Central Hudson Gas & Electric Corp. v. Public Service Commission

108 A.D.2d 266, 489 N.Y.S.2d 124, 1985 N.Y. App. Div. LEXIS 48384
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 9, 1985
StatusPublished
Cited by6 cases

This text of 108 A.D.2d 266 (Central Hudson Gas & Electric Corp. v. Public Service Commission) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Hudson Gas & Electric Corp. v. Public Service Commission, 108 A.D.2d 266, 489 N.Y.S.2d 124, 1985 N.Y. App. Div. LEXIS 48384 (N.Y. Ct. App. 1985).

Opinion

OPINION OF THE COURT

Levine, J.

The instant case culminates a more than decade long dispute between the cable television (hereinafter CATV) industry and State public utilities over regulation of fees charged CATV for use of utility power poles to run CATV cables. A similar controversy occurred at the national level, resulting in litigation before the Federal Communications Commission (FCC) (see, Matter of CATV Pole Attachments Regulation, 77 FCC2d 187), the Federal courts (Monongahela Power Co. v Federal Communications Commn., 655 F2d 1254) and in Federal legislation amending the Federal Communications Act (Pub L 95-234; 47 USC § 224). In 1973, the State Cable Television Association and the State Commission on Cable Television petitioned the Public Service Commission (PSC) to complain of claimed excessive charges for attaching cable lines to utility poles. The utilities’ legal challenge to PSC regulatory authority was rejected by this court (Matter of General Tel. Co. v Public Serv. Commn., 63 AD2d 93). Meanwhile, the Legislature added Public Service Law § 119-a (L 1978, ch 703), enacted within a matter of days following the latter decision. That amendment conferred jurisdiction on the PSC to establish just and reasonable rates for attachments to utility poles. The section also, however, incorporated a minimum rate recovery to the utilities of not less than their additional costs of providing a pole attachment and a maximum rate recovery of the utilities’ “actual operating expenses and return on capital * * * attributed to that portion of [268]*268the pole * * * used” (Public Service Law § 119-a). Regarding the foregoing rate ceiling, section 119-a expressed the CATV share of a utility’s recovery of pole expenses and return on investment in terms of the CATV’s percentage of actual use of the “total usable space” on the pole (Public Service Law § 119-a). Put another way, CATV may not be charged more than a percentage of the utility’s pole operating costs and return on pole investment equivalent to the percentage of total usable space on the pole occupied by CATV. The statute further defined “usable space” as “the space on a utility pole above the minimum grade level which can be used for the attachment of wires and cables” (Public Service Law § 119-a).

After remand of the original petition by this court, the PSC elected to hold hearings before an Administrative Law Judge (ALJ). After some 23 days of hearings over more than a two-year period, during which the disputants introduced evidence covering virtually every element of the statutory minimum and maximum rate equations and as to where the rates should fall within those outer limits, the ALJ issued a recommended decision. Of pertinence to the instant proceedings, the ALJ recommended that, for purposes of calculating the total usable pole space (the percentage of which occupied by CATV would determine the maximum rate chargeable by utilities for such use), 40 inches of so-called “neutral space” should be excluded. This favored the utilities’ position, since a smaller total usable space would result in a larger percentage thereof used by CATV. The neutral space was derived from requirements of the National Electric Safety Code (NESC) which provided that there be a 40-inch gap on the pole between horizontal electrical conductors and telephone or CATV conductors. The NESC does not, however, prohibit all use of the neutral space on poles and in a significant number of instances, the neutral space is used for the attachment of streetlights, transformers and the like, to which wires running up the pole are connected. The ALJ, however, accepted the utilities’ argument that the statutory phrase “usable space” refers only to the portion of the pole available for the attachment of horizontal cables and wires and, on this basis, excluded the neutral space from total usable space in the statutory maximum charge ratio.

