Celotex Corp. v. CAMPBELL ROOF. & MET. WORKS, INC.

352 So. 2d 1316
CourtMississippi Supreme Court
DecidedDecember 14, 1977
Docket50005
StatusPublished
Cited by12 cases

This text of 352 So. 2d 1316 (Celotex Corp. v. CAMPBELL ROOF. & MET. WORKS, INC.) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Celotex Corp. v. CAMPBELL ROOF. & MET. WORKS, INC., 352 So. 2d 1316 (Mich. 1977).

Opinion

352 So.2d 1316 (1977)

CELOTEX CORPORATION
v.
CAMPBELL ROOFING AND METAL WORKS, INC.

No. 50005.

Supreme Court of Mississippi.

December 14, 1977.

Fox & Gowan, John H. Fox, III, Marc A. Biggers, Jackson, for appellant.

Johnston & Adams, Lem Adams, III, Brandon, for appellee.

EN BANC.

WALKER, Justice, for the Court:

This case grew out of a construction project undertaken by the Jackson Municipal Airport Authority. Becknell Construction, Inc. was the general contractor on the project, Campbell was the roofing subcontractor and Celotex supplied the roofing materials. Becknell warranted and guaranteed that all work would be of good quality, free from faults and defects and in compliance with the plans and specifications. The warranty included defects resulting from the use of inferior materials and workmanship. Becknell entered into a subcontract with Campbell for constructing a roof and Campbell in turn warranted its work against all defects of materials and workmanship.

*1317 Soon after construction of the roof was completed, the roof blistered and leaked. Two unsuccessful repair attempts were made, the first by Campbell alone, and the second by Campbell at the direction and expense of Celotex. In the original installation of the roof and in both repair attempts, Celotex materials were used. When the roof continued to leak after these two repair attempts, the airport authority gave notice to Becknell that it would have the roof replaced by another contractor if Becknell did not replace it. Becknell in turn gave notice to Campbell and Celotex, and when they failed to act, the airport authority had the roof replaced by Southern Roofing Company. Thereafter the airport authority filed suit against Becknell which resulted in a judgment against Becknell in the amount of $32,546.05.

Becknell thereupon filed suit against Campbell and Celotex for indemnity based upon the express warranty made by Campbell and the implied warranty of fitness made by Celotex. After a trial in the Circuit Court of Rankin County, Mississippi, a joint and several judgment was rendered against Campbell and Celotex for $32,766.10. Celotex appealed the judgment contending that the proof was not sufficient to sustain the verdict of the jury because it was not shown that the materials furnished by Celotex were defective. However, after careful consideration of the record, this Court found that the jury's verdict was based on conflicting evidence and the verdict would have to stand. Celotex Corp. v. Becknell Construction, Inc., 325 So.2d 566, 568 (Miss. 1976).

Although Becknell could have recovered in part from both Campbell and Celotex, since the judgment was joint and several, it chose recovery from Celotex alone. Consequently, under the compulsion of an execution of judgment issued by the clerk of the Circuit Court of Rankin County, Celotex was forced to pay the entire amount of the judgment which, with interest and costs, amounted to $37,517.20.

Thereafter Celotex (whose materials were found to be faulty) initiated the instant action in the Chancery Court of Rankin County seeking contribution from Campbell (whose workmanship was found to be faulty). Celotex acknowledges that it is precluded from a relitigation as to its liability for the judgment rendered against it and Campbell jointly and severally, but argues that each of the joint and several defendants should pay their proportionate share of the judgment and that the share of each defendant should be calculated or based upon the degree of fault of each defendant. In this regard, Celotex claims that the fault of its roofing materials, if any, was minute as compared to the lack of skill and workmanship and the failure of performance of the roofing contract by Campbell. Specifically, Celotex alleges that Campbell's lack of skill and workmanship and the failure of Campbell's performance of its contract was the direct and proximate cause of and contributed a minimum of ninety percent to the defective aspects of the roofing failure which was the basis of the $32,546.05 judgment against Celotex and Campbell.

Campbell demurred to Celotex's bill of complaint alleging that no equity appeared upon the face of the bill. The chancellor agreed and entered an order sustaining the demurrer.

