Cellco Partnership v. Deer District LLC

140 F.4th 854
Court of Appeals for the Seventh Circuit·Decided June 13, 2025·No. 24-1212·Published

Opinion

In the

United States Court of Appeals For the Seventh Circuit

No. 24-1212 CELLCO PARTNERSHIP, d/b/a VERIZON WIRELESS, Plaintiff-Appellee,

v.

CITY OF MILWAUKEE and JERREL KRUSCHKE, Defendants,

APPEAL OF: DEER DISTRICT LLC, Intervening Defendant-Appellant.

Appeal from the United States District Court for the Eastern District of Wisconsin.

No. 2:23-cv-01581-BHL — Brett H. Ludwig, Judge.

ARGUED NOVEMBER 14, 2024 — DECIDED JUNE 13, 2025

Before JACKSON-AKIWUMI, PRYOR, and MALDONADO, Circuit Judges.

MALDONADO, Circuit Judge. Two years ago, in an effort to improve network coverage, Verizon Wireless sought permits 2 No. 24-1212

from the City of Milwaukee to install small cells and matching utility poles in a downtown plaza next to a major arena. The City denied most of the permits, initially citing aesthetic concerns and proximity to existing poles. Later, it asserted that it lacked authority to grant the permits because the plaza was leased to a private entity, Deer District LLC.

Verizon sued the City in federal court, arguing that the denials violated the Telecommunications Act (TCA), 47 U.S.C. § 332(c)(7)(B)(iii), and Wis. Stat. § 66.0414. After a bench trial, the district court ruled for Verizon. It concluded that the City’s shifting justifications did not hold up and that the City wanted to steer Verizon toward using Deer District’s own wireless system. Exercising its equitable authority under the TCA, the district court ordered the City to issue the permits. Verizon has since installed the poles.

The City accepted the ruling. Deer District—an intervening -defendant—did not. It now appeals, challenging the district court’s interpretation of the lease and Wis. Stat. § 66.0414, but not its holding under the TCA. In essence, Deer District argues that the district court’s decision, particularly its characterization of the plaza as a public right-of-way, violates its rights under the lease. As discussed below, we cannot reach Deer District’s arguments because it lacks Article III standing to bring this appeal. We therefore dismiss for want of jurisdiction .

BACKGROUND

I. Facts In July 2021, the Milwaukee Bucks won the NBA Finals. The championship series spanned two weeks and drew thousands of fans to the Bucks’ arena, the Fiserv Forum, and its

No. 24-1212 3

adjacent pedestrian mall, the Deer District Public Plaza (the Plaza). The large crowds strained cellular coverage in the area. Verizon’s network, in particular, struggled to support the volume of devices, resulting in unreliable service for many customers.

Then, in December 2022, news broke that the Fiserv Forum would host the Republican National Convention (RNC) in July 2024, an event projected to attract 50,000 attendees over four days. Wary of repeating the network issues experienced during the NBA Finals, Verizon began exploring options to improve cellular coverage in the Plaza.

Initially, Verizon sought to install “small cells,” shortrange mobile cell sites designed to augment network capacity in dense urban areas, on existing utility poles in the Plaza. But the City of Milwaukee rejected this request because it did not own the poles. The City explained that these poles were owned by Deer District LLC, an affiliate of the Milwaukee Bucks, and that Deer District refused permission for the small cells to be installed.

Unable to utilize the existing infrastructure, Verizon considered alternatives. One option was to design, construct, and install its own utility poles in the Plaza, which would require Verizon to secure the necessary city permits. Alternatively, Verizon considered a proposal from Deer District to deploy a distributed antenna system (DAS) instead of small cells. Under Deer District’s proposal, Verizon would pay Deer District an initiation fee of $10 million to use the DAS and then a monthly rent of $10,000, subject to a 3.5% increase per year. In the end, Verizon decided to install its own small-cell poles, concluding that the DAS would introduce compatibility 4 No. 24-1212

issues with its existing network and that Deer District’s proposal was cost-prohibitive.

Accordingly, on August 3, 2023, Verizon submitted permit applications with the City to install four small-cell poles: three within the Plaza and one north of the Fiserv Forum. Verizon specified in its permit applications that the poles would be custom-made to match the existing ones in the Plaza.