On exceptions to the ALJ’s recommendations made to the full PSC, the ALJ’s exclusion of neutral space was rejected. Proceeding No. 1 for a declaratory judgment and proceeding No. 2 for a judgment under CPLR article 78 were then brought, each for the purpose of challenging the PSC’s determination to include the neutral space within the total usable space in the statutory rate [269]*269equation, essentially on the same principal ground that it conflicted with the statutory definition of usable space. Special Term converted the declaratory judgment action to a CPLR article 78 proceeding and transferred both matters to this court for determination.

At the outset, we note our agreement with the objections to the transfer of these proceedings to this court. Since a hearing by the PSC regarding the original petition on excessive charges for CATV use of utility poles was not mandated by law, Special Term lacked authority to transfer review thereof to the Appellate Division (see, CPLR 7804 [g]; 7803 [4]; Matter of Incorporated Vil. of Val. Stream v State of New York Public Serv. Commn., 107 AD2d 856). There may also be validity to the objection to the conversion of the declaratory judgment action to a CPLR article 78 proceeding (see, Matter of Morgenthau v Erlbaum, 59 NY2d 143,150, cert denied __ US __ , 104 S Ct 486). However, petitioners do not seek remittal but rather urge that we retain jurisdiction, and we do so in the interest of judicial economy (Matter of National Fuel Gas Distrib. Corp. v Public Serv. Commn., 86 AD2d 901, 902-903, lv denied 57 NY2d 601).

Turning then to the merits, we have concluded that the PSC’s determination should be confirmed. Contrary to petitioners’ arguments, the question of whether the definition of usable space in section 119-a requires the inclusion or exclusion of the neutral space and whether “wires and cables” in that definition refer only to horizontal lines is not one of pure statutory reading and analysis. Indeed, the very arguments advanced by petitioners before us, the PSC and the ALJ demonstrate that fair consideration of these issues cannot be had without reference to extensive information contained in the record on various technical matters and concerning customary industry practices with respect to the use of utility poles, including, inter alia, the purpose and proper application of the neutral space requirements of the NESC, the degree to which utilities are permitted to and actually use the neutral space for revenue producing attachments, the extent of practical restrictions on use of portions of utility poles apart from NESC requirements, and whether CATV should be charged with a greater portion of the pole than the 2 or 3 inches of the actual width of the cable attached thereto. Each of the disputants introduced voluminous evidence at the hearings on these and other issues, including expert testimony and field surveys. Therefore, the instant case falls well within the class of cases “[w]here the interpretation of a statute or its application involves knowledge and understanding of underlying operational practices or entails an evaluation [270]*270of factual data and inferences to be drawn therefrom” in which “courts regularly defer to the governmental agency charged with the responsibility for administration of the statute” (Kurcsics v Merchants Mut. Ins. Co., 49 NY2d 451, 459).

The PSC’s interpretation of the statute to require inclusion of the neutral space within total usable space cannot be said to lack rationality. By statutory definition, usable space includes the space available for the attachment of “wires” (Public Service Law § 119-a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Perez
18 Misc. 3d 582 (New York Supreme Court, 2007)
AT&T Communications of New York, Inc. v. Public Service Commission
231 A.D.2d 155 (Appellate Division of the Supreme Court of New York, 1997)
Rochester Gas & Electric Corp v. Public Service Commission
135 A.D.2d 4 (Appellate Division of the Supreme Court of New York, 1987)
Oneida Indian Nation v. Burr
132 A.D.2d 402 (Appellate Division of the Supreme Court of New York, 1987)
New York State Cable Television Ass'n v. New York State Public Service Commission
125 A.D.2d 3 (Appellate Division of the Supreme Court of New York, 1987)
Occidental Chemical Corp. v. Public Service Commission
114 A.D.2d 149 (Appellate Division of the Supreme Court of New York, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
108 A.D.2d 266, 489 N.Y.S.2d 124, 1985 N.Y. App. Div. LEXIS 48384, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-hudson-gas-electric-corp-v-public-service-commission-nyappdiv-1985.