This case presents three questions to be answered by this Court:

(1) Is contribution allowed between joint judgment debtors, one of whom was found liable to the judgment creditor, Becknell, on account of a breach of express warranty, and the other who was found liable to Becknell on account of breach of an implied warranty?

(2) Is contribution enforceable in a court of equity?

(3) Should contribution, if allowed, be pro-rata based upon the number of defendants or should it be based on the percentage of liability attributable to the seriousness of the conduct of each of them?

*1318 I.

IS CONTRIBUTION ALLOWED BETWEEN JOINT JUDGMENT DEBTORS, ONE OF WHOM WAS FOUND LIABLE TO THE JUDGMENT CREDITOR, BECKNELL, ON ACCOUNT OF A BREACH OF EXPRESS WARRANTY, AND THE OTHER WHO WAS FOUND LIABLE TO BECKNELL ON ACCOUNT OF BREACH OF AN IMPLIED WARRANTY?

The doctrine of contribution requires that persons having a common liability, such as the joint and several judgment against Campbell and Celotex, bear their individual share of the burden imposed and not have any one of them carry the full load. The general rule of common law is that one who is compelled to satisfy, or pay more than his just share of such common burden or obligation, is entitled to contribution from the others to obtain from them payment of their respective shares.

Contribution was generally allowed at common law except that no contribution could be had between tort-feasors and wrongdoers. This exception to the general rule allowing contribution was first enunciated in 1799 in the case of Merryweather v. Nixan, 8 Durn & E. 186, 101 Eng.Rep. 1337 (K.B. 1799). However, in England the exception to the rule was abolished in 1935 by the Law Reform (married women and tortfeasors) Act which provides that a tort-feasor may recover contribution from any other tort-feasor who is, or would, if sued, have been liable in respect of the same damage, whether as a joint tort-feasor or otherwise.

Prior to the passage of Mississippi Code Annotated section 85-5-5 (1972),[*] Mississippi followed the rule denying contribution between joint tort-feasors. In the case of Klaas v. Continental Southern Lines, 225 Miss. 94, 111-12, 82 So.2d 705, 707 (1955), it was said:

Before Chap. 259 was passed, there was in Mississippi no right in joint tort feasors to obtain contribution between themselves. Thomas v. Rounds, 161 Miss. 713, 137 So. 894 (1931); Mississippi Central R.R. Company v. Roberts, 173 Miss. 487, 160 So. 604 (1935); Teche Lines v. Pope, 175 Miss. 393, 166 So. 539 (1936); Meridian City Lines v. Baker, 206 Miss. 58, 39 So.2d 541 (1949).
... The effect of the statute was to create rights which did not exist before. And it destroyed a valid defense to an action available before the enactment of the statute. Richards v. City Lumber Co., 101 Miss. 678, 57 So. 977 (1912). It took away a substantive right, a valid defense, and created a right in a joint tort feasor who has paid the entire judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Remy Jonathan Bozant v. Hang M. Nguyen
Court of Appeals of Mississippi, 2020
EMJ Corp. v. Hudson Specialty Insurance
90 F. Supp. 3d 644 (N.D. Mississippi, 2015)
George Williams v. Joe Sam Owen
Mississippi Supreme Court, 1993
Clement Alleyne v. Theodore Jones
Mississippi Supreme Court, 1993
Williams v. Owen
613 So. 2d 829 (Mississippi Supreme Court, 1993)
Adkinson v. International Harvester Co.
975 F.2d 208 (Fifth Circuit, 1992)
Comfort Engineering Co., Inc. v. Kinsey
523 So. 2d 1019 (Mississippi Supreme Court, 1988)
Wilson v. Giordano Ins. Agency, Inc.
475 So. 2d 414 (Mississippi Supreme Court, 1985)
General Dynamics Corp. v. WRIGHT AIRLINES
470 So. 2d 788 (District Court of Appeal of Florida, 1985)
Masters v. State
668 P.2d 73 (Idaho Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
352 So. 2d 1316, Counsel Stack Legal Research, https://law.counselstack.com/opinion/celotex-corp-v-campbell-roof-met-works-inc-miss-1977.