Central Maine Drywall, Inc v. Pro Con, Inc

CourtSuperior Court of Maine
DecidedOctober 2, 2017
DocketCUMbcd-cv-16-14
StatusUnpublished

This text of Central Maine Drywall, Inc v. Pro Con, Inc (Central Maine Drywall, Inc v. Pro Con, Inc) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Maine Drywall, Inc v. Pro Con, Inc, (Me. Super. Ct. 2017).

Opinion

CUMBERLAND, ss BUSINESS AND CONSUMER COURT BCD-CV-16-14

CENTRAL MAINE DRYWALL, INC. ) ) Plaintiff ) ) v. ) ORDER FOR ENTRY OF ) JUDGMENT ON COUNT ) III AND COUNT V PRO CpN, INC., et al ) ) Defendant. )

BACKGROUND

This matter came on for trial before the Business and Consumer Court on July 21, 2017.

Counts remaining for decision by the Court are Count III (Unjust Enrichment) and Count V

(Mechanic's Lien). Plaintiff is represented by Attorney Jon Languet and Pro Con is represented

by Attorneys Joseph Talbot and John Hobson. Pro Con entered into a contract to provide

design/build services on the construction of the Bangor Residence Inn. Plaintiff Central Maine

Drywall ("CMD") performed work on the project under a written subcontract agreement with

Pro Con. Pro Con hired another subcontractor, Porter Building Systems ("PBS") to do work on

the project as well. CMD later in the project entered into a contract with PBS to complete work

that was originally within the scope of work PBS had agreed to perform in its contract with Pro

Con.

On January 18, 2017, the Court issued an Order granting Partial Summary Judgment in

favor of Pro Con on Count V. CMD had obtained a mechanic's lien against Pro Con in the

amount of $175,352.81 on November 17, 2015, but the Court's Order reduced that amount to

1 $15,909.38 because CMD conceded that it had received payment for all but that amount from

Pro Con. PBS had paid CMD for work CMD performed on the project at issue in this case, and

soon thereafter filed for bankruptcy protection. CMD thus opposed the reduction of the lien

amount to $15,909.38, arguing that $73,265 .63 of the original lien amount was potentially

subject to recovery from the bankruptcy trustee as a "preference" under Section 547 of Title 11

of the United States Code ("Bankruptcy Code"). See 11 U.S.C. § 547(b). The Court in its Order

on Partial Summary Judgment concluded that there was no evidence in the record that CMD had

actually returned any of the $73,265.63 in payments to the bankruptcy trustee. On the same day

that the Court issued its Order, CMD voluntarily agreed to pay the bankruptcy trustee $37,500.00

for a release of claims from the trustee related to the alleged avoidable transfers from PBS to

CMD. CMD then sent the bankruptcy trustee a check in the amount of $37,500.00 and now seeks

to recover that sum from Pro Con, claiming Pro Con has been unjustly enriched in that amount.

Prior to trial, the parties stipulated to judgment on Count I of Plaintiffs Complaint

(Breach of Contract and Violation of Prompt Payment Act) and agreed to dismiss Count IV

(Quantum Meruit) in accordance with a stipulation signed by both parties. (Joint Pretrial

Statement, Stipulated Facts~ 27.) No Count II was brought in the Complaint. In the parties'

Joint Pretrial Statement the parties agreed that at the time PBS filed for bankruptcy it had paid

CMD for all the work CMD had performed with the exception of $15,909.38. At the time of the

bankruptcy filing, CMD requested that Pro Con pay that balance. (Joint Pretrial Statement,

Stipulated Facts ~~ 10-12.) The Court is informed that Pro Con has since paid that amount to

CMD. In the Joint Pretrial Statement the parties further agreed that the "only remaining issue for

the Court to decide are whether Pro Con is liable to CMD for payment of $37,500.00 under

2 Count III (Unjust Enrichment) or Count V (Mechanic's Lien) of CMD's Complaint." (Joint

Pretrial Statement, Factual and Legal Issues in Dispute.)

The parties filed written post-trial arguments, the last of which was received by the Court

on August 18, 2017. The Court has reviewed the evidence admitted at trial, along with the

parties' written arguments, and issues this Order for Entry of Judgment on Counts III and V in

favor of the Defendant.

FINDINGS AND CONCLUSIONS

The parties agree on a number of facts. (See Joint Pretrial Statement, Stipulated Facts.)

