Cellized Block Flooring Co. v. Campbell

188 So. 674, 1939 La. App. LEXIS 231
CourtLouisiana Court of Appeal
DecidedMay 8, 1939
DocketNo. 17016.
StatusPublished

This text of 188 So. 674 (Cellized Block Flooring Co. v. Campbell) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cellized Block Flooring Co. v. Campbell, 188 So. 674, 1939 La. App. LEXIS 231 (La. Ct. App. 1939).

Opinion

JANVIER, Judge.

R. W. Markel, who conducts his business as “Cellized Block Flooring Company”, brings this suit against Vic Campbell for the contract price agreed upon for the furnishing of all material and labor necessary to install an “oak tile” flooring in certain parts of a residence which Campbell was constructing in New Orleans.

Defendant admits the making of the contract and the price stipulated for, but resists payment on the ground that the work was not done in a workmanlike manner, contending that it is so defective that the cost of putting the said floors into proper condition will be greater than the amount which would be due defendant under the contract. Defendant contends, also, that he has sustained special damages and, furthermore, that, as a result of the recordation of the lien claimed by plaintiff, he has sustained additional damage, and he, therefore, by reconventional demand, seeks judgment against plaintiff for $450.

There was judgment dismissing both the suit of plaintiff and the reconventional demand and plaintiff alone has appealed.

■On May 16, 1936, Markel submitted to Campbell a written offer to furnish and lay certain oak tile flooring in Campbell’s residence. The price offered was $224 and in this offer Markel included the following recommendation:

“We recommend to use two-ply asphalt membrane water-proofing applied to the concrete sub-flooring with hot asphalt, and submit price for this work in the amount of $48.00.”

The offer was accepted and the price, $224, was agreed to, but Campbell did not adopt the recommendation concerning the use of “asphalt membrane water-proofing”. At just about the time of the commencement of the work, Campbell decided to put the same kind of floors in the kitchen and in the solarium and he asked Markel for a bid on the additional flooring. Markel, in writing, agreed to do the additional work for $63 and in his written offer again referred to his former suggestion concerning the membrane water-proofing. This time he said:

“With reference to the membrane waterproofing that we recommended in our original estimate, we are following your instructions in not using the membrane waterproofing, as you do not desire to assume the extra cost for this work. However should *675 any tremble be caused from dampness, account being laid on concrete over earth fill, we will not be responsible for it.”

Apparently Campbell was not satisfied with this qualification of Markel’s guarantee and, after some discussion, Markel wrote Campbell a letter containing the following paragraph:

“With reference to the second paragraph of our letter of September 3rd, regarding guarantee on account of omission of membrane water-proofing, as stated to you and Mr. Herbert Benson, at the building, we fully guarantee the floors installed at your residence and we agree to make any corrections that may be necessary from any expansion or cupping from the general use of your building, but we will not be responsible for any damage that may be caused from the outside entrance doorways, if water should get thru to the floors at these outside points; or if the water should get on the floors, from some unforeseen weather condition, thru the concrete walls above the floor line.”

When the work was completed, many faults were found therein, chief among which was the fact that the floor was found to bulge up in many spots and to break loose from the plastic material which was intended to bind it to the concrete foundation on which it was laid. It seems certain that this condition resulted primarily from dampness, which penetrated the said concrete from below and which also seems to have reached the edges of the floor through the exterior walls. The record leaves no room for doubt that that type of floor cannot be satisfactorily applied to a concrete floor which itself is resting on earth, unless the building is located where there is extremely good drainage, or unless, between the. concrete and the plastic material on which the floor is laid, there is placed the membrane water-proofing material which Markel had recommended. There seem to have been other defects in the floor, most of which could apparently have been remedied, but the absence of the water-proofing material was obviously responsible for the fact that water penetrated through the concrete and attacked the floor from below. It is quite apparent that this was the danger which Mr. Markel had in mind when he recommended the installation of the waterproofing material, and, had he unqualifiedly advised Mr. Campbell that he would not guarantee the floor against such condition unless the water-proofing material should be installed, there is no doubt that he could not be held responsible. But it must be remembered that Markel is a flooring expert and that he was furnishing a special, patented type of flooring, concerning which he had all information and about which Campbell knew nothing.

He now states that, in buildings such as Campbell’s, it is practically impossible to keep water from penetrating the concrete, and yet, even his first letter did not warn Campbell of this fact. It is true that he recommended the use of the water-proofing material, but he in no way intimated that failure to insert such material might cause the result which has occurred. It is true, also, that in his second letter he stated that he would not be responsible “should any trouble be caused by dampness”, and, had the matter terminated there, it is probable that Campbell would be held to have assumed the risk of damage from dampness had it reached the floor because of absence of the said water-proofing material. But Campbell was not satisfied and did not permit the matter to terminate with this reservation, but demanded a more unconditional guarantee, and thereupon Markel wrote the letter in which he seems to have broadened his guarantee to include damage from any cause except as a result of water entering from the outside doorways, or as a result of water getting on the floors “from some unforeseen weather condition, through the concrete walls above the floor line”. An analysis of these reservations shows that Markel agreed to be responsible unless the water should enter “from some unforeseen weather condition”, and even then, only for such water as might find its way through the concrete walls “above the floor line”. We may say here that it is very obvious that the water reached the floor by seeping up through the concrete on which it was laid and that, therefore, the reservation contained in Markel’s guarantee had no application to such water, but, wherever it came from, there was no “unforeseen weather condition” which caused it to enter. There is no showing of any unusual fall of rain and it is very evident, from a reading of a paragraph in Markel’s letter of October 5, that all he intended to protect himself against was one of the torrential downpours with which this city is sometimes visited, for, immediately following the paragraph extending the guarantee is the following explanation made by Mr. Markel:

*676 “We are only making the above statement for the fact, that should we have a condition to arise that existed in New Orleans about eight years ago, where many buildings were flooded that had a considerable higher floor level than in your building.”

We conclude, from all of these facts, that Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A. Baldwin Sales Co. v. Mitchell
142 So. 700 (Supreme Court of Louisiana, 1932)
Succession of Kerry v. Freed Realty Co.
6 La. App. 437 (Louisiana Court of Appeal, 1927)
Reicke v. Bland
7 La. App. 280 (Louisiana Court of Appeal, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
188 So. 674, 1939 La. App. LEXIS 231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cellized-block-flooring-co-v-campbell-lactapp-1939.