Central Power & Light Co. v. Mauritz

7 S.W.2d 937, 1928 Tex. App. LEXIS 617
CourtCourt of Appeals of Texas
DecidedJune 1, 1928
DocketNo. 9163.
StatusPublished
Cited by1 cases

This text of 7 S.W.2d 937 (Central Power & Light Co. v. Mauritz) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Power & Light Co. v. Mauritz, 7 S.W.2d 937, 1928 Tex. App. LEXIS 617 (Tex. Ct. App. 1928).

Opinion

PLEASANTS, O. J.

This appeal is from a judgment in the court below, rendered in a condemnation proceeding, by which appellees were awarded the sum of $941.96 as full compensation for damages caused them by the construction and maintenance by appellant of a high:power transmission and distributing electric line across appellees’ lands.

The judgment was rendered upon the verdict of a jury on special issues submitted by the trial court.

The lands of apellees over which appellant sought to condemn a right of way for its electric power line consists of two tracts, one containing 168.35 acres and the other 146.4 acres. Both tracts, which are described by metes and bounds in the petition, while not contiguous, are out of the same original survey and are bounded on the southeast by the Ganado Wharton public road in Jackson county.

The land sought to be taken is not described in the petition further than to designate a beginning point for the transmission line and the course and distance of the line.

The cause reached the court below by appeal of appellant from the award of commissioners apointed by the county judge to assess appellees’ damages. No pleadings were filed by appellees other than a waiver of citation and enter of appearance.

The only issues submitted to the jury were the value of the land taken by, appellant and the damage, if any, to the remainder of ap-pellees’ land caused by the construction and maintenance of appellant’s line.

In deciding these issues the jury found, “Value the land at $60 per acre” and “damage on the 314 acres, $3 per acre.” Upon return of this verdict the court rendered a judgment in favor of appellees for $941.96 as damages found by the jury “in full compensation” for the erection and maintenance of appellant’s electric line over the lands of appellees described in the petition for tbe condemnation, and further “adjudged and" decreed that said portions of said above-described lands upon which said transmission line is now constructed are hereby condemned as a perpetual easement in behalf of said Central Power & Light Company for the purposes above mentioned as long as the same is so used by it, 'and that said Central Power & light Company shall have the right of ingress and egress to said tracts of land for the purpose of doing any and' all necessary work for the operation and maintenance of said transmission line.”

Appellant, under appropriate assignments and propositions, very earnestly contends that the judgment should be reversed on the ground that the verdict of the jury is not responsive to the issues submitted and is too indefinite and uncertain to sustain the judgment.

The issues ■ submitted to the jury were these:

“First Special Issue. What was the market value of the land actually appropriated by plaintiff for the erection and maintenance of its transmission line at the time of the erection of such line?
“Special Issue No. 2. Did the erection and proposed maintenance of such transmission line cause any decrease in the market value of the lands of defendants described in the petition other than the land actually taken?
“If you answer the foregoing special issue No. 2 in the negative, you need not answer the next following special issue, but if you answer it in the affirmative then you will also answer the following:
“Special Issue No. 3. What was the amount of the depreciation in the market value of the defendants’ said lands other than the lands actually appropriated by plaintiff by reason of the erection, and proposed maintenance of said transmission line?”

The jury returned the following verdict:

“1. To the first special issue, we, the jury, answer: Value the land at $60' per acre.
“2. To the second special issue we answer: We, the jury, consider the damage on the 314 acres, $3 per. acre.
“3. To the third special issue, we answer: -- J. W. Chapman, Foreman.”

This verdict is not irresponsive to the issues submitted.

The first answer is a direct reply to the first question propounded.

The second answer is responsive to and fully answers the second and third "questions propounded. It is not material that these questions were not answered separately.

The findings of the jury cannot possibly be misunderstood, and can only be construed to mean that the value of appellees’ land taken by appellant was $60 per acre, and that the maintenance of appellant’s line depreciated the value of 314 acres of appellees’ land not actually taken to the extent of $3 per acre. Appellant neither pleaded nor proved the quantity of land required by it for right of way purposes, and that issue was not submitted nor requested to be submitted to the jury. The judgment does not condemn any specified quantity of land, but only those portions of the lands described, in the petition “upon which said transmission line is now constructed.”

Appellant does not complain, and is in no position to complain, of this portion of the judgment, because it is as definite and certain as appellant’s pleadings and evidence as to the quantity of land actually taken.

There was no exception to the petition, and *939 both parties appear to be satisfied with the condemnation portions of the judgment.

In so far as the amount awarded ap-pellees by the judgment is concerned, the failure of the verdict and the evidence to definitely show the quantity of land actually tak-. en by appellant could not possibly have injured appellant. The two tracts of land over which the right of way was condemned contain 314.39 acres. The verdict gave appellees $3 per acrq damages on 314 acres of the land not actually taken. This only leaves 3%oo °f an acre for the land actually taken. Since the land taken was worth, $60 an acre and the remaining land was only damaged to the extent of $3 per acre, it goes without saying that if the quantity taken was more than 3⅛0 of an acre, appellees would have been entitled to a larger compensation, and appellant will not be heard to complain if required by the verdict and judgment to pay $3 an acre for land taken which the jury finds was worth $60 per acre. The discrepancy of 4 cents between the amount of damages found by the jury and • the judgment rendered on the verdict must he regarded as de minimis, and in addition to this, the judgment being for an amount less than that found by the verdict, appellant cannot complain.

Appellant also complains of the rulings of the court upon objections to evidence offered by appellees upon the issue of damages to the two tracts of land caused by the maintenance of appellant’s electric line. We shall not discuss in detail all of the several rulings on ■the admission of evidence complained of by appellant.

F. H. Knipling, a witness for appel-lees, testified:

“The nationality that we are selling mostly to are Bohemians. This line that runs along the southern part of Mauritz land is in front of two residences, which decreases the sale value of the property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fort Worth & Denver Northern Railway Co. v. Johnson
84 S.W.2d 232 (Texas Supreme Court, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
7 S.W.2d 937, 1928 Tex. App. LEXIS 617, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-power-light-co-v-mauritz-texapp-1928.