772; .

By the consolidation, McBee & Co. and the other lien claimants were put in the position of interveners in the original action brought by the Central Trust Company. Certainly, in that capacity, the circuit court for the eastern district of Tennessee would have jurisdiction to consider their claims. It comes with a bad grace from the Central Trust Company to object to the jurisdiction of the federal court to do equity tó lien claimants' in respect to property which by its own application has been taken into the custody of that court, and out of the reach of lien claimants, by ordinary process in the state courts. It is by no means clear that the bill of McBee & Co. could not be considered by the federal court as an independent bill; but, as the jurisdiction can be sustained on the ground already stated, it is unnecessary to consider the bill in this aspect. . .

The liens of the contractors and material men are asserted under an act of the legislature of Tennessee, -passed March' 29, 1883. The first section of the act provides that when a railroad company contracts with any person to construct or repair any part of its railroad, or to furnish material for such construction or repair, or to superintend the same, the person so contracted with shall have a lien for the amount of the debt thus contracted for and incurred, to continue in force for six months after the performance of the work or the delivery of the material, and until the termination of any suit commenced within the six months for its enforcement. The second section directs in what courts, how,' and in what manner, the suit shall be brought to enforce the lien conferred in the first section. The third section of the act provides that; when “any principal contractor [by which is meant one who contracts directly [763]*763with the railroad companies] shall refuse to pay any subcontractor, material man or other person employed by him to assist in the fulfillment of his contract, such subcontractor or other person may, by giving notice to the railway company of this fact, and the amount and value of the material and labor furnished, bind any amount (not exceeding the amount claimed) then due and owing from the company to the principal contractor, and the amount so claimed shall be a lien in favor of the claimant superior to all others, to continue ninety days from the service of such notice and until the termination of a suit begun within the ninety days to enforce it.” Provision is made for the railway company to relieve itself, if sued by the principal contractor, by paying the amount claimed into court, where the contractor and subcontractor, duly summoned, shall try the issue between them. The claim provided in this section may be enforced by the subcontractor or other person by suit against the principal contractor as debtor and the railway company as garnishee. The fourth section makes provision for the employes of the subcontractors, and permits them, in a prescribed way, to acquire a lien on the debts due from the principal contractor to the subcontractor.

Under this law, the contractor must deal directly with the company to secure a lien for his work or material, or, if a subcontractor, then he can have no lien on the railroad, unless at the time that or after he serves notice of his claim upon the company the company shall owe money to his principal on the contract wrhich his subcontract has helped to perform; and his lien is limited to the amount so due and owing to his principal. In other words, the security of the subcontractor is the balance due the principal contractor from the company when the company receives notice of the subcontractor’s claim, and, after notice is given, the lien of the subcontractor is transferred from the balance due on the contract to the corpus of the railroad, pro tanto; but, if there is no balance due on service of the notice, there can be no lien.

In the consideration of the liens adjudicated below two questions, therefore, arise: First, did the lien claimant deal directly with the company, as principal contractor? Second. If the lien claimants were subcontractors under Eager as principal contractor, was there any sum due Eager, as such principal contractor, from the Knoxville Southern Railroad Company,' after the company was notified by the subcontractors of their intention to claim liens?

1. The theory upon which the master and the learned court below held that all the intervening petitioners dealt directly with the Knoxville Southern Railroad Company as principal contractors was that Eager was an agent of the railroad company in making the contracts. One may be liable for the acts of another as his agent on one of two grounds: first, because by his conduct or statements he has held the other out a& his.agent; or, second, because he has actually conferred authorii v on the other to act as such. The master reported to tb< court below that in no case did Eager, under or in the name &>, the Knoxville Southern Railroad [764]*764Company,- make any contract with any one doing work or furnish-ing material for the road; that,the men who contracted with Eager knew very little of Eager, saw him only occasionally, made no inquiry into his real relation to the company, what interest he had in it,- or how he obtained money to carry on the work. In substance, the master- reported that the intervening petitioners believed that they were dealing with Eager as principal contractor. The proof fully sustains this conclusion. All the estimates introduced in evidence upon which payments were made, bear the name of Eager as principal contractor, and every circumstance in the case rebuts the idea that the intervening petitioners either believed or had reason to believe that they were doing their work or furnishing their material to the company instead of to Eager.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. H. Baird Publishing Co. v. Commissioner
39 T.C. 608 (U.S. Tax Court, 1962)
Mack v. American Security & Trust Co.
191 F.2d 775 (D.C. Circuit, 1951)
W. H. Barber Co. v. Hughes
63 N.E.2d 417 (Indiana Supreme Court, 1945)
Kosters v. Hoover
98 F.2d 595 (D.C. Circuit, 1938)
Aybar v. Vara Smith
51 P.R. 182 (Supreme Court of Puerto Rico, 1937)
Fors v. Farrell
260 N.W. 886 (Michigan Supreme Court, 1935)
In Re Kentucky Wagon Mfg. Co.
3 F. Supp. 958 (W.D. Kentucky, 1932)
Butler v. Ellis
45 F.2d 951 (Fourth Circuit, 1930)
Wyse v. Miller
2 S.W.2d 806 (Missouri Court of Appeals, 1928)
National Oil Transport Co. v. United States
18 F.2d 305 (E.D. Louisiana, 1927)
Pacific Telephone & Telegraph Co. v. Star Pub. Co.
2 F.2d 151 (W.D. Washington, 1924)
Ozan Lumber Co. v. Davis Sewing Mach. Co.
284 F. 161 (D. Delaware, 1922)
Adler v. Seaman
266 F. 828 (Eighth Circuit, 1920)
New York Trust Co. v. Detroit, T. & I. Ry. Co.
251 F. 514 (Sixth Circuit, 1918)
Pittsburgh & Buffalo Co. v. Duncan
232 F. 584 (Sixth Circuit, 1916)
Manhattan Trust Co. v. Chicago Electric Traction Co.
188 F. 1006 (U.S. Circuit Court for the Northern District of Illnois, 1910)
Newton v. Gage
155 F. 598 (U.S. Circuit Court for the District of Southern California, 1907)
Fordyce v. Kansas City & N. Connecting R. Co.
145 F. 566 (U.S. Circuit Court for the District of Western Missouri, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
57 F. 753, 6 C.C.A. 539, 1893 U.S. App. LEXIS 2205, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-trust-co-v-bridges-ca6-1893.