Centerpoint Energy Gas Transmission Co. v. Green

413 S.W.3d 867, 2012 Ark. App. 326, 2012 WL 1608576, 2012 Ark. App. LEXIS 445
CourtCourt of Appeals of Arkansas
DecidedMay 9, 2012
DocketNo. CA 11-1197
StatusPublished
Cited by5 cases

This text of 413 S.W.3d 867 (Centerpoint Energy Gas Transmission Co. v. Green) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Centerpoint Energy Gas Transmission Co. v. Green, 413 S.W.3d 867, 2012 Ark. App. 326, 2012 WL 1608576, 2012 Ark. App. LEXIS 445 (Ark. Ct. App. 2012).

Opinion

JOHN MAUZY PITTMAN, Judge.

| fin this eminent-domain case, the circuit court awarded appellee James Green $63,100 as just compensation for a taking by appellant CenterPoint Energy Gas Transmission Company. CenterPoint seeks reversal, arguing that the circuit court failed to enter specific findings of fact and conclusions of law, abused its discretion in admitting evidence, and erred in its just-compensation finding. We affirm.

I. Facts

Green owns 2.358 acres on Lake Catherine in Garland County. A 7,700-square-foot building, which formerly housed a restaurant, is located on the western portion of the tract, near the water. The remainder of the property is vacant, with minimal landscaping. Green purchased the property in 2009 for $235,513.31. At that time, a gas-line easement measuring twenty feet wide ran diagonally, southeast to northwest, across much of the eastern and northeastern sections of the property opposite the lake.

|20n February 11, 2010, CenterPoint filed this condemnation action in Garland County Circuit Court to obtain a forty-foot easement, over the property, along with an adjacent temporary workspace easement. The forty-foot easement essentially followed the existing twenty-foot easement but encroached a greater distance into Green’s property. CenterPoint deposited $7,200 into the court registry as just compensation to Green, and the circuit court entered an order of possession. Green asked the court to deny CenterPoint’s petition or determine the amount of just compensation due him. The parties did not dispute that just compensation would be measured by the difference in the value of Green’s property, when put to its highest and best use, immediately before and immediately after the taking, plus an additional amount for the temporary workspace easement. See Rest Hills Memorial Park, Inc. v. Clayton Chapel Sewer Improvement District No. 233, 6 Ark.App. 180, 639 S.W.2d 519 (1982); Howard W. Brill, Arkansas Law of Damages § 18-4 (4th ed.2002).

At trial, appellee James Green testified that he is a real-estate developer who built several condominium units in Hot Springs. Green said that he had planned to build a sixteen-unit condominium complex consisting of four buildings on the subject property, but the increased width of the new easement prevented him from constructing a fourth building. He acknowledged that no development had actually taken place on the property, but he stated that his profit on condominium projects was generally about $200,000 per four-plex building. Green additionally offered testimony that, during construction, CenterPoint conducted operations and placed heavy equipment on land outside the designated workspace easement. Green attempted to introduce photographs taken during the construction period, but, [¡¡following CenterPoint’s objection, the court accepted the photographs as a proffer and Green’s testimony “under reservation.”

On Green’s behalf, real-estate appraiser Michael Pearce testified that the highest and best use of Green’s property was residential development, such as condominiums, townhomes, or zero-lot-line homes. Pearce determined that development of the land as a restaurant site would be worthwhile only as an intermittent use, noting that the restaurant building had reached the end of its economic life. In appraising the property using a comparable-sales approach and a cost approach, Pearce concluded that Green’s land had a value of $381,200 before the taking and $285,700 after the taking, for a difference of $95,500; and $2,600 for the temporary construction easement, which yielded a total just-compensation figure of $98,100.

CenterPoint’s appraiser, John David Stone, also concluded in his report that the highest and best use of Green’s land was residential, with usefulness as commercial property only on an interim basis. Relying primarily on the comparable-sales approach, Stone determined that the difference in value of Green’s land before and after the taking was $13,600, which, when added to a figure of $2,400 for the construction easement, resulted in total compensation to Green of $16,100. Stone’s calculations relied in part on his determination that the land alone, without improvements, was worth $174,400 after the taking. At trial, Stone testified that there was not currently a demand for condominiums at the site and that the highest and best use of the property was unknown.

|4On July 28, 2011, the circuit court issued a letter opinion, finding that the value of Green’s property before the taking was $235,000, the value after the taking was $174,400, and the resulting reduction in value was $60,600. The court then added $2,500 as the value of the temporary construction easement, for a total compensation to Green of $63,100.

Upon receipt of the letter ruling, Cen-terPoint requested “findings of fact and conclusions of law which constitute the grounds for your rulings.” The court then entered the following findings and conclusions:

A. Findings of Fact:
1. The value of the property before the taking was $235,000.
2. The value of the property after the taking was $174,400.
3. The diminution in value of the property was $60,600.
4.The value of the temporary construction easement is $2,500.
B. Conclusions of Law:
1. The property owner is entitled to the difference between the value of the property before the taking and the value of the property after the taking.
2. The property owner is entitled to the fair market rental value of the property not taken but used during the construction process.

Thereafter, the court entered judgment in favor of Green for $63,100, amended to $55,900 after Green received the $7,200 CenterPoint had deposited in the court registry.

II. Findings of Fact

CenterPoint argues that additional findings of fact are necessary because it is impossible to ascertain the basis for the circuit court’s just-compensation decision. We disagree.

| fiRule 52(a) of the Arkansas Rules of Civil Procedure provides that, if requested by a party at any time prior to the entry of judgment, in all contested actions tried on the facts without a jury, the court shall find the facts specially and state separately its conclusions of law thereon. The rule does not place a severe burden upon the trial judge, for the judge needs only to make brief, definite, and pertinent findings of fact and conclusions upon the contested matters. See BPS, Inc. v. Richardson, 341 Ark. 834, 20 S.W.3d 403 (2000). The trial court need not explain why it found the facts the way it did or give detailed reasons for its decision. David Newbern, John J. Watkins, & D.P. Marshall, Civil Practice & Procedure § 30:7 (5th ed.2010). Rather, the findings should be specific enough to enable the appellate court to understand the factual basis and analytical process by which the trial court reached its decision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christina Morris v. Chad Morris
2026 Ark. App. 52 (Court of Appeals of Arkansas, 2026)
Ashley Bancstock Co. v. Meredith
2017 Ark. App. 598 (Court of Appeals of Arkansas, 2017)
Howard v. Adams
2016 Ark. App. 222 (Court of Appeals of Arkansas, 2016)
City of Jacksonville v. Nixon
2014 Ark. App. 485 (Court of Appeals of Arkansas, 2014)
GSS, LLC v. Centerpoint Energy Gas Transmission Co.
2014 Ark. 144 (Supreme Court of Arkansas, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
413 S.W.3d 867, 2012 Ark. App. 326, 2012 WL 1608576, 2012 Ark. App. LEXIS 445, Counsel Stack Legal Research, https://law.counselstack.com/opinion/centerpoint-energy-gas-transmission-co-v-green-arkctapp-2012.