Center for Biological Diversity v. Spellmon

CourtDistrict Court, D. Montana
DecidedAugust 18, 2022
Docket4:21-cv-00047
StatusUnknown

This text of Center for Biological Diversity v. Spellmon (Center for Biological Diversity v. Spellmon) is published on Counsel Stack Legal Research, covering District Court, D. Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Center for Biological Diversity v. Spellmon, (D. Mont. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MONTANA GREAT FALLS DIVISION

CENTER FOR BIOLOGICAL CV-21-47-GF-BMM DIVERSITY, et al.,

Plaintiffs, ORDER

v.

L T. GEN SCOTT A. SPELLMON, et al.,

Defendants,

and

A MERICAN GAS ASSOCIATION, et al.,

Defendant-Intervenors,

S TATE OF MONTANA,

Defendant-InterveInNorT. RODUCTION Plaintiffs Center for Biological Diversity, Sierra Club, Montana Environmental Information Center, Friends of the Earth, Waterkeeper Alliance (“Plaintiffs”) filed this action against the U.S. Army Corps of Engineers (“Corps”) and Lieutenant General Scott Spellmon (collectively, “Federal Defendants”) for

alleged violations of the Endangered Species Act (“ESA”), 16 U.S.C. §§ 1531- 1544, the National Environmental Policy Act (“NEPA”), 42 U.S.C. §§ 4321 et seq., the Clean Water Act (“CWA”), 33 U.S.C. § 1344(e), and the Administrative

Procedure Act (“APA”), 5 U.S.C. §§ 701-706 in reissuing Nationwide Permit 12 (“NWP 12”) during the final days of the Trump administration. (Doc. 1.) BACKGROUND NWP 12 authorizes—without the need for a separate individual CWA

permit—certain activities in waters of the United States associated with the construction, maintenance, repair, and removal of oil and gas pipelines. CWA Section 404 prohibits the discharge of dredged or fill material into “waters of the

United States” without a Corps permit. See 33 U.S.C. § 1344(a). Section 404 originally authorized the Corps to issue only individual permits. Individual permits require a resource-intensive, case-by-case review, including extensive site- and permit-specific documentation and public comment. See Id. § 1344(e)(1); 33

C.F.R. pts. 323 and 325. Accordingly, in 1977, Congress added CWA Section 404(e), creating a general permit program for minor, routine activities to avoid imposing unnecessary

delay and administrative burdens on the public and the Corps. See 33 U.S.C. § 1344(e). Section 404(e) authorizes the Corps to issue general permits “for any category of activities involving discharges of dredged or fill material if the [Corps]

determines that the activities in such category are similar in nature, will cause only minimal adverse environmental effects when performed separately, and will have only minimal cumulative adverse effect on the environment.” Id. § 1344(e)(1).

General permits remain valid for no more than five years. Id. § 1344(e)(2). General permits also must comply with the CWA Section 404(b)(1) Guidelines promulgated by the U.S. Environmental Protection Agency (“EPA”). Id. § 1344(b)(1).

As with the individual permitting process, the Corps must comply with the ESA and NEPA when issuing a NWP. See 33 C.F.R. § 330.4(b)(2), (f). As relevant here, Section 7 of the ESA requires “action agencies,” such as the Corps, to engage

in consultation with the Fish and Wildlife Service and National Marine Fisheries Service (“Services”) to “insure” that their actions are “not likely to jeopardize” the continued existence of listed species. 16 U.S.C. § 1536(a)(2). Once a NWP has been issued, projects meeting the specific terms and

conditions of a NWP may be constructed without even notifying the Corps. See 33 C.F.R. § 330.1(c), (e)(1). In some cases, however, applicants must submit a preconstruction notification (“PCN”) to the Corps and defer construction until the

district engineer verifies that the project meets the NWP’s terms and conditions. See id. §§ 330.1(e)(1), 330.6(a)(1). If the district engineer determines that the project does not comply with the NWP’s terms and conditions, the Corps must

deny verification. See id. § 330.6(a)(2). The applicant may then seek authorization under Section 404’s individual permitting process. Id. The Corps issued a set of nationwide permits—including a new NWP 12—

in January 2021. 86 Fed. Reg. 2744. As reissued, NWP 12 authorizes the construction of oil and gas pipelines through rivers, streams and wetlands, so long as each “single and complete project” will not result in the loss of more than half an acre of U.S. waters. NWP000945. In the Decision Document for NWP 12, the

Corps estimated that NWP 12 will be used for approximately 47,750 projects over its five-year lifespan and impact 3,160 acres of U.S. waters and wetlands. NWP001052. Generally, NWPs cannot be used more than once for any “single and

complete project.” 33 C.F.R. § 330.6(c). For linear projects like those authorized by NWP 12, however, the Corps defines “single and complete project” to apply to each individual water crossing. Id. § 330.2(i); NWP000038, NWP000072. Thus, for a single pipeline, NWP 12 can be used for multiple—indeed, an unlimited

number of—water crossings without necessarily exceeding the half-acre threshold. See NWP000120-21. NWP 12 requires the submission of a PCN “prior to commencing the

activity” if, among other reasons, the “discharges [will] result in the loss of greater than 1/10-acre of [CWA] waters of the United States,” or a permit is required for crossing a navigable water. Unlike the prior 2017 NWP 12, the 2021 NWP 12 also

requires a PCN if the Permit is sought to be used for construction of new pipeline greater than 250 miles in length. Compare id. with 82 Fed. Reg. 1860, 1986 (Jan. 6, 2017).

As with all the nationwide permits, NWP 12 was subject to public notice and comment, and the Corps prepared an Environmental Assessment (to consider the permit’s potential environmental effects), conducted a public interest review, and completed an analysis under the Section 404(b)(1) Guidelines. See NWP000945–

1078. In addressing its ESA obligations for NWP 12, the Corps has once again relied on General Condition 18. This condition requires applicants to submit a PCN

whenever a project “might affect” listed species or critical habitat. See NWP000104. Because of General Condition 18, the Corps asserted that the reissuance of NWP 12 would have “no effect” on listed species and that any such effects from individual projects would be analyzed on a project-specific basis. See

NWP000105, NWP003596. The Corps therefore did not conduct any ESA consultation with the Services before it reauthorized NWP 12. The Court previously determined that the 2017 reissuance of NWP 12

violated the ESA for failure to consult. N. Plains Res. Council v. U.S. Army Corps of Engineers, 454 F. Supp. 3d 985, 992 (D. Mont. April 15, 2020) (“Northern Plains”). The Court stated plainly that the “Corps cannot circumvent ESA Section

7(a)(2) consultation requirements by relying on project-level review or General Condition 18.” Id. ANALYSIS

I. The Court will transfer venue of this case to the United States District Court for the District of Columbia

This case presents a unique issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Center for Biological Diversity v. Spellmon, Counsel Stack Legal Research, https://law.counselstack.com/opinion/center-for-biological-diversity-v-spellmon-mtd-2022.