Pro Con entered into a written contract with BanRes, LLC to provide design/build services and

construct the Bangor Residence Inn ("The Project"). (Joint Pretrial Statement, Stipulated Facts ,r

1.) Pro Con, the general contractor, hired CMD as a subcontractor and entered into a written

agreement for installation of cold formed metal framing. (Joint Pretrial Statement, Stipulated

Facts ,r 3.) The original contract between the parties was a fixed price contract for $84,505.00,

but the amounts paid to CMD were subject to additions and deductions for changes as agreed in

writing, subject to a retainage of 10% of the amount requisitioned by CMD. (Joint Pretrial

Statement Stipulated Facts ,r,r 4-5.) The scope of work performed by CMD was expanded

throughout the Project and CMD performed other work for Pro Con on both a fixed price and

time and materials basis. (Joint Pretrial Statement, Stipulated Facts ,r 15.) Invoices for the

additional work were sent by CMD to Pro Con for the additional work. (Joint Pretrial Statement,

Stipulated Facts ,r 16.)

The parties also agree that Pro Con hired PBS as a subcontractor on the Project for

construction and installation of wood walls, floor and roof trusses, wood stairs, sheathings, air

barriers, anchor tie down systems, and installation of windows. (Joint Pretrial Statement,

3 Stipulated Facts 1 2.) The written agreement between Pro Con and PBS was a fixed price

contract for $960,212.00. (Trial Exh. G.) PBS was paid by Pro Con when PBS submitted

monthly payment applications to Pro Con which included representations by PBS regarding the

percentage of completion of the PBS Scope of Work. (Trial Exh. S.)

Pro Con paid in full the first four payment applications submitted by PBS based upon the

completion percentages represented in the applications. (Trial Exhibits S, 0.) The fourth

application was for work performed up to December 22, 2014. According to Daniel Messier,

Senior Vice President of Pro Con, at the end of December PBS had only completed 60-65% of

their Scope of Work even though they represented that the work was 82.66% completed in the

fourth application. Mr. Messier testified that he believed PBS had "front loaded" its payment

applications to Pro Con which would mean that PBS was paid by Pro Con for work that it had

not actually completed.

On December 8, 2014, CMD contracted with PBS to help it complete its scope of work

obligations under PBS's contract with Pro Con. According to Kaleb Violette, Project Manager

for CMD, in December of 2014 Ken Juthe, Pro Con's Project Manager, contacted Mr. Violette to

ask if CMD could provide carpenters to Pro Con on an hourly basis to assist PBS in fulfilling its

contract. When PBS became aware that Pro Con intended to use CMD's workers to perform on­

site work and back-charge PBS for the cost, Mr. Violette testified that PBS contacted him to ask

that CMD provide carpenters directly to PBS. PBS agreed to pay CMD $37.50 per man-hour and

CMD was supposed to be paid by PBS within two weeks of the date of billing. (Joint Pretrial

Statement, Stipulated Facts 16.) CMD provided carpenters to PBS from December 9, 2014 until

February 26, 2015 when PBS left the Project. Article X 14 of the contract between Pro Con and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lynch v. Ouellette
670 A.2d 948 (Supreme Judicial Court of Maine, 1996)
Dyer v. Department of Transportation
2008 ME 106 (Supreme Judicial Court of Maine, 2008)
A.F.A.B., Inc. v. Town of Old Orchard Beach
610 A.2d 747 (Supreme Judicial Court of Maine, 1992)
In Re Wage Payment Litigation
2000 ME 162 (Supreme Judicial Court of Maine, 2000)
Howard & Bowie, P.A. v. Collins
2000 ME 148 (Supreme Judicial Court of Maine, 2000)
PLATZ ASSOCIATES v. Finley
2009 ME 55 (Supreme Judicial Court of Maine, 2009)
June Roberts Agency, Inc. v. Venture Properties, Inc.
676 A.2d 46 (Supreme Judicial Court of Maine, 1996)
A.F.A.B., Inc. v. Town of Old Orchard Beach
639 A.2d 103 (Supreme Judicial Court of Maine, 1994)
Van Arsdall v. State
486 A.2d 1 (Supreme Court of Delaware, 1984)
Styer v. Hugo
619 A.2d 347 (Superior Court of Pennsylvania, 1993)
Watt v. UniFirst Corp.
2009 ME 47 (Supreme Judicial Court of Maine, 2009)
Federal Insurance v. Maine Yankee Atomic Power Co.
183 F. Supp. 2d 76 (D. Maine, 2001)
Nadeau v. Pitman
1999 ME 104 (Supreme Judicial Court of Maine, 1999)
Levine v. R.B.K. Caly Corp.
2001 ME 77 (Supreme Judicial Court of Maine, 2001)
Mark Chartier v. Farm Family Life Insurance Co.
2015 ME 29 (Supreme Judicial Court of Maine, 2015)
Oceanic Inn, Inc. v. Sloan's Cove, LLC
2016 ME 34 (Supreme Judicial Court of Maine, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Central Maine Drywall, Inc v. Pro Con, Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-maine-drywall-inc-v-pro-con-inc-mesuperct-2017.