On October 24, the City approved Verizon’s permits for the pole to be constructed outside the Plaza. Two days later, however, the City denied the permits for the three proposed poles within the Plaza. In an email to Verizon, the City justified the denials because the proposed poles were “too close to existing poles” and constituted “unsightly or out-of-character deployments” in violation of the City’s aesthetic requirements .

The next day, Deer District’s lawyer told the City that its lease of the Plaza precluded it from permitting Verizon to install poles in the Plaza. Specifically, the City had leased the Plaza to Wisconsin Center District, a quasi-governmental entity , which subleased the property to Deer District. According to Deer District, its sublease (the Lease) granted it exclusive rights over commercial activities in the Plaza, including the installation of public utilities. The email also referenced Deer District’s ongoing proposal to implement a DAS as an alternative for Verizon to improve network connectivity.

On November 10, two weeks after receiving Deer District ’s email and ninety-nine days after Verizon submitted its permit applications, the City sent Verizon a letter offering an additional rationale for the permit denials. Adopting Deer District’s position, the City claimed that it lacked authority to

No. 24-1212 5

grant permits for pole installations within the Plaza because it had effectively transferred all control over the Plaza to Deer District, reserving only limited rights for public transportation and public access. Two weeks later, Verizon sued the City of Milwaukee and its Commissioner of Public Works in federal court.

II. Procedural History Verizon’s complaint proceeded under two causes of action . First, it alleged that the City’s permit denials were preempted by the TCA, 47 U.S.C. § 332(c)(7)(B)(iii), because the denials were not supported by “substantial evidence.” It also alleged that the denials violated Wis. Stat. § 66.0414, which requires approval of small wireless facility permits inside a “right-of-way” unless they conflict with specified regulations . Because the RNC was only months away, Verizon sought “expedited review” of its claims in the district court and moved for a preliminary injunction. See 47 U.S.C. § 332(c)(7)(B)(v).

The City argued that it did not violate either statute, maintaining that it lacked the authority to issue permits for the Plaza since the property was leased to Deer District. The City conceded that the Plaza was “technically” a public right-of- way that would ordinarily be subject to the TCA and Wis. Stat. § 66.0414, but it contended that the Lease extinguished some of the City’s rights (and obligations) under those statutes .

On January 19, 2024, the district court held an initial hearing on Verizon’s motion for a preliminary injunction. After this hearing, and on the City’s recommendation, the district 6 No. 24-1212

court invited Deer District to join the suit. Three days later, Deer District moved to intervene, and the court granted its motion. Two days after that, with all parties’ consent, the court held a bench trial on the merits under FED. R. CIV. P. 65(a)(2), hearing arguments from Verizon, the City, and Deer District, along with witness testimony and numerous declarations and exhibits.

After the trial, the district court ruled in favor of Verizon.

Free access — add to your briefcase to read the full text and ask questions with AI

Cellco Partnership v. Deer District LLC, 140 F.4th 854 (7th Cir. 2025).

140 F.4th 854 (Cellco Partnership v. Deer District LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Juidice v. Vail
430 U.S. 327 (Supreme Court, 1977)
Allen v. Wright
468 U.S. 737 (Supreme Court, 1984)
Asarco Inc. v. Kadish
490 U.S. 605 (Supreme Court, 1989)
Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Greenlaw v. United States
554 U.S. 237 (Supreme Court, 2008)
K.C. Ex Rel. Africa H. v. Shipman
716 F.3d 107 (Fourth Circuit, 2013)
Hollingsworth v. Perry
133 S. Ct. 2652 (Supreme Court, 2013)
Chris Cabral v. City of Evansville
759 F.3d 639 (Seventh Circuit, 2014)
Kendall-Jackson Winery, Ltd. v. Branson
212 F.3d 995 (Seventh Circuit, 2000)
California v. Texas
593 U.S. 659 (Supreme Court, 2021)
TransUnion LLC v. Ramirez
594 U.S. 413 (Supreme Court, 2021)
Murthy v. Missouri
603 U.S. 43 (Supreme Court, 2024)