Cent. La. Elec. Co. v. LA. PUB. SERV. COM'N

377 So. 2d 1188
CourtSupreme Court of Louisiana
DecidedNovember 1, 1979
Docket64452
StatusPublished
Cited by2 cases

This text of 377 So. 2d 1188 (Cent. La. Elec. Co. v. LA. PUB. SERV. COM'N) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cent. La. Elec. Co. v. LA. PUB. SERV. COM'N, 377 So. 2d 1188 (La. 1979).

Opinion

377 So.2d 1188 (1979)

CENTRAL LOUISIANA ELECTRIC COMPANY, INC.
v.
LOUISIANA PUBLIC SERVICE COMMISSION.

No. 64452.

Supreme Court of Louisiana.

November 1, 1979.
Rehearing Denied January 11, 1980.

*1189 Marshall B. Brinkley, Gen. Counsel, Baton Rouge, for La. Public Service Commission, defendant-appellee.

William O. Bonin, New Iberia, for Central La. Elec. Co., Inc., plaintiff-appellant.

Bobby L. Forrest, Forrest, Kiefer, Bacot & Moore, Baton Rouge, for intervenor-appellant, Forrest House Apartments.

SUMMERS, Chief Justice.

Forrest House Apartments (Forrest), a limited partnership, filed a complaint with the Public Service Commission (Commission) on September 10, 1976. The complaint set forth that Central Louisiana Electric Company, Inc. (CLECO) is a public utility, operating in Louisiana. On or about January 15, 1971, Forrest applied to the Department of Housing and Urban Development (HUD) for a loan to finance an apartment complex on Highway 28, also known as Holloway Prairie Road in Pineville, Louisiana. The application was approved on December 8, 1971, and amended November 9, 1972, whereby HUD issued a commitment to insure under the National Housing Act.

The complaint further set forth that, in order to obtain the commitment, Forrest made a market survey of the utility charges in the Alexandria-Pineville metropolitan area. Forrest based its request for mortgage insurance to the Federal Housing Commission on the data obtained, projecting an average utility cost of approximately $17.50 per month per unit. The estimate was based upon the rates prevailing in the area paid by customers being served by CLECO, the sole company furnishing electrical power in the area.

Between January 15, 1971 and December 8, 1971, at which time Forrest was approved for a loan by the Federal Housing Administration, representatives of CLECO met with *1190 Forrest, the complaint alleges. The purpose of these meetings was to discuss the most economically feasible method of furnishing electric power to the individual apartment units. At these meetings representatives of CLECO agreed, it is alleged, that if Forrest would meet what was then referred to as "Gold Medallion Standards", an "all electric" utility installation, CLECO would guarantee and contract to meter the apartment units in the most economical method in use in the area at that time to apartment owners.

According to the complaint, Forrest began construction on or about December 30, 1971, with CLECO furnishing electricity for the construction phase of the apartment project. The project consists of 80 living units and one office and laundry building combination. There are 20 one-bedroom units, 50 two-bedroom units, and ten three-bedroom units housed in 13 buildings, plus the office and laundry building.

Several buildings were substantially complete in the latter part of 1972. As each building passed final inspection it was energized by CLECO. After all of the apartment buildings had been energized, Forrest complained, it was noted in 1973 that the utility bills far exceeded those prevailing in the area. Complaints were made to CLECO, according to Forrest, and conferences were had in late 1973 and during 1974. In August 1974, Forrest alleges, it learned that CLECO had installed a metering device known as a "demand meter", to service its apartment complex, the installation having been made without the consent of Forrest. A "demand meter", according to Forrest, is a device and system for commercial establishments, and its use resulted in excessive charges for the electricity it used. With this knowledge Forrest again made formal demand on CLECO to reduce the rates, and CLECO replied that the "demand meter" and the rates it was charging were approved by the Commission.

Forrest asserts in its complaint that the "demand meter" is not in general use for apartments, and its use resulted in rates in excess of those paid by similar apartment complexes. For these reasons Forrest claims its rates were unreasonable and unjust. The Commission was asked to determine the extent and amount of the excessive charges.

CLECO answered, alleging that prior to October 8, 1971, its representatives met with a representative of Forrest. The meeting concerned Forrest's desire to have CLECO provide electric service through a master meter with free underground service from the meter to the apartments. No agreement was made nor did CLECO then guarantee to meter the apartments in any particular way. In addition, the answer asserts, the apartments did not meet CLECO's "Gold Medallion" standards.

In its answer CLECO admits that a "demand meter" is a device used for measuring load in order to compute the demand charge provided in the GS (General Service) rate schedule, and that representatives of Forrest indicated a desire to have electric service furnished through one meter in an effort to reduce electric energy charges. However, CLECO claimed it informed Forrest that in order to obtain this advantage it was necessary for Forrest to bear the cost of the distribution system beyond the meter. Forrest was unwilling to supply the required distribution system. Therefore, CLECO advised Forrest that demand meters were the alternative, they were approved by the Commission and electric energy was furnished under rates approved by the Commission.

Finally, CLECO answered, electric energy had been furnished to Forrest pursuant to the distribution plan approved by Forrest and pursuant to the applicable GS rate schedule.

In a supplemental complaint Forrest represents that subsequent to the meeting with representatives of CLECO in 1971, CLECO advised them in an October 8, 1971 letter that three types of service were available to Forrest:

"A. Primary metering—single or three phase—CLECO will build and provide *1191 service to (a) point on the property and install appropriate metering equipment. CLECO's ownership ceases at the meter and all work and equipment from that point on becomes the responsibility of the developer.

"B. Individual metering per apartment —CLECO will install all overhead services to the apartment buildings at our cost, provided necessary rights-of-way are furnished.

"C. Individual metering per apartment (underground service using padmount transformers) CLECO will install, own and maintain all single phase primary lines and padmount transformers necessary to serve the apartment project. The Developer will pay in advance the difference in cost of an overhead system and the above mentioned (item C) underground service. The Developer will be responsible for installation of all secondary equipment and lines past the transformer."

Forrest having rejected these, by a November 3, 1971 letter CLECO suggested a fourth method:

"... to meter each building on a master meter. Again, this could be done through an overhead system where we installed all services to the buildings at our cost, or an underground system, where CLECO will install, own and maintain all single phase primary lines and pad mount transformers necessary to serve your apartments. With the underground, you would pay the difference between the cost of overhead and underground and be responsible for installation of all secondary equipment and lines past the transformers."

Forrest was not advised, it alleges, that selection of any one of the four types of service recommended by CLECO would result in rates higher than its competitors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DEPT., PUBLIC SAF. & CORR. v. Savoie
569 So. 2d 139 (Louisiana Court of Appeal, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
377 So. 2d 1188, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cent-la-elec-co-v-la-pub-serv-comn-la-1979.