Cedar Rapids Lodge & Suites, LLC v. JFS Development, Inc.

789 F.3d 821, 2015 U.S. App. LEXIS 10066, 2015 WL 3650379
CourtCourt of Appeals for the Eighth Circuit
DecidedJune 15, 2015
Docket12-3919
StatusPublished
Cited by4 cases

This text of 789 F.3d 821 (Cedar Rapids Lodge & Suites, LLC v. JFS Development, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cedar Rapids Lodge & Suites, LLC v. JFS Development, Inc., 789 F.3d 821, 2015 U.S. App. LEXIS 10066, 2015 WL 3650379 (8th Cir. 2015).

Opinion

COLLOTON, Circuit Judge.

Cedar Rapids Lodge and Suites, LLC appeals from the district court’s 1 grant of summary judgment in favor of Lightowler Johnson Associates, Inc., a North Dakota architectural firm. Cedar Rapids Lodge and Suites sued Lightowler alleging professional negligence in connection with the design of a hotel, and the district court ruled that the claim was' barred by the statute of limitations. We affirm.

I.

In 2003, John Seibert, Mark Gabrielson, and Ted Vosburg, governors of Cedar Rapids Lodge & Suites, obtained the rights to build an Americlnn franchise in Cedar Rapids, Iowa. Cedar Rapids Lodge & Suites used Lightowler as the architect for the new project. Lightowler sent Sie-bert a standard form agreement that included a choice-of-law provision specifying that its terms would be governed by the law of North Dakota.

Lightowler provided a full set of plans for the project on November 7, 2003. On November 20, 2003, Lightowler issued an addendum containing several changes to the plans requested by the Cedar Rapids Fire Marshal. The next day, Americlnn project manager Shawn Lidberg sent a letter to Siebert, with a copy to Lightowler, listing problems with the plans’ compliance with franchise standards. On January 7, 2004, the city sent Cedar Rapids Lodge & Suites a report seeking revisions to the architectural plans; the company forwarded the report to Lightowler. In response, Lightowler submitted revised plans on February 27, 2004.

Construction began in January 2004. On July 26, 2004, Lidberg of Americlnn led a construction site visit attended by Siebert, Gabrielson, and Vosburg of Cedar Rapids Lodge & Suites, various Americlnn representatives, and Tim Olson, a Ligh-towler engineer. Both Lidberg and Olson prepared reports detailing the design and construction deficiencies they observed during the site visit. They provided these reports to Siebert shortly thereafter. The last act performed by Lightowler on the hotel project was the transmission of a document to the contractor on September 24, 2004, responding to a question about plank cuts in the stairwells.

Lidberg of Americlnn led a second site visit on October 21, 2004. Neither Sie-bert from Cedar Rapids Lodge & Suites nor anyone from Lightowler attended. Lidberg produced a report identifying additional deficiencies and construction concerns, and sent it to Siebert’ and Lightowler. On November 1, 2004, Lightowler’s Steve Goldade sent a letter to Americlnn, with a copy to Siebert, responding to the report from the October site visit. Gol- *824 dade stated that Lightowler was not involved in construction administration for the hotel project and had no knowledge of the problems identified by the report.

The hotel opened for business on December 9, 2004, but problems continued. The city, after granting temporary certificates of occupancy, denied the hotel a final certificate in October 2006. At a meeting on October 16, 2008, the investors in Cedar Rapids Lodge & Suites voted to remove Siebert, Gabrielson, and-Vosburg as governors of the company.

On December 3, 2009, Cedar Rapids Lodge & Suites brought federal claims in the district court' against the company’s former governors and others involved in the hotel project. Invoking the district court’s supplemental jurisdiction, see 28 U.S.C. § 1367(a), the complaint also alleged professional negligence by Ligh-towler. The district court granted Ligh-towler’s motion for summary judgment, concluding that the claim was barred by the statute of limitations under either North Dakota law or Iowa law. The court denied a motion to reconsider, and all claims against other parties eventually were resolved. Cedar Rapids Lodge & Suites now appeals the order dismissing the claim against Lightowler. We review the district court’s ruling de novo.

II.

The parties dispute whether the action is governed by North Dakota’s two-year limitations period or Iowa’s five-year statute of limitations. Cedar Rapids Lodge & Suites does not argue that its claim against Lightowler was timely under North Dakota law, but contends that Iowa law applies, and that the claim was brought within the five-year limitations period. Even áccept-ing the applicability of Iowa law for purposes of analysis, we conclude that the claim is untimely.

The applicable Iowa statute provides a five-year limitations period for actions on unwritten contracts, or those “brought for injuries to property.” Iowa Code § 614.1(4). When the limitations period begins to run is also governed by Iowa law. See Walker v. Thielen Motors, Inc., 916 F.2d 450, 451 (8th Cir.1990). The district court concluded that Cedar Rapids Lodge & Suites had notice of problems with the hotel design by November 2003, so that the cause of action against Ligh-towler accrued more than five years before the lawsuit was filed in December 2009. Cedar Rapids Lodge & Suites advances two reasons why the clock allegedly did not start running until a later date that was within five years of December 2009.

A.

Cedar Rapids Lodge & Suites relies first on the “adverse domination doctrine.” This doctrine, where applicable, holds that the statute of limitations is tolled as to claims of wrongdoing against officers or directors of a corporation as long as they control the corporation. See Resolution Trust Corp. v. Armbruster, 52 F.3d 748, 751 (8th Cir.1995). Cedar Rapids Lodge & Suites seeks to apply the doctrine to toll the limitations period for a claim not against the officer or directors of the company, but against a third party, Lightowler. The company contends that because its governors were wrongdoers who withheld information from investors about design and construction defects with the hotel, the statute of limitations for the company’s claim against Lightowler did not begin to run until Siebert, Gabrielson, and Vosburg were removed as governors in October 2008.

The Iowa Supreme Court has not adopted the adverse domination doctrine, but it has applied a discovery rule under which the limitations period does not begin *825 to run until the injured party has “actual or imputed knowledge of the facts that would support a cause of action.” K & W Elec., Inc. v. State, 712 N.W.2d 107, 116 (Iowa 2006) (quotations omitted). The adverse domination doctrine is a logical extension of the discovery rule in light of agency law principles. When the plaintiff is a corporation, it must learn of an injury to the corporation through its agents. But if the agent’s interests are adverse to the corporation, then the agent’s knowledge is not imputed to the corporation. Lease Resolution Corp. v. Larney,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michelle R. Skadburg v. Gary Gately and Whitfield and Eddy, PLC
911 N.W.2d 786 (Supreme Court of Iowa, 2018)
Skadburg v. Gately
Court of Appeals of Iowa, 2018
Antioch Co. Litigation Trust v. Lee Morgan
644 F. App'x 579 (Sixth Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
789 F.3d 821, 2015 U.S. App. LEXIS 10066, 2015 WL 3650379, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cedar-rapids-lodge-suites-llc-v-jfs-development-inc-ca8-2015.