Central Ceilings, Inc. v. National Amusements, Inc.

873 N.E.2d 754, 70 Mass. App. Ct. 172, 2007 Mass. App. LEXIS 999
CourtMassachusetts Appeals Court
DecidedSeptember 18, 2007
DocketNo. 06-P-291
StatusPublished
Cited by6 cases

This text of 873 N.E.2d 754 (Central Ceilings, Inc. v. National Amusements, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Ceilings, Inc. v. National Amusements, Inc., 873 N.E.2d 754, 70 Mass. App. Ct. 172, 2007 Mass. App. LEXIS 999 (Mass. Ct. App. 2007).

Opinion

Perretta, J.

Central Ceilings, Inc. (Central), brought the present action against National Amusements, Inc. (National), seeking damages sustained as a result of a breach of an oral agreement it had with National. In answers to special questions, see Mass. [173]*173R.Civ.P. 49(a), 365 Mass. 813 (1974), a jury found that National was in breach of an oral promise to pay Central for its work. On appeal, National argues that the judge erred in denying its motions for a directed verdict, for judgment notwithstanding the verdict, and for a new trial. The principal issue before us on National’s appeal is whether enforcement of the oral agreement is barred by the Statute of Frauds, G. L. c. 259, § 1, Second (the Statute). We agree with the judge’s conclusion that the “main purpose” exception to the Statute was applicable and affirm the judgment.1

1. The facts. There was evidence to show the following facts. National is the owner of a cinema theater complex in Lawrence. This dispute arose out of the construction of that complex (the Project). On or about March 10, 2000, National entered into a contract with Old Colony Construction Corporation (Old Colony), the general contractor, with an anticipated completion date of June 28, 2000. Central submitted a bid to Old Colony that Old Colony accepted on March 17, 2000, making Central a “core” subcontractor; specifically, Central was to do the drywall, acoustical, carpentry, and hardware installation work at the Project.

Meeting the anticipated completion date of June 28, 2000, proved difficult if not improbable due, in part, to delays caused by problems related to groundwater at the construction site. It was discovered in late April of 2000 that the groundwater table at the construction site was higher than originally thought. Consequently, National was required to redesign structural and other aspects of the construction. Revised architectural plans were in place by mid-June, and by early July, work on the Project was poised to move forward. National then extended the completion date for the Project to September 3, 2000.2

As matters stood as of the end of June, the completion date of September 3, 2000, was highly aggressive, if not unrealistic. [174]*174National, however, wanted to have the theater complex open for the Labor Day weekend because summer holiday weekends, with their large audiences and blockbuster releases, represented substantial revenue opportunities. In other words, National tried to schedule the opening of its new theater complex to coincide with a holiday or the release of blockbuster movies so as to open with a “splash.” Put otherwise, there was evidence to show that National had an interest in having the Project completed and its theater complex opened before a competitor’s theater in the same area opened.

There was another problem with the Project. In the spring of 2000, Old Colony was experiencing severe cash flow problems. These difficulties were due in large measure to its failure timely to bill National for work performed on the Project as well as on earlier projects. Old Colony owed substantial sums to its subcontractors, including Central, for work done on past projects. In June, 2000, Old Colony owed Central over one million dollars for its work on prior projects. Old Colony was not paying invoices in a timely fashion, and some of its checks were returned as uncollected. As a consequence, when the groundwater problem was starting to be resolved and work could have been continued, many subcontractors were refusing to return to the Project.

While the revised architectural redesign plans were complete, they called for a change in the scope of the work to be performed by Central. As things stood at the end of June, Central estimated that it would need to increase its manpower substantially on the Project in order to meet a September completion date.

It is against the backdrop of these problems that Joseph McPherson, a Central manager, informed Old Colony’s project manager, Patrick Hogan, that Central would not go forward with its work unless he obtained “assurances” of payment from National. He demanded that Hogan arrange for him to meet with National’s then vice-president of construction, Peter Brady.

Just prior to the July 4, 2000, holiday, Brady, Hogan, McPherson and others met. There was discussion of the fact that Old Colony owed Central substantial sums of money and that the revised scope of the work would require additional funding if Central were to accomplish its work by Labor Day. McPherson indicated that Central would not continue its work on [175]*175the Project without a payment commitment from National. He told Brady, “[Yjou’ve got to guarantee me the payments. You’ve got to guarantee me that I will get funded for this project.”3 Brady said that “he would guarantee [McPherson].”4 However, his promise to McPherson was not made conditional upon Old Colony’s prior default in paying for the work. It was ultimately agreed by Brady and McPherson that Central would continue to work under the direction of Old Colony and that National would pay half the amount due Central on the Monday after Labor Day and the balance ten days thereafter. Central set to work the day after this meeting and achieved substantial completion of its work by August 25, 2000.5

In November of 2000, National issued a joint check to Old Colony and Central in the amount $679,949.75, which Old Colony signed over to Central in exchange for Central’s execution of a lien waiver in favor of Old Colony. The amount of the check was a partial payment of what Central claimed it was owed, but National refused to pay Central its claimed unpaid balance of $593,237.25.6 In the course of reconciling its account for the Project, National discovered that Brady had collaborated with the president of Old Colony in a scheme to defraud National on a number of construction projects, including the project in issue, by inflating Old Colony’s contract price above what was necessary to accomplish the work and then splitting the overage.

In March, 2001, Central brought this action alleging breach of contract against Old Colony and seeking to establish a lien [176]*176on National’s property pursuant to G. L. c. 254. After a default judgment was entered against Old Colony in the amount of $593,237.25, plus interest and costs,7 Central amended its complaint to add claims against National for breach of its agreement to pay Central for its work at the Project, quantum meruit, and violations of G. L. c. 93A. The quantum meruit and G. L. c. 93A claims, as well as Central’s request for a lien on National’s property, were dismissed at various stages of the litigation, leaving for trial its claim against National for breach of contract.

2. The special questions and posttrial motions. In response to special questions, the jury found that (1) Brady did promise to pay Central the debt of Old Colony for Central’s work on the Project; (2) Brady had thé actual or apparent authority to make such a promise on behalf of National; (3) National’s promise was supported by valid consideration; (4) the main purpose of the agreement between National and Central was to bestow a benefit upon National to which it was not already entitled; (5) National was in breach of its promise; and (6) Central was entitled to receive $593,237.25 from National as a result of that breach.8

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peter M Tufts
D. Massachusetts, 2022
Beauregard v. Meldon
D. Massachusetts, 2019
A.T. Equipment, Inc. v. Cleckley
29 Mass. L. Rptr. 91 (Massachusetts Superior Court, 2011)
LBM Financial, LLC v. Individual Lot, LLC
26 Mass. L. Rptr. 492 (Massachusetts Superior Court, 2010)
Berkshire-Westwood Graphics Group, Inc. v. Davidson
2007 Mass. App. Div. 178 (Mass. Dist. Ct., App. Div., 2007)
Egan v. Herb Chambers I-93, Inc.
2007 Mass. App. Div. 181 (Mass. Dist. Ct., App. Div., 2007)

Cite This Page — Counsel Stack

Bluebook (online)
873 N.E.2d 754, 70 Mass. App. Ct. 172, 2007 Mass. App. LEXIS 999, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-ceilings-inc-v-national-amusements-inc-massappct-